Griffin v. . Colver

16 N.Y. 489
CourtNew York Court of Appeals
DecidedMarch 5, 1858
StatusPublished
Cited by261 cases

This text of 16 N.Y. 489 (Griffin v. . Colver) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffin v. . Colver, 16 N.Y. 489 (N.Y. 1858).

Opinion

Selden, J.

The only point made "by the appellants is-that in estimating their damages on account of the plaintiff’s failure to furnish the engine by the time specified in the contract, they should have been allowed what the proof showed they .might have earned by the use of such engine, together with their other machinery, during the time lost by the delay. This claim was objected to, and *483 rejected upon the trial as coming within the rule which precludes the allowance of profits, by way of damages, for the breach of an executory contract.

To determine whether this rule was correctly applied by the referee, it is necessary to recur to the reason upon which it is founded. It is not a primary rule, but is a mere deduction from that more general and fundamental rule which requires that the damages claimed should in all cases be shown, by clear and satisfactory evidence, to have been actually sustained. It is a well established rule of the common law that the damages to be recovered for a breach of contract must be shown with certainty, and not left to speculation or conjecture ; and it is under this rule that profits are excluded from the estimate of damages in such cases, and not because there is anything in their nature which should per se prevent their allowance. Profits which would certainly have been realized but for the defendant’s default are recoverable; those which are speculative or contingent are not.

Hence, in an action for the breach of a contract to transport goods, the difference between the price, at the point where the goods are and that to which they were to be transported, is taken as the measure of damages; and in an action against a vendor for not delivering the chattels sold, the vendee is allowed the market price upon the day fixed for the delivery. Although this, in both cases, amounts to an allowance of profits, yet, as those profits do not depend upon any contingency, their recovery is permitted. It is regarded as certain that the goods would have been worth the established market price, at the place and on the day when and where they should have been delivered.

On the other hand, in cases of illegal capture, or of the insurance of goods lost at sea, there can be no recovery for the- probable loss of profits at the port of destination. The principal reason for the difference between these cases and that of the failure to transport goods upon land is, that in *484 the latter case the time when the goods should have been delivered, and consequently that when the market price is to be taken, can be ascertained with reasonable certainty; while in the former the fluctuation of the markets and the contingencies affecting the length of the voyage render every calculation of profits speculative and unsafe,

There is also an additional reason, viz., the difficulty of obtaining reliable evidence as to the state of the markets in foreign ports; that these are the true reasons is shown by the language of Mr. Justice Stout, in the case of the Schooner Lively (1 Gallis., 315), which was a case of illegal capture. He says: “ Independent, however, of all authority, I am satisfied upon principle that an allowance of damages, upon the basis of a calculation of profits, is inadmissible. The rule would be in the highest degree unfavorable to the interests of the community. The subject would be involved in utter uncertainty. The" calculation would proceed upon contingencies, and would require a knowledge of foreign markets to an exactness in point of time and value which would sometimes present embarrassing obstacles. Much would depend upon the length of the voyage, and the season of the arrival; much upon the vigilance and activity of the master, and much upon the momentary demand. After all, it would be a calculation upon conjectures and not upon facts.”

Similar language is used in the cases of the Amiable " Nancy (3 Wheat., 546) and A’Amistad de Rues (5 Wheat., : 385). Indeed, it is clear that whenever profits are rejected as an item of damages, it is because they are subject to too many contingences, and are too dependent upon the fluctuations of markets and the chances of business, to constitute a safe criterion for an estimate of damages. This is to be : inferred from the cases in our own courts. The decision in the case of Blanchard v. Ely (21 Wend., 342) must have proceeded upon this ground, and can, as I apprehend, be supported upon no other. It is true that Judge Cowen, in *485 giving his opinion, quotes from Pothier the following rule of the civil law, viz.: “ In general, the parties are deemed to have contemplated only the damages and injury which the creditor might suffer from the non-performance of the obligations in respect to the particular thing which is the object of it, and not such as may have been accidentally occasioned thereby in respect to» his own (other) affairs.” But this rule had no application to the case then before the court. It applies only to cases where, by reason of special circumstances having no necessary connection with the contract broken, damages are sustained which would not ordinarily or naturally flow from such breach : as where a party is prevented by the breach of one contract from availing himself of some other collateral and independent contract entered into with other parties, or from performing some act in relation to his own business not necessarily connected with the agreement. An instance of the latter kind is where a Canon of the church, by reason Of the non delivery of a horse pursuant to agreement, was prevented from arriving at his residence in time to collect his tithes.

In 'such cases the damages sustained are disallowed, not because they are uncertain, nor because they are merely consequential or remote, but because they cannot be fairly considered as having been within the contemplation of the parties at the time of entering into the contract. Hence the objection is removed, if it is shown that the contract was entered into for the express purpose of enabling the party to fulfill his collateral agreement, or perform the act supposed. (Sedg. on Dam., ch. 3.)

In Blanchard v. Ely the damages claimed consisted in the loss of the use of the very article which the plaintiff had agreed to construct; and were, therefore,- in the plainest sense, the direct and proximate result of the breach alleged. Moreover, that use was contemplated by the parties in entering into the contract, and constituted the object for which the steamboat was built. It is clear, therefore, that *486 the rule of Pothiek had nothing to do with the case. Those damages must then have been disallowed, because they consisted of profits depending, not, as in the case of a contract to transport goods, upon a mere question of market value, but upon the fluctuations of travel and of trade, and many other contingencies. The citation, by Judge Cowen, of the maritime cases to which I have referred, tends to confirm this view.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Jersey Carpenters Health Fund v. Philip Morris, Inc.
17 F. Supp. 2d 324 (D. New Jersey, 1998)
Certain-Teed Products Corp. v. Goslee Roofing & Sheet Metal, Inc.
339 A.2d 302 (Court of Special Appeals of Maryland, 1975)
Steitz v. Gifford
19 N.E.2d 661 (New York Court of Appeals, 1939)
Adrian v. Rabinowitz
186 A. 29 (Supreme Court of New Jersey, 1936)
Furst & Thomas v. Davis
147 S.E. 654 (Supreme Court of South Carolina, 1929)
Tague Holding Corp. v. Harris
165 N.E. 834 (New York Court of Appeals, 1929)
Western Union Telegraph Co. v. Trinidad Bean & Elevator Co.
267 P. 1068 (Supreme Court of Colorado, 1928)
Calkins v. F. W. Woolworth Co.
27 F.2d 314 (Eighth Circuit, 1928)
Lewis Clark County v. Nett
263 P. 418 (Montana Supreme Court, 1928)
North v. Brittain
291 S.W. 1071 (Tennessee Supreme Court, 1927)
Overstreet v. Merritt
200 P. 11 (California Supreme Court, 1921)
Sprout v. . Ward
107 S.E. 214 (Supreme Court of North Carolina, 1921)
Storey v. . Stokes
100 S.E. 689 (Supreme Court of North Carolina, 1919)
Nance v. . Telegraph Co.
98 S.E. 838 (Supreme Court of North Carolina, 1919)
Crutchfield Hardware Co. v. Reid Foundry & MacHine Co.
93 S.E. 970 (Supreme Court of North Carolina, 1917)
Gardner v. Postal Telegraph & Cable Co.
88 S.E. 630 (Supreme Court of North Carolina, 1916)
Bokoshe Smokeless Coal Co. v. Bray
1916 OK 111 (Supreme Court of Oklahoma, 1916)
First State Bank of Mannsville v. Howell
1913 OK 504 (Supreme Court of Oklahoma, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.Y. 489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffin-v-colver-ny-1858.