Mazzotta v. Bornstein

133 A. 677, 104 Conn. 430, 1926 Conn. LEXIS 112
CourtSupreme Court of Connecticut
DecidedMay 29, 1926
StatusPublished
Cited by21 cases

This text of 133 A. 677 (Mazzotta v. Bornstein) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mazzotta v. Bornstein, 133 A. 677, 104 Conn. 430, 1926 Conn. LEXIS 112 (Colo. 1926).

Opinion

Maltbie, J.

The plaintiff is seeking the foreclosure of a mechanic’s lien filed by him to secure a balance he claims under a contract for the construction of a two-story factory building for the defendants. The trial court, in determining the amount due, refused to include a charge in addition to the contract price, made by the plaintiff by reason of a change in the kind of elevator to be installed; and it made certain deductions on account of damages suffered by the defendants through the plaintiff’s alleged failure fully to perform his contractual obligations. Both parties have appealed, claiming errors in the rulings of the trial court in regard to these items.

During the progress of the work, the defendants decided that they would prefer to have installed an electric elevator in place of the hydraulic elevator specified, and the plaintiff agreed to install one of “the best type,” with a capacity of two tons, at an additional cost of $300, and received from the defendants a written order to do so. The plaintiff thereafter submitted to defendants’ architect specifications for a chain driven two-ton electric elevator which he refused to approve. After some discussion as to the type of elevator referred to in the order, the defendants notified the plaintiff to install a direct connection one-ton electric eleva *434 tor, stating that there had been a misunderstanding as to the matter and that, as the cost of the one-ton elevator was not more than that of the hydraulic elevator specified in the contract, there would be no change in the contract price on account of the substitution. The plaintiff installed a one-ton direct connection elevator, and notified the defendants that he would expect to be paid the difference between the cost to him of that elevator and the amount he would have had to pay for a two-ton chain driven electric elevator, that is, $300. In the original bill of particulars of “extras” filed by the plaintiff he included an item as follows: “For installing electric elevator in place of hydraulic elevator, $300”; and the defendants in their answer admitted the correctness of this bill of particulars. Later he filed an amendment seeking to recover an additional sum of $300 on account of the change in the kind of elevator installed. Plaintiff’s agreement to install a two-ton electric elevator of “the best type,” and the defendants’ order to him to install an electric elevator without specifying the type or capacity, were, in view of the evident diversity in the way in which such elevators are constructed, too indefinite to impose any obligation upon the plaintiff. They furnish no basis for the plaintiff’s claim that the later notice from the defendants and the plaintiff’s compliance with it, superimposed one agreed alteration of the contract upon another. The plaintiff might have regarded that notice as a distinct and separate direction for an alteration of the contract. But by inserting in his bill of particulars the item of $300 for installing the electric elevator, he chose to regard that notice as supplementing and making definite the earlier attempted agreement and order, and the defendants, by admitting the correctness of the item, have assented to that construction of the situation. There is no *435 ground for the recovery by the plaintiff of any additional sums.

The trial court made an allowance to the defendants because the plaintiff used tile instead of cast iron pipe for certain drains under the floor of the building to carry off the water from the rain conductors leading from the roof. Depending, as it does, solely upon the construction of the plans and specifications for the building, the question presented is one of law, reviewable by us. Quinby Co. v. Sheffield, 84 Conn. 177, 188, 79 Atl. 179. Neither the plans nor the specifications expressly designated the materials of which these drains were to be made. The latter, under the heading “Mason Work,” required a line of tile drain from the street sewer to the building for the soil pipe and conductor drains, “to be 6" for the main line and 5" for the branches”; and under the head of “Plumbing,” they contained the following: “There will be a complete plumbing system installed to conform to the local and state ordinances and rules. Run a line of cast iron ex. heavy pipe from 5' outside of building in and up to 2' above the roof.” The main portion of the building was rectangular, but on one side a short wing jutted out, in which were to be the toilets and the boiler-room. The plans of the main building throw little, if any, light upon the particular issue being considered, but the detail drawings of the wing are illuminating. They show that the six-inch drain from the street sewer was to run nearly to its outer wall; that it was to continue into the area of the wing as a five-inch drain, the material not being specified; that about six feet inside the outer wall, the drain divided, one branch, marked as a four-inch cast iron pipe, running to the toilets, and the other continuing on beyond the wall or the wing, marked where the lines of the drawing cease, “5" tile”; and that into this latter branch *436 ran the conductor which drained the roof of the toilet and boiler-rooms. A consideration of this portion of the plans makes certain the fact, suggested in the very terms of the specification, that the requirement of a cast iron pipe under the head of “plumbing” referred to the soil and vent pipe connected with the toilets, not to the drains from the rain-water conductors. So a comparison of these drawings with the specifications under the heading “Mason Work,” discloses quite as convincingly an intent that the drains from the rainwater conductors in the main building were to be of tile; the provision in the specifications as to the “branches” from the main drain would otherwise be meaningless; the rain-water conductor from the roof of the wing ran into a drain beneath the floor of the boiler-room clearly designated as tile; the extension of this drain beyond the wing could only, under the plans, be intended to illustrate the connection to be made with the other rain-water conductors; and here, the only place on the plans where the underground drains appear at all, the material of which they were to be constructed was designated as tile. The trial court was in error in construing the plans and specifications as requiring that these drains be constructed of cast iron.

The largest item in dispute is a deduction made by the trial court because of the failure of the plaintiff to complete the work within the time fixed by the contract. The contract contained this provision: “The contractor shall complete the several portions, and the whole of.the work comprehended in this agreement before the expiration of the eighty working days commencing with and next succeeding the fifth day of November, 1923.” The plaintiff contends that this provision was not of the essence of the contract and hence his failure to comply with it did not entitle the defend *437 ants to any damages they may have suffered. It is not necessary to decide whether, accurately speaking, the time of performance fixed was of the essence of the contract, for whether it was so or not, the defendants, in the absence of circumstances of excuse or waiver, are entitled to recover any damages they have suffered by reason of the plaintiff’s breach of his undertaking in this regard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Banks Building Co. v. Malanga Family Real Estate Holding, LLC
926 A.2d 1 (Connecticut Appellate Court, 2007)
Farrelly Co. v. Devito Bros. Inc., No. Cv-89-0356545s (Jun. 21, 1990)
1990 Conn. Super. Ct. 140 (Connecticut Superior Court, 1990)
Dorchester Development, Inc. v. Burk
439 So. 2d 1032 (District Court of Appeal of Florida, 1983)
Ruscito v. F-Dyne Electronics Co.
411 A.2d 1371 (Supreme Court of Connecticut, 1979)
Thames Shipyard & Repair Co. v. Willametz
428 A.2d 1143 (Connecticut Superior Court, 1978)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Leo Foundation, Inc. v. Kiernan
240 A.2d 218 (Connecticut Appellate Court, 1967)
Maier v. Arsenault
100 A.2d 403 (Supreme Court of Connecticut, 1953)
M. Shapiro & Son Construction Co. v. Battaglia
83 A.2d 204 (Supreme Court of Connecticut, 1951)
Campbell v. Rockefeller
59 A.2d 524 (Supreme Court of Connecticut, 1948)
Lovejoy v. Town of Darien
41 A.2d 98 (Supreme Court of Connecticut, 1945)
Lombardi v. Laudati
200 A. 1019 (Supreme Court of Connecticut, 1938)
Shaughnessy v. Morrison
165 A. 553 (Supreme Court of Connecticut, 1933)
Silfvast v. Asplund
20 P.2d 631 (Montana Supreme Court, 1933)
W. G. Maltby, Inc. v. Associated Realty Co.
158 A. 548 (Supreme Court of Connecticut, 1932)
Gray v. Greenblatt
155 A. 707 (Supreme Court of Connecticut, 1931)
Colonial Trust Co. v. Joseph Hilton, Inc.
149 A. 513 (Supreme Court of Connecticut, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
133 A. 677, 104 Conn. 430, 1926 Conn. LEXIS 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mazzotta-v-bornstein-conn-1926.