Abbott v. Gatch

13 Md. 314, 1859 Md. LEXIS 31
CourtCourt of Appeals of Maryland
DecidedApril 28, 1859
StatusPublished
Cited by69 cases

This text of 13 Md. 314 (Abbott v. Gatch) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abbott v. Gatch, 13 Md. 314, 1859 Md. LEXIS 31 (Md. 1859).

Opinion

Tuck, J.,

delivered the opinion of this court.

The plaintiff, the present appellee, contracted to put up a mill guarantied to grind the best wheat flour, with the neces[329]*329sary bolters, elevator and rubber, for the sum of five thousand dollars. In the contract there is this clause: “No extra charges to be made unless a written agreement be made and attached to the contract.” In the progress of the work, alterations were made, and portions of the mill put in, as the plaintiff contends, not embraced by the terms of the contract, without the parties availing themselves of the above provision, and one of the questions in the cause is, can the plaintiff demand additional compensation beyond the sum stipulated for the entire work? The claim is placed on the ground, that the defendant interfered with the work by directing or authorizing these departures from the original design, and in some instances, against the opinion of the plaintiff. Whether these circumstances can aid him must depend on the object of the parties in inserting this clause, and the interpretation we are to put upon the entire agreement.

It is manifest, that the object of such provisions in building contracts is certainly as to the terms on which the work is to be done, in. order that the parties may know how much one is to pay and the other to receive for such changes and alterations as maybe made. Neither has a right to change the plans without the other’s consent; but, as this may be done by agreement, when alterations are specified in writing and attached to, tfhey become parts of, the original contract, and the-builder may recover for such work according to the agreement in that behalf. The present plaintiff undertook to erect a mill, a work requiring practical knowledge and skill in that branch of the mechanic arts, on which it is to be presumed, the defendant relied in giving him the contract.- It was his right, as well as duty, to determine what was necessary to complete such a mill as he liad contracted to put, up; and as to all matters not mentioned in the agreement, or laid down on the plans, he was solely responsible. He was under no obligation to receive suggestions from Abbott; on the contrary, if he deemed them unsuitable or impracticable, or likely to cause increased expense, he should have resorted to the contract, as containing all that he was required to perform, and insisted on having the additional work brought within its terms, as well for his own [330]*330protection, as to prevent misapprehension on the other side.The words in question protected Abbott against extra charges.They cannot mean that no extra charge was to be made for what the contract required, because the very office of that was to define what was to be done and to fix the price. We take the true construction to be, that there was to be no charge for extra work, that is, for any work beyond that stated in the contract, no matter what it might be, whether alterations in the plan or mode of doing the work, or additions or improvements in and about the completion of the mill, unless reduced to writing and attached. It makes no difference if the extra work was ordered by the owner, provided it was on the mill. As we have said, the builder need not accede to the owner’s views; he may refuse, or he may assent, under the protection' afforded by this clause. If extra work be done without it the right to additional compensation is waived. Any other interpretation of such words would make them valueless to the parties. The appellee’s view, if adopted,-would deny to the-owner the privilege of suggesting any, the most trivial, alteration of the work, without incurring the risk of opening the-whole contract; then the written agreement would be substituted by a mere quantum meruit claim for work and labor, to-be afterwards adjusted upon uncertain oral testimony. And,in many cases, his mere presence on the premises might subject him to extra charges, on the ground of acquiescence in-alterations made by the builder, when it might well be supposed there was to be no additional charge, because not previously attached to the contract. 5 G. & J., 263, 264. 6 H. & J., 89. 9 Barr., 245. We cannot distinguish this agreement from that passed upon in the case of Baltimore Cemetery Co. vs. Coburn, 7 Md. Rep., 202, The same considerations apply to both. To hold a party liable in the face of such a stipulation, would be to turn his plain words into something that he had not assented to. In 9 Barr., 245, extra work was not. allowed for, though done with the owners’’ knowledge, and without objection, and afterwards accepted by them. There, the contract did not require the agreement for extra work to be in writing, but the terms were very explicit,[331]*331viz: “At any time during the progress of the building, the committee reserves the right to direct any alteration or variation from tire original plan, so as not to vary therefrom in any very essential manner, so as to cause any material extra expense to the building; but any alteration suggested by them shall be made, and the expense, if any, shall be agreed upon at the time; but no extras shall be allowed under any pretence whatever.” Extra work was done with the knowledge of tire committee, who made no objection, and some of them approved of the plaintiff’s acts. The court held, that in the face of such an agreement, affording ample protection to both parties, the action could be maintained only, “by clear and satisfactory evidence of a new, distinct and independent contract, authorizing the alterations, and expressly agreeing to pay for them a certain fixed price, or what they may be reasonably worth,” and that if the contract was to be thrown open, because of the presence of the committee while the work was going on, without objection to the changes, though often conversing about them, and because of their acceptance of the work, it would be useless to pot such agreements in writing. This may appear to be a harsh construction, where the owner has received the benefit of the work; but the law is well settled, that contracts are to be interpreted and enforced, according to the fair import of their terms, without reference to the hardships that may fail on the parties. Wagner vs. White, 4 H. & J., 566. 6 H. & J., 143. Dorsey vs. Smith, 7 H. & J., 345. If persons voluntarily express themselves in writing, they must be bound by the language employed. McElderry vs. Shipley, 2 Md. Rep., 25. The law presumes, that they understand the import of their own contracts, and to have entered into them with knowledge of their mutual rights and obligations. And if, in a case like this, one party omits to have the changes reduced to writing, they must, in view of the rights of the other, be deemed to have been made with reference to the contract price, unless there be proof of an express waiver of that clause of the contract, or a promise to pay for the extra work. Hort vs. Norton, 1 McCord, 22. Wilmot vs. Smith, 3 C. & P., 453. 7 H. & J., 345, 363. 1 Gill, 311. 5 Md. Rep., 121. 9 Pick., 298.

[332]*332it follows from these views of the agreement, that the comt below erred in disallowing the defendant’s objection to the evidence of work claimed as extra or additional, and also in granting the plaintiff’s 5th, 6th and 7th prayers; and this ruling renders it unnecessary to pass upon the 1st, 2nd, 3rd, 4th and 7th prayers of the defendant, relating to the same points.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minh-Vu Hoang v. Hewitt Avenue Associates, LLC
936 A.2d 915 (Court of Special Appeals of Maryland, 2007)
Southern Maryland Hospital Center v. Edward M. Crough, Inc.
427 A.2d 1051 (Court of Special Appeals of Maryland, 1981)
St. Paul at Chase Corp. v. Manufacturers Life Insurance
278 A.2d 12 (Court of Appeals of Maryland, 1971)
AB CORPORATION v. Futrovsky
267 A.2d 130 (Court of Appeals of Maryland, 1970)
Smith v. Potomac Electric Power Co.
202 A.2d 604 (Court of Appeals of Maryland, 1964)
United States v. Blount
182 F. Supp. 648 (D. Maryland, 1960)
M & R Contractors & Builders, Inc. v. Michael
138 A.2d 350 (Court of Appeals of Maryland, 1958)
Freeman v. Stanbern Construction Co.
106 A.2d 50 (Court of Appeals of Maryland, 1954)
Iowa Electric Light & Power Co. v. Hopp
866 N.W. 512 (Supreme Court of Iowa, 1936)
Parker v. Tilghman v. Morgan, Inc.
183 A. 224 (Court of Appeals of Maryland, 1936)
Duplex Envelope Co. v. Baltimore Post Co.
163 A. 688 (Court of Appeals of Maryland, 1933)
Shriver v. Druid Realty Co.
131 A. 815 (Court of Appeals of Maryland, 1926)
Hipple v. Mason
127 A. 383 (Court of Appeals of Maryland, 1925)
Wilson v. Hilliard
101 A. 603 (Court of Appeals of Maryland, 1917)
Cramer v. Baugher
100 A. 507 (Court of Appeals of Maryland, 1917)
Sullivan v. Boswell
89 A. 940 (Court of Appeals of Maryland, 1914)
Hicks v. National Surety Co.
155 S.W. 71 (Missouri Court of Appeals, 1913)
Mayor of Baltimore v. J. A. Kinlein & Co.
84 A. 483 (Court of Appeals of Maryland, 1912)
Rawlings v. Duane H. Nash, Inc.
83 A. 646 (Court of Appeals of Maryland, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
13 Md. 314, 1859 Md. LEXIS 31, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abbott-v-gatch-md-1859.