John Hutchinson Manufacturing Co. v. Pinch

51 N.W. 930, 91 Mich. 156, 1892 Mich. LEXIS 722
CourtMichigan Supreme Court
DecidedApril 8, 1892
StatusPublished
Cited by17 cases

This text of 51 N.W. 930 (John Hutchinson Manufacturing Co. v. Pinch) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Hutchinson Manufacturing Co. v. Pinch, 51 N.W. 930, 91 Mich. 156, 1892 Mich. LEXIS 722 (Mich. 1892).

Opinion

Morse, C. J.

The plaintiff sued defendant for machinery and repairs furnished for the latter’s flouring-mill. The defendant claimed that under the agreement, the plaintiff promised to put in the machinery and complete the repairs in a good and workman-like manner within 10 days after the work was commenced, which work should begin “ in a few days or a short time ” after the date of the agreement; that plaintiff did not commence the work as soon as agreed, did not do it in a. workman-like- manner, and did not complete it within four weeks after the work was begun; that by reason of' improper material, and the unskillful manner in which, the work was done, much of the flour made by such mill was unfit for custom and merchant flour;” that said mill was kept closed 50 days, and that the mill, as-completed by plaintiff, is in an improper condition for-running and properly performing the work of a first-class-full roller process custom and merchant flouring-mill, as-plaintiff agreed it should, and that it takes more power to operate it.

On the trial the defendant was asked:

“Q. Mr. Pinch, how much were you damaged by reason-of the mill lying idle for the excess of 10 days, until the-time it was finished? In other words, it laid still how many days more than the 10 days?
“Mr. Ferguson: I object.
“The Court: That brings up the question. The witness, I think, can’t state how many dollars and cents he has been damaged. He can state how he was damaged, and show the circumstances that will enable the jury to-judge. There is another, question involved in it, and perhaps it had better be discussed together. I suppose-you are getting at the profits of the mill?
“Mr. Shriner: Tes, sir.”

Mr. Corbin, for plaintiff, contended that the profits-were too indefinite, and the question was excluded.

Counsel for defendant then offered as follows:

[158]*158“Mr. Shriner: Now, if the court please, we offer to ■show that after Mr. Crandall and his men worked on the mill 10 days, Mr. Pinch notified Mr. Hutchinson that the time had expired in which he was to have the mill completed; that the mill was overstocked with grain; that he was losing by reason of the delay every day; and that these men went on with that mill until the 3d day of March; and that, by reason of that failure to fulfill their •contract, Mr. Pinch suffered large damages, to the .amount of $500.
The Court: This offer may be considered as preceding ■the former ruling.
“Q. About how many grists were in your mill at the ■time they had worked 10 days upon their contract, on the repairing of the mill? * * *
“Q. What was the difference, Mr. Pinch, of the value ■of flour per barrel after the mill ■ was finally completed ■in perfect order, than what it was before they commenced fixing the mill?”

Both these questions were objected to and ruled out. ■He was also asked:

“What, in your opinion, was the use of the mill worth for those 11 days? ” ■

„ The court said this was an indirect way of •asking witness how much he could have made out of the mill, and excluded the question. Other questions were •asked in different ways, but all to the same import, and were not allowed to be answered. It was also attempted ~to show the value of defendant’s time lost during the time over 10 days in which the mill could not be run, but the circuit judge was of the opinion that he could-not recover for such lost time. Counsel for defendant •then made the following offer:

“ I offer to show by - Pinch that his business was injured a large amount by reason of the manner in which the ' contract was performed, .and that he lost the use of the mill, and the profits of the mill, for a long time, to wit, 30 days, by .reason of the manner in which the contract was performed. [159]*159I desire to show what the profits were, and to show in '•every way that he was injured. I desire to show by him how he was injured.
“The Court: How do you propose to show that he was injured?
“ Counsel for Defendant: By the loss of his time; by the injury of the flour; by the amount he had to pay out in the place of it; by the loss of time; by the loss of ■customers; and by the loss of the reputation of the mill, because of its having been pronounced finished by those parties, when it was improperly finished.
Counsel for Plaintiff: It is objected to as immaterial and irrelevant. Not a proper way to prove the measure •of damages. (Which objection was by the court then and there sustained.”)

The court instructed the jury that no damages could be.awarded to the defendant for the profits lost by reason of the mill being idle, even if they found that the agreement was that the mill should be put in good running order in 10 days.

This was a custom, as well as a manufacturing, flouring-mill. The prospective profits of such a mill would certainly be too speculative to be shown as damages. Howard v. Manufacturing Co., 139 U. S. 199 (11 Sup. Ct. Rep. 500); Pennypacker v. Jones, 106 Penn. St. 237; Abbott v. Gatch, 13 Md. 314; Rogers v. Bemus, 69 Pa. St. 432; Winne v. Kelley, 34 Iowa, 339; Allis v. McLean, 48 Mich. 428; McKinnon v. McKwen, Id. 106; Maltby v. Plummer, 71 Id. 579; Petrie v. Lane, 58 Id. 527. The defendant relies upon Leonard v. Beaudry, 68 Mich. 312, 80 Id. 163, in support' of his contention that he was entitled to ¡show the profits that he might have made in the mill if it had been finished within ten days. But in Leonard v. Beaudry, supra, and in Atkinson v. Morse, 63 Mich. 276, there was a breach of contract, where the difference between the cost of doing the work to be performed and the contract price would be the measure of damages. The profits in such a case we held could be ascertained [160]*160with reasonable certainty. This case seems to fall within-the other line of cases, where the uncertain and speculative profits of a mill from day to day are endeavored to be measured; where there is no certain amount of work contracted to be done at a certain or fixed price for the work, but where the mill-owner must depend upon how much custom he may happen to have, and many other contingencies, as pointed out in the cases above cited.

But upon examination of the authorities, and upon principle, I am satisfied that the defendant was entitled to show in reduction of plaintiffs claim the value of the use of the mill while it was compelled to lie idle by the failure of plaintiff to complete the contract within the time specified. A denial of this right would be rank injustice, and leave the defendant remediless for his loss, and at the same time compel him to pay the full value-of the machinery and repairs to the plaintiff, the same-as if the work had been done within the time agreed upon.

“As a general rule, the expected profits of a. business cannot be proved, and therefore cannot be recovered, They might have been made, and they might not..

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mississippi Power Co. v. Harrison
152 So. 2d 892 (Mississippi Supreme Court, 1963)
Gates Rubber Co. v. Kold-Hold Manufacturing Co.
41 N.W.2d 324 (Michigan Supreme Court, 1950)
Lutz v. Hill-Diesel Engine Co.
237 N.W. 546 (Michigan Supreme Court, 1931)
Mazzotta v. Bornstein
133 A. 677 (Supreme Court of Connecticut, 1926)
Southern Iron Equipment Co. v. Holmes L. Co.
51 So. 531 (Supreme Court of Alabama, 1909)
Quay v. Duluth, South Shore & Atlantic Railway Co.
116 N.W. 1101 (Michigan Supreme Court, 1908)
Dowagiac Manufacturing Co. v. Corbit
127 Mich. 473 (Michigan Supreme Court, 1901)
Port Blakely Mill Co. v. Sharkey
102 F. 259 (Ninth Circuit, 1900)
Levinski v. Middlesex Banking Co.
92 F. 449 (Fifth Circuit, 1899)
Stevens v. Yale
72 N.W. 5 (Michigan Supreme Court, 1897)
Burruss v. Hines
26 S.E. 875 (Supreme Court of Virginia, 1897)
Covode v. Principaal
68 N.W. 987 (Michigan Supreme Court, 1896)
John Hutchison Manufacturing Co. v. Pinch
107 Mich. 12 (Michigan Supreme Court, 1895)
Fell v. Newberry
64 N.W. 474 (Michigan Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
51 N.W. 930, 91 Mich. 156, 1892 Mich. LEXIS 722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-hutchinson-manufacturing-co-v-pinch-mich-1892.