Leonard v. Beaudry

36 N.W. 88, 68 Mich. 312, 1888 Mich. LEXIS 926
CourtMichigan Supreme Court
DecidedJanuary 26, 1888
StatusPublished
Cited by23 cases

This text of 36 N.W. 88 (Leonard v. Beaudry) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leonard v. Beaudry, 36 N.W. 88, 68 Mich. 312, 1888 Mich. LEXIS 926 (Mich. 1888).

Opinion

Champlin, J.

This action was brought to recover damages for a breach of contract. The declaration alleged, by way of inducement, that plaintiff was the owner of a steam saw-mill in the township of Laketown, which was fitted with a band-saw and all the appliances necessary for its proper operation, well equipped, in good working condition, and capable of cutting 30,000 feet of pine lumber per day.

The plaintiff then alleges that on the first day of March, 1886, the plaintiff made and entered into a contract with defendants, whereby they agreed to furnish and deliver at her mill in the spring of 1886, as soon as her mill was ready for operation, 1,000,000 feet of pine saw-logs suitable for sawing on band-saws, to be sawed into lumber on said band-saw for defendants, and to pay plaintiff for sawing the same three dollars for each thousand feet for merchantable and short lumber, and two dollars a thousand feet for culls; all of said logs to be so delivered prior to the first day of July, 1886.

That, in consideration thereof, the plaintiff promised and agreed to and with the said defendants to receive said logs, and to manufacture the same into lumber upon said band-saw as soon as delivered as aforesaid, according to the capacity of said saw.

[314]*314That the plaintiff’s mill was, to wit, on the tenth day of May, 1886, ready for operation, whereof defendants had due notice; and the plaintiff was then and there, during the sawing season of 1886, ready and willing to have accepted said logs, and to have sawed them on said band-saw, whereof said defendants had notice; yet the defendants did not nor would at said time, nor during said sawing season of 1886, or at any time since, deliver, or cause to be delivered, said logs, or any part thereof, or any other logs whatsoever, but, on the contrary, wholly refused so to do, and in consequence thereof the plaintiff has been deprived of sundry great gains and profits which she might and would have acquired to herself by sawing said logs as aforesaid.

That after the making of said contract she made and entered into a contract with H. C. Akeley for the sawing and manufacture of logs into lumber on said band-saw during the remainder of said sawing season of 1886 not needed by her for the performance of said contract made by her with the defendants as aforesaid, and the logs delivered to her by said Akeley, together with those which said defendants had agreed to furnish by their said contrast, were sufficient to stock said mill, and to keep said band-saw in full operation, during the whole of said sawing season of 1886 ; and that the plaintiff, relying on said contract and agreement of defendants, and for the purpose of holding and keeping herself ready and able to perform said contract on her part, declined and refused to enter into other contracts for the sawing of logs on said band-saw during said sawing season for said year, which were, after the making of said contract and prior to the opening of the sawing season for said year, offered and tendered to her, and by means of which she would have been able to run and operate said band-saw continuously during said sawing season of 1886 to its full capacity, at a great profit.

That after the refusal of said defendants to furnish and [315]*315deliver said logs as aforesaid, and as soon as she learned that the said defendants would not furnish them, she made diligent endeavors and exertions to obtain other suitable logs for sawing on band-saws, to cut and manufacture into lumber at her said mill on said band-saw, and that she was unable to obtain them; and that by reason of defendants’ failure and refusal to furnish and deliver said logs as aforesaid, and her inability to obtain other logs to be cut iu their place, said plaintiff was obliged to and did run said mill and operate said saw at a loss in cutting inferior logs, not suitable to be cut upon a band-saw, but which were the best logs she could obtain for that purpose for a long time, to wit, three-weeks and upwards; and for another long space of time, to wit, two weeks and upwards, said mill was compelled to lie idle, and said plaintiff was compelled, during said time, to pay out large sums of money as wages to her employés- while waiting for said logs to be delivered by defendants, and while the mill was lying idle, — all to plaintiff’s damage $3,000.

A bill of particulars of plaintiff’s demand was filed, as follows:

1886.
“ August 1. Actual loss sustained by plaintiff in running mill and cutting logs inferior to those to be furnished by defendants..................... 1500.00
“ August 1. Loss of actual profits plaintiff would have made for 8 weeks while cutting inferior logs 500.00
“ August 1. Loss of actual profits plaintiff would have made while mill was lying idle by reason of defendants’ failure to furnish logs............... 500.00
“August 1. Cash paid by plaintiff for employes’ wages while mill was lying idle by reason of defendants’ failure to furnish logs............... 500.00
“ August 1. Loss of actual profits plaintiff would have received in manufacturing lumber from one million feet (board measure) of logs contracted to be delivered to her by said defendants for sawing, had said logs been so delivered in accordance with the agreement of said defendants, at $1.50 per M.......................................... 1,500.00
“ Interest at 7 per cent, on each item.
Da:ed April 14, 1887.”

[316]*316The defendants pleaded the general issue.

The cause was tried at the Muskegon circuit before Hon. F. J. Russell, circuit judge, and a jury, at which time the following proceedings were had: After the jury was impaneled, the counsel for the plaintiff made an opening statement to them as follows:

Gentlemen of the Jury: 'The'plaintiff, by her proof, will endeavor to show that during the spring of 1886, and before the commencement of the sawing season of that year, the plaintiff, through her agent and representative on the one side, and the defendants on the other, entered into a contract, by the terms of which the defendants agreed to deliver at the plaintiff’s mill, which is situated on the north side of Muskegon lake, one million feet of logs, to be sawed by the plaintiff by what is known as a band-saw; that the plaintiff was to receive the logs, and manufacture them into lumber, for which the defendants were to pay three dollars ($3.00) per thousand feet for the merchantable and short lumber made from the logs, and two dollars ' ($2.00) per thousand feet for the culls.
That at the timé they were negotiating to make this contract, and at the time it was made, it was known and understood by the parties to it that, in order for the plaintiff to prepare to do this work, — to receive and saw these logs, — it would be necessary for her to arrange to have the sawing of a quantity of her own logs, with which her mill was supplied, done by other parties; and that, soon after entering into this agreement with the defendants, the plaintiff had a million feet or more of her own logs sawed elsewhere; that the plaintiff was all the time willing and ready to perform the contract on her part, but that the defendants neglected to perform it on their part, and never delivered any logs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fister v. Henschel
152 N.W.2d 555 (Michigan Court of Appeals, 1999)
H. M. Seldon Co. v. Carson
185 N.W.2d 842 (Michigan Court of Appeals, 1971)
Obremski v. Dworzanin
21 N.W.2d 828 (Michigan Supreme Court, 1946)
In Re Griffith's Estate
291 N.W. 21 (Michigan Supreme Court, 1940)
Rushford-Surine v. Grand Trunk Railway Co.
214 N.W. 168 (Michigan Supreme Court, 1927)
Federal Bond & Mortgage Co. v. Burstein
192 N.W. 549 (Michigan Supreme Court, 1923)
Fiegel v. First Nat. Bank of Kingfisher
1923 OK 112 (Supreme Court of Oklahoma, 1923)
Cannon v. Oregon Moline Plow Co.
197 P. 39 (Washington Supreme Court, 1921)
Detroit Fireproofing Tile Co. v. Vinton Co.
157 N.W. 8 (Michigan Supreme Court, 1916)
Quay v. Duluth, South Shore & Atlantic Railway Co.
116 N.W. 1101 (Michigan Supreme Court, 1908)
Lafitte v. Vanderwark
41 Colo. 270 (Supreme Court of Colorado, 1907)
Emerson v. Pacific Coast & Norway Packing Co.
104 N.W. 573 (Supreme Court of Minnesota, 1905)
Martin Emerich Outfitting Co. v. Siegel, Cooper & Co.
108 Ill. App. 364 (Appellate Court of Illinois, 1903)
Hichhorn, Mack & Co. v. Bradley
117 Iowa 130 (Supreme Court of Iowa, 1902)
Industrial Works v. Mitchell
72 N.W. 25 (Michigan Supreme Court, 1897)
Barrett v. Grand Rapids Veneer Works
67 N.W. 976 (Michigan Supreme Court, 1896)
Watson v. Kirby & Sons
112 Ala. 436 (Supreme Court of Alabama, 1895)
Fell v. Newberry
64 N.W. 474 (Michigan Supreme Court, 1895)
Cranmer v. Kohn
64 N.W. 125 (South Dakota Supreme Court, 1895)
Greenwood v. Davis
64 N.W. 26 (Michigan Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
36 N.W. 88, 68 Mich. 312, 1888 Mich. LEXIS 926, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leonard-v-beaudry-mich-1888.