Freeman v. Stanbern Construction Co.

106 A.2d 50, 205 Md. 71, 1954 Md. LEXIS 261
CourtCourt of Appeals of Maryland
DecidedJune 24, 1954
Docket[No. 152, October Term, 1953.]
StatusPublished
Cited by44 cases

This text of 106 A.2d 50 (Freeman v. Stanbern Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freeman v. Stanbern Construction Co., 106 A.2d 50, 205 Md. 71, 1954 Md. LEXIS 261 (Md. 1954).

Opinion

Delaplaine, J.,

delivered the opinion of the Court.

Stanbern Construction Company was the general contractor for the construction of 270 apartments in Section A of Glassmanor, a project of the Federal Housing Administration located in Prince George’s County at Congress Heights, a suburb of Washington. On May 25, 1949, Freeman Brothers, a partnership consisting of Walter B. Freeman, Sr., Walter B. Freeman, Jr., and George Freeman, entered into a contract with the general contractor to do all the landscaping in accordance with the architect’s plans and specifications for the sum of $36,500.

Freeman Brothers, as such subcontractors, agreed that the selection of all materials and the execution of all work required by the plans and specifications should be subject to the approval of the F.H.A. landscape inspector, who would have the right to reject any articles, materials, supplies or workmanship which, in his opinion, did not conform to the specifications at any stage of the operations. They agreed that no planting would be done in frozen soil, or during unfavorable weather conditions, or after the month of April without the express permission of the F.H.A. landscape inspector. They agreed to guarantee all plant material to be true to name and size and to be in vigorous growing condition. They agreed that trees would be guaranteed for one year, and that evergreens and shrubs would be guaranteed through one growing season. They agreed to make any necessary replacements at the beginning of the first succeeding planting season.

According to Walter B. Freeman, Sr., defendants began clearing the top soil on May 26 and completed that preliminary work about July 15. In explaining why it took so long, he testified: “It couldn’t all be done at once. The sub-grade wasn’t ready. The job was late due to the fact that the excavating contractor was not *75 through with the grading around the buildings, and we had to wait for the buildings, going from building to building from time to time until the back-fill and grading had been completed.”

Mr. Freeman explained the process of landscaping as follows: “There is a sequence in this work. You first get your grading done, your rough grading, then your fine grading. That wasn’t up to me. The fine grading was done. Then you put your top soil on. You dig your shrubbery where excess top soil is required. Then the next step after that is you put your top soil in those pits and also everywhere that you are going to put grass or sod. Then, when that is done, you dig down through the sod that you already planted, and put in the required shrubbery for which you have a plan. That is the sequence.”

Mr. Freeman testified that Herbert Glassman, the construction boss, ordered him to have all the planting completed by September 15, but he objected because shrubbery is practically never planted before September 15, and even then it is dependent upon the weather. “If it is dry,” he said, “You wait for a rainy period. It might be October 15.” When he objected, in view of the guarantee defendants had made that the shrubbery would be satisfactory through one growing season, Mr. Glassman held up payments for the work.

Mr. Freeman thereupon offered to show that defendants entered into an oral agreement whereby they agreed to plant the shrubbery without delay, and plaintiff agreed to waive the guarantee defendants had made as to the continued growth of the shrubbery, thus relieving them of liability for any unsatisfactory results from the planting. Mr. Freeman further testified that they began planting the shrubbery in the last week of August and completed it about September 13. He acknowledged that this was out of season, but he explained that it was impossible to plant earlier in the year on account of the failure of another subcontractor to complete the grading work on time, and that he did the planting in *76 August and early in September to comply with plaintiff’s request to finish the work before the deadline of September 15.

During the course of the work, plaintiff paid defendants $35,882.20. Plaintiff then found that the planting did not meet the F.H.A. requirements, and the F.H.A. landscape inspector would not approve the work.

Plaintiff thereupon entered suit to recover damages from defendants for alleged breach of contract. Plaintiff alleged that, after unsuccessful efforts to persuade defendants to replace the rejected plant material and to complete the planting work, it replaced a number of plants itself in order to secure approval of the entire apartment project and' a release of the balance of the F.H.A. insured construction loan.

The trial judge excluded testimony as to the alleged oral agreement varying the terms of the written contract, basing his ruling on the clause of the contract which provides: “No deviations from plans and specifications will be permitted without an agreement written by the General Contractor.” At the conclusion of the trial the jury rendered a verdict in favor of plaintiff for $3,300.00. Defendants appealed from the judgment entered thereon.

Plaintiff filed a motion in this Court to dismiss the appeal on the ground that the transcript of the record was not transmitted to the Court of Appeals within 60 days from the time when the appeal was entered. The appeal was entered on December 10, 1953. Defendants submitted an affidavit of the Deputy Clerk of the Circuit Court for Prince George’s County averring that on February 4, 1954, counsel for defendants ■ submitted to her for filing a 'transcript of the testimony and the exhibits in the case, but those papers were not filed until February 8, because the bond presented by defendants did hot conform with the requirements of the Circuit Court; that on February 8 a bond in proper form was presented to her and was filed on the same day, whereupon various papers which had been with *77 held were filed. The Deputy Clerk further swore that she then prepared the record and mailed the transcript on February 10. It was filed in the office of the Clerk of the Court of Appeals on February 11.

Our rules provide that the transcript of the record in an appeal from a judgment of a court of law shall be transmitted within 60 days from the time of the appeal taken, but no appeal shall be dismissed because the transcript shall not have been transmitted within the time prescribed, if it shall appear to the Court of Appeals that such delay was occasioned by the neglect, omission or inability of the clerk or appellee. Rules Respecting Appeals, rules 2, 11. Inasmuch as defendants submitted the transcript of testimony and exhibits to the Deputy Clerk in ample time for transmission to the Clerk of the Court of Appeals, and the transcript was delayed several days by the mistake of the Deputy Clerk, we overruled plaintiff’s motion to dismiss the appeal. The Deputy Clerk was under the impression that it was her duty to withhold the papers until the bond was filed, but actually the filing of a bond merely stays execution on the judgment and failure to file a bond does not affect the appeal and the right to have the papers transmitted.

It is an elementary rule of the common law that parol evidence is inadmissible to vary or contradict the terms of a written instrument. The reason for that rule, as we said in Markoff v. Kreiner, 180 Md. 150, 23 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

600 North Frederick Road, LLC v. Burlington Coat Factory
19 A.3d 837 (Court of Appeals of Maryland, 2011)
Maryland Automobile Insurance Fund v. John
16 A.3d 1008 (Court of Special Appeals of Maryland, 2011)
Clawson v. FedEx Ground Package System, Inc.
451 F. Supp. 2d 731 (D. Maryland, 2006)
Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc.
885 A.2d 381 (Court of Special Appeals of Maryland, 2005)
DirecTV, Inc. v. Mattingly
829 A.2d 626 (Court of Appeals of Maryland, 2003)
Fantle v. Fantle
782 A.2d 377 (Court of Special Appeals of Maryland, 2001)
National School Studios, Inc. v. Mealey
126 A.2d 588 (Court of Appeals of Maryland, 1999)
Truhe v. Turnac Group, L.L.C.
1999 SD 118 (South Dakota Supreme Court, 1999)
A.D. Powers v. Miller
1999 NMCA 080 (New Mexico Court of Appeals, 1999)
Evergreen Amusement Corp. v. Milstead
112 A.2d 901 (Court of Appeals of Maryland, 1998)
Prime Financial Group, Inc. v. Masters
676 A.2d 528 (Supreme Court of New Hampshire, 1996)
Waller v. Maryland National Bank
620 A.2d 381 (Court of Special Appeals of Maryland, 1993)
Annapolis Mall Ltd. Partnership v. Yogurt Tree of Annapolis, Inc.
473 A.2d 32 (Court of Appeals of Maryland, 1984)
Erlewine v. Happ
383 A.2d 82 (Court of Special Appeals of Maryland, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
106 A.2d 50, 205 Md. 71, 1954 Md. LEXIS 261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freeman-v-stanbern-construction-co-md-1954.