Christopher & Simpson Architectural Iron & Foundry Co. v. E. A. Steininger Construction Co.

205 S.W. 278, 200 Mo. App. 33, 1918 Mo. App. LEXIS 131
CourtMissouri Court of Appeals
DecidedJuly 12, 1918
StatusPublished
Cited by12 cases

This text of 205 S.W. 278 (Christopher & Simpson Architectural Iron & Foundry Co. v. E. A. Steininger Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christopher & Simpson Architectural Iron & Foundry Co. v. E. A. Steininger Construction Co., 205 S.W. 278, 200 Mo. App. 33, 1918 Mo. App. LEXIS 131 (Mo. Ct. App. 1918).

Opinion

ALLEN, J.

— This is an action, instituted May 15, 1907, by a sub-contractor, Christopher & Simpson Architectural Iron & Foundry Company, against the general contractor, E. A. Steininger Construction Company, and the owner, Mound City' Ice & Cold Storage Company, for a balance alleged to be due plaintiff from the defendant contractor for the reasonable value of labor and materials furnished in the erection of a certain building, and for a lien therefor [39]*39against the property. The parties to the record are all corporations. The issues arise upon the petition, the first amended answer of the defendant owner, the third amended answer and counterclaims of the defendant general contractor, and a reply including answers to the counterclaims.

The petition avers, in substance, that on or about July 26, 1906, defendant E. A. Steininger Construction Company (hereinafter termed the contractor) entered into a contract with its co-defendant, the Mound City Ice & Cold Storage Company (hereinafter referred to as the owner), wherein the contractor agreed to erect, an “ice storage house” for its co-defendants on certain described property owned by the latter in the city of St. Louis; that thereafter, at the request of the contractor, plaintiff furnished the materials and performed the work and labor in installing the iron and steel work required in the erection of such building, as described in a “bill of particulars,” aggregating $8646.48. It is averred that the deliveries of the material were completed on October 8, 1906, and the installation thereof completed on October 22', 1906, excepting certain work done upon a door, required to be done under the contract, which was completed on November 14, 1906; that said work and labor were reasonably - worth the prices charged therefore and actually entered into the building, and that the claim accrued and became due November 14, 1906. It is further averred, among other things, that on February 11, 1907, plaintiff gave the defendant owner written notice of its claim and its intention to file a lien therefor, and that the lien account sued upon was filed on February 21, 1907. Giving credit for certain payments made plaintiff by the defendant contractor, on account, one of which is alleged to háve been made after the filing of the lien account, viz., on March 15, 1907, and alleging that on the last mentioned date demand was made for the payment of the balance due; to-wit, $3047.68, and judgment is prayed against the defendant contractor for such sum, with interest from [40]*40March. 15, 1907, and that the same be declared a lien against the property.

The amended answer of the defendant owner admits that on July 25, 1906, it entered into a contract with its co-defendant whereby the latter agreed to erect the building in question, and that “contemporaneously with the making of said contract” the defendant contractor entered into a contract with plaintiff whereby plaintiff agreed to install the iron and steel work required in the erection thereof, in the manner and within the time required by the contract between the defendants, and as shown by the plans and specifications of the architect. Then follows a general denial of all the allegations of the petition not specifically admitted.

The third amended answer of the defendant contractor admits that on or about July 26, 1906, this defendant entered into a contract with its co-defendant herein, by which (this defendant agreed to erect the ice storage house mentioned. It is then averred that by said contract this defendant bound itself to have two “sections” of said ice storage house under roof and in such condition that the owner might install the refrigerating piping and do the insulation within fifty (which should be “fifty-five”) working days from the date of the contract, and agreed to have the remainder of the building under roof and ready for like purposes within sixty-five working days from the date of the contract, and to have the entire building completed in all details within eighty working days .from the date of the contract; and that this defendant agreed that if it failed to complete the building “to the various stages” mentioned it would pay its co-defendant, as liquidated damages, $100 per day for each day beyond the time set for such completion.

And by its answer this defendant “further admits and states” that on July 26, 1906, it entered into a written contract with plaintiff, whereby the latter agreed to furnish and install the iron and steel work required in the erection and completion of the ice [41]*41storage bouse, arid to complete and “have set in position” all of the same within fifty days from July 26, 1906; and that plaintiff agreed that its said agreement and undertaking should be and become a part and parcel of the contract between this defendant, as general contractor, and its co-defendant as owner. And it is averred that plaintiff agreed to commence at once upon the work to be done by it .under its contract, and to complete the same in such time as to cause no delays to this defendant, the general contractor, or any other sub-contractor on the building; and agreed that any damage or liability for which this defendant, as general contractor, should “be held or become liable for in consequence of the neglect” of plaintiff to install and complete the work to be performed by it within fifty days from the date of its ■ contract should be deducted from the contract price of $8600 which plaintiff was to receive for performing and completing its contract. And this defendant denies “that the plaintiff performed its said contract, or did all the work, or furnished all the materials set out in the petition, or did said work or furnished said materials at the time or date set out in the petition,” and denies each and every allegation of the petition not specifically admitted.

Further answering, this defendant states that plaintiff is not entitled to recover for the work, labor and materials sued for in this action, for the reason that plaintiff breached its contract by failing to complete its work within the time limited therein, and because by the terms of its contract any loss or damage resulting to this defendant from such delay is to be deducted from the amount to which plaintiff would otherwise be entitled. It is averred that work which this defendant was required to do in order to complete the building could not be done until the iron and steel work was installed; and that although the building was ready to receive plaintiff’s work, and plaintiff was notified thereof, plaintiff did not commence its work thereupon until forty-five days after July 26, [42]*421906, and did not install the iron and steel work in time to enable this defendant to complete the building in its various stages within the time limit fixed by its contract with its co-defendant; that -although this defendant repeatedly notified and. urged plaintiff to observe the terms of its contract in this respect, plaintiff failed “for more than forty-five calendar days, or more than thirty working days after the expiration of the .fifty days from July 26, 1906,” to install and complete the iron and steel work on the building, whereby plaintiff became liable to pay the damages thereby sustained by this defendant, as stipulated and fixed in the contract between the latter and the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.H. Berra Construction Co. v. City of Washington
510 S.W.3d 871 (Missouri Court of Appeals, 2017)
Gee v. Payne
939 S.W.2d 383 (Missouri Court of Appeals, 1997)
c.ed Gaines v. c.w.jones
486 F.2d 39 (Eighth Circuit, 1973)
Trout's Investments, Inc. v. Davis
482 S.W.2d 510 (Missouri Court of Appeals, 1972)
Mid-West Engineering & Construction Co. v. Campagna
421 S.W.2d 229 (Supreme Court of Missouri, 1967)
Franken v. Carpenter
364 S.W.2d 15 (Missouri Court of Appeals, 1963)
Stubblefield v. Montgomery Ward & Co.
98 P.2d 14 (Oregon Supreme Court, 1940)
Leach v. Bopp
12 S.W.2d 512 (Missouri Court of Appeals, 1929)
Wright v. King
292 S.W. 602 (Court of Appeals of Texas, 1927)
Adam Groth & Co. v. Goss & Guise
232 Ill. App. 450 (Appellate Court of Illinois, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
205 S.W. 278, 200 Mo. App. 33, 1918 Mo. App. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christopher-simpson-architectural-iron-foundry-co-v-e-a-steininger-moctapp-1918.