Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc.

885 A.2d 381, 165 Md. App. 262, 2005 Md. App. LEXIS 273
CourtCourt of Special Appeals of Maryland
DecidedOctober 31, 2005
Docket592, September Term, 2004
StatusPublished
Cited by14 cases

This text of 885 A.2d 381 (Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc., 885 A.2d 381, 165 Md. App. 262, 2005 Md. App. LEXIS 273 (Md. Ct. App. 2005).

Opinion

DAVIS, J.

Richard F. Kline, Inc., et al., appellant, appeals from a judgment entered on April 29, 2004, by the Circuit Court for Frederick County, in favor of appellee, Shook Excavating & Hauling, Inc, against appellant in the amount of $889,938.11 for breach of contract. The court had previously, in denying appellant’s motion for summary judgment, determined that Article XIX of the subcontract entered into by appellant and appellee is not a “paid if paid” condition precedent, relieving appellant from any obligation to pay appellee.

Appellant presents four questions for our review, which we rephrase, in part, as follows.

1. Did the trial court err as a matter of law in denying appellant’s motion for summary judgment and finding that article XIX of the subcontract was not a “paid if paid” condition precedent, relieving appellant from any obligation to pay appellee?
2. Did the trial court err as a matter of law in rendering a judgment that was outside the cause of action pled in the amended complaint?
3. Did the trial court err as a matter of law in finding that the subcontract between appellant and appellee was modified orally?
4. Did the trial court err as a matter of law in finding article XIX of the subcontract was not a liquidated damages clause?

We answer these questions in the negative. Therefore, we affirm the decision of the circuit court.

*267 FACTUAL BACKGROUND

Richard F. Kline, Inc., et al., appellant, entered into a contract (hereinafter, “general contract”) with The City of Frederick (hereinafter, “City”) on September 21, 1993, to provide services related to the excavation and construction of Phase IIIB of the Carroll Creek Flood Control Project. 1 Appellant entered into a subcontract with appellee to provide excavation, grading and other related services in support of appellant’s contract with the City on August 31, 1993 (hereinafter, “subcontract”). The project site, where the excavation, grading and construction were to take place, contained hazardous materials in the form of underground storage tanks (hereinafter, “USTs”) and contaminated soil. It is the payment associated with the hauling, stockpiling and handling of the contaminated soil that is ultimately the issue in this appeal.

During the project, the engineer and project manager for the City was Rummel, Klepper & Kahl (hereinafter “R.K. & K.”) Later, R.K. & K. Environment was hired to be on site to assess the condition of the soil and storage tanks on a daily basis. The Maryland Department of the Environment (hereinafter, “MDE”), has regulatory authority over the excavation and disposal of storage tanks and contaminated soil for the State of Maryland. The City and R.K. & K. deferred to the determinations of MDE relating to the excavation and disposal of storage tanks and the disposition of soils believed to be contaminated.

The subcontract incorporated by reference all of the terms and conditions of the general contract. The general contract contained a contingent item, Item 220, that dealt with removal of contaminated soil. Initially, it was appellant that was responsible for the handling of contaminated soil during the project. The subcontract did not contain any provisions for handling contaminated soil and appellee was only responsible for the removal of USTs on the site.

*268 Beginning on November 17, 1993, storage tanks were excavated and removed from the job site. As the USTs were removed, the soil was segregated pursuant to the directions of MDE and R.K. & K. Although not a part of the subcontract between appellant and appellee, appellee hauled the soil to the site as directed by appellant. Appellant and appellee amended the subcontract on December 7, 1993, to add “item 220,” the contingent pay item, making appellee responsible for handling contaminated soils on the site. Handling contaminated soil on the site involved moving the soil from the area around the USTs and hauling the soil to another location on the site where it could be mixed in order to expose it to the air. The mixing of the soil was to reduce the level of contamination in the soil to an acceptable level. Once the contamination level in the soil was reduced, it was then to be used in backfilling on the project.

By letter dated August 11, 1994, the City issued a directive for the handling of soils on the project believed to be contaminated. In that letter, addressed to appellant, the City stated that appellant was to be compensated on a time and materials basis after receiving approval, from R.K. & K., to treat the soil as contaminated. By letter dated March 17, 1995, the City directed that appellant was to cease work on the contaminated soil stockpile because MDE, through its testing, had determined that the soils were not contaminated.

Both parties continued to believe the soils were contaminated, despite MDEs determination that the soils were not. William Shook testified on behalf of appellee that sometimes the smell of the soil on the site made him, as well as members of his crew, sick. He also testified that the soil appeared oily, had an odor of petroleum, and contaminants had caused him to develop a rash on his arm. Following receipt of the March 17, 1995 letter, appellant had the soil on the site tested by an independent laboratory to determine the level of contamination. The testing confirmed that the soil on the project site contained higher amounts of contaminants than reported by MDE.

*269 On May 23, 1995, appellee began to move soil from the stockpile to an earth berm as required by the subcontract with appellant. Appellee contends that it moved the soil in accordance with the instructions given by appellant, which were to continue to treat the soil as contaminated. Appellee was to be paid on a monthly basis by submitting estimates to appellant. William Shook testified that he was paid monthly for other work performed on the job, but not for work involving contaminated soils.

Appellee then demanded payment from appellant in accordance with the contingent rate for contaminated soils agreed upon in the contract amendment. As required by Article XIX of the subcontract, appellant demanded payment from the City at contingent rate for contaminated soils. Article XIX of the subcontract states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
885 A.2d 381, 165 Md. App. 262, 2005 Md. App. LEXIS 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-f-kline-inc-v-shook-excavating-hauling-inc-mdctspecapp-2005.