Franken v. Carpenter

364 S.W.2d 15, 1963 Mo. App. LEXIS 598
CourtMissouri Court of Appeals
DecidedJanuary 15, 1963
DocketNo. 31019
StatusPublished
Cited by5 cases

This text of 364 S.W.2d 15 (Franken v. Carpenter) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franken v. Carpenter, 364 S.W.2d 15, 1963 Mo. App. LEXIS 598 (Mo. Ct. App. 1963).

Opinion

GEORGE P.-ADAMS, Special Judge.

Defendant-landowner appeals from an adverse -judgment for $4,640.00 and a mechanic’s lien against her land in favor of plaintiff-contractor, entered pursuant to a jury’s verdict.

The jury’s verdict and the judgment below did not dispose of a counterclaim filed by defendant. Even though neither of the parties has raised the point, we are obliged to determine sua sponte, whether we have appellate jurisdiction. Bennett v. Wood, Mo., 239 S.W.2d 325, 328(4); Collier et al. v. Smith et al., Mo.App., 292 S.W.2d 627, 631(5). Having concluded that the appeal is premature, only'such facts as are necessary for this determination will be detailed.

By a written contract, plaintiff agreed to construct a one story commercial building at Murphy, in Jefferson County, for defendant. The contract provided that the “job” was to be done in a “workmanlike manner” and in accordance with plans and specifications identified in the contract; that construction should be complete by June 15, 1960 and if not completed by said date “a penalty of twenty-five dollars ($25.00) per day shall be incurred by the Contractor thereafter, and total of said penalty deducted from the Contract Price”; and that final payment was to be made “upon completion and acceptance without reservation of.building by Mrs. D. Carpenter.”

After inclusion of some “extras” not in dispute on this appeal, plaintiff claimed a total of $15,040.00 upon which defendant paid $6,000.00 on May 17, and $4,000.00 on July 28.' On July 29, 1960, plaintiff filed his “mechanic’s lien” claiming a balance of $5,040.00.

The suit was tried under plaintiff’s second amended petition which was in two counts, one under the contract, and the second in quantum meruit. Both sought the recovery of $5,040.00 and a lien on defendant’s property.

Defendant filed an answer and counterclaim. In her answer, in addition to denying generally the allegations of Counts I and II of plaintiff’s petition, defendant also plead that plaintiff had been fully paid and had waived his lien.

By Count I of her counterclaim, defendant sought recovery of $10,812.00 based on claims that plaintiff failed to perform various phases of the construction in accordance with the contract and the plans and specifications. Included was $1,700.00 claimed due because of plaintiff’s failure to complete the building by June 15th.

By Count II of her counterclaim, defendant sought $1,000.00 actual and $5,000.-00 punitive damages, claiming plaintiff had waived his lien and by “maliciously” filing his notice of lien and the subsequent filing [17]*17of this suit, defendant was required to defend a “baseless suit”; was prevented from selling the real estate or obtaining a loan thereon; and the filing of the lien resulted in a cloud on the title to the real estate.

On May 16, 1961, the case proceeded to trial before a jury.

At the close of defendant’s evidence, plaintiff’s 'motion for a directed verdict on Count I of defendant’s counterclaim was overruled and his motion for a directed verdict on Count II of defendant’s counterclaim was sustained.

After rebuttal evidence by plaintiff, and at the close of all the evidence, defendant offered motions for directed verdicts, as follows:

“The Defendant at the close of all evidence moves the Court to direct a verdict for Defendant and against plaintiff on Plaintiff’s petition: For the reason that, under law, pleadings and the evidence there is no question for the Jury.”

and,

“At the close of all the evidence, Defendant moves for a directed verdict against the Plaintiff on his claim, and for the Defendant on her counterclaim.”

Both motions were denied.

While no point is made on the appeal as to the instructions (nor was any effective assignment relating thereto contained in the motion for new trial), it is appropriate to say that plaintiff’s theories were submitted in two instructions authorizing a recovery on quantum meruit.

By her instructions, the defendant submitted her right to the $25.00 per day penalty and her right to damages if the jury found that plaintiff had not performed according to the contract and had failed to perform certain specific phases of the construction. By another instruction, the jury was directed to find for defendant under Count I of plaintiff’s petition if they found that plaintiff “failed to construct the building in evidence substantially according to the said contract, plans and specifications.”

The jury returned the following verdict:

“We, the Jury in the above entitled cause find the issues in favor of the Plaintiff and against Defendant, Dorothy V. Carpenter and assess Plaintiff’s damages in the amount of $4,640.00.
“We further find Plaintiff is entitled to a mechanic’s lien against the property of Dorothy V. Carpenter in the amount of $4,640.00.”

Immediately following the foregoing verdict, there appears in the transcript another verdict, as follows:

“We, the Jury find the issues on the Defendant’s Count Two of the counterclaim in favor of the Plaintiff and against the Defendant.”

The latter verdict was signed by a different jury foreman than the former. It is reasonable to assume that the latter verdict was executed pursuant to the trial court’s direction following its sustention of plaintiff’s motion for a directed verdict on Count II of defendant’s counterclaim.

The trial court’s judgment concluded as follows:

“Whereupon the Court adopts the verdict of the jury as his verdict.
“It is therefore Considered, Ordered and Adjudged by the Court that the plaintiff recover of the defendant the sum of $4,640.00, and that plaintiff is entitled to a mechanic’s lien against the real estate described in plaintiff’s petition.”

Obviously the issues raised by Count I of defendant’s counterclaim have not been specifically disposed of by the jury’s verdict or the court’s judgment. Therefore, unless the verdict of the jury necessarily constitutes a finding against defendant on Count I of her counterclaim and such issue has been effectively disposed of, Commer[18]*18cial National Bank of Kansas City, Kansas v. White, Mo., 254 S.W.2d 605, 608(3), there has been no “final determination of the rights of the parties in the action” (Civil Rules 74.01, V.A.M.R.) and the appeal is premature. Collier et al. v. Smith et al., Mo.App., 292 S.W.2d 627, 629(1, 2), 630 (3); Bennett v. Wood, Mo., 239 S.W.2d 325, 327, 328(3-5).

To determine whether the verdict of the jury has effectively disposed of all issues raised by the pleadings and tendered under the instructions, it is essential that the “issues” be defined.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baumstark v. Jordan
540 S.W.2d 611 (Missouri Court of Appeals, 1976)
c.ed Gaines v. c.w.jones
486 F.2d 39 (Eighth Circuit, 1973)
Herbert & Brooner Construction Co. v. Golden
499 S.W.2d 541 (Missouri Court of Appeals, 1973)
Custom Control Manufacturer, Inc. v. Matney & Co.
480 S.W.2d 321 (Missouri Court of Appeals, 1972)
Corrigan Co. Mechanical Contractors, Inc. v. Fleischer
423 S.W.2d 209 (Missouri Court of Appeals, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
364 S.W.2d 15, 1963 Mo. App. LEXIS 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franken-v-carpenter-moctapp-1963.