Patriot Construction v. VK Electrical

CourtCourt of Special Appeals of Maryland
DecidedMarch 2, 2023
Docket0942/21
StatusPublished

This text of Patriot Construction v. VK Electrical (Patriot Construction v. VK Electrical) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patriot Construction v. VK Electrical, (Md. Ct. App. 2023).

Opinion

Patriot Construction, LLC v. VK Electrical Services, LLC No. 942, September Term, 2021 Filed March 2, 2023. Opinion by Friedman, J.

HEADNOTES: LIMITATIONS OF ACTIONS > COMPUTATION OF LIMITATIONS PERIOD > ACCRUAL OF RIGHT OF ACTION OR DEFENSE > CONTRACTS > CONSTRUCTION AND OPERATION > CONDITIONS PRECEDENT TO PAYMENT When a contract contains a pay-when-paid clause as a condition precedent to payment, a breach of contract action for failure to pay does not accrue until the condition is met. Circuit Court for Anne Arundel County Case No. C-02-CV-20-001339

REPORTED

IN THE APPELLATE COURT

OF MARYLAND*

No. 942

September Term, 2021

______________________________________

PATRIOT CONSTRUCTION, LLC

v.

VK ELECTRICAL SERVICES, LLC

Wells, C.J., Friedman, Eyler, James R. (Senior Judge, Specially Assigned),

JJ. ______________________________________

Pursuant to the Maryland Uniform Electronic Legal Materials Opinion by Friedman, J. Act (§§ 10-1601 et seq. of the State Government Article) this ______________________________________ document is authentic.

2023-03-02 10:17-05:00 Filed: March 2, 2023

Gregory Hilton, Clerk

* At the November 8, 2022 general election, the voters of Maryland ratified a constitutional amendment changing the name of the Court of Special Appeals of Maryland to the Appellate Court of Maryland. The name change took effect on December 14, 2022. In June 2020, appellee VK Electrical Services, LLC (“VKES”) filed a breach of

contract action against Patriot Construction, LLC in the Circuit Court for Anne Arundel

County, alleging that Patriot had refused to pay VKES for completed subcontract work.

Patriot moved to dismiss the complaint for failure to state a claim upon which relief could

be granted. The trial court denied the motion to dismiss but for one count, and the matter

proceeded to a bench trial. VKES prevailed, and the trial court awarded it a judgment in

the amount of $64,575.09.

On appeal, Patriot asks us to consider whether the trial court erred in: (1) failing to

find that VKES did not satisfy a condition precedent contained in the subcontract;

(2) failing to find that VKES’s claims were barred by the statute of limitations;

(3) admitting parol evidence regarding pre-contract discussions; (4) failing to sufficiently

state on the record the reasons for its decisions on the contested issues; and (5) denying

Patriot’s motion to dismiss. For the reasons that follow, we affirm the trial court’s

judgment.

FACTUAL AND PROCEDURAL BACKGROUND

In October 2015, Patriot was working under a contract with the Maryland

Procurement Office of the National Security Agency (“MPO”) to provide general

contractor services for an NSA project at Fort Meade. After its original electrical

subcontractor was unable to complete the work, Patriot entered into a subcontract with

VKES, in which VKES agreed to perform electrical work for the project for a sum of

$495,000. The subcontract between Patriot and VKES explicitly provided that “[n]o alteration,

addition, omission or change shall be made in the Work or the method or manner of

performance of the Work except upon the written change order of PATRIOT

CONSTRUCTION.” In addition, an “Important Notice” was incorporated into the

subcontract. It detailed that performance of work prior to the full execution of a change

order would be done with “no expectation of monetary compensation from Patriot

Construction, LLC for that work.” (emphasis in original). The notice further provided

that in the event of “a rare emergency instance” that would require work prior to the full

execution of a change order, “permission to proceed shall only be granted by [John

Gilmore] or Matthew Timbario.” The contract between Patriot and VKES also included a

“pay-when-paid provision” which provided that Patriot’s receipt of payment from the MPO

was a condition precedent to Patriot’s payment obligations to its subcontractors. The

subcontract was signed by Craig Mills, Director of Operations, on behalf of Patriot and by

Vincent Krakat, President, on behalf of VKES.

As work on the project proceeded, Patriot requested that VKES perform fire alarm

and other work additional to the duties set forth in its subcontract. The additional work

increased VKES’s invoiced services by $366,428.09. Two of the additional invoices

submitted to Patriot were related to executed change orders, and the remainder were for

additional “ticket work” that had not been authorized in writing by Patriot.

VKES completed its work on the project on or about July 20, 2016, and sought

payment. Due to the pay-when-paid provision, however, VKES had to wait for Patriot to

be paid by the MPO. Patriot received its full payment from the MPO in October 2019. In

2 April 2020, a representative from Patriot contacted VKES and informed it that Patriot did

not submit the additional ticket work to the MPO for approval or payment, and therefore

Patriot would not pay VKES for those invoices. Patriot ultimately paid VKES a total of

$796,853 but declined to pay the ticket work invoice in the amount of $64,577.15.

In June 2020, VKES filed suit against Patriot seeking damages in the amount of

$64,577.15. Its complaint contained counts of: (1) breach of contract; (2) quantum meruit;

(3) unjust enrichment; (4) violation of federal prompt payment statute; (5) violation of

Maryland prompt payment statute; and (6) violation of Maryland trust fund statute.

Patriot moved to dismiss the complaint with prejudice, asserting that VKES had

failed to meet the condition precedent in the subcontract to obtain written authorization for

the additional work before proceeding. Patriot further argued that the action was barred by

the statute of limitations because VKES had submitted the unpaid invoice to Patriot more

than three years prior to the filing of its complaint.

VKES responded to Patriot’s motion to dismiss, arguing that its claims should not

be dismissed because Patriot “ordered, acknowledged, accepted and benefited from the

electrical services VK[ES] performed at the project” and “acquiesced to and waived the

subcontract written modification requirement.” VKES further argued that, due to the

subcontract’s pay-when-paid provision, the statute of limitations did not begin to run until

October 2019, when Patriot was paid by the MPO and declined to pay VKES. VKES

referenced August 2017 email correspondence between it and Patriot, in which Patriot

assured VKES that the MPO had approved the invoice, that, while it was “not custom to

3 pay[ ] prior to receiving funds ... Patriot will honor all work completed on the project,” and

that the funds would be forthcoming in the upcoming weeks.

The trial court held a hearing on Patriot’s motion to dismiss on December 7, 2020.

At the hearing, Patriot argued that because there was no factual dispute that VKES did not

have written approval for the additional ticket work as required by the express terms of the

subcontract, VKES had not met the condition precedent to being paid for that work. Patriot

also asserted that it had not submitted the invoices for the unpaid $64,577.15 to the MPO

and thus Patriot had not been paid for the work, which, under the pay-when-paid provision,

would mean it had no duty to pay VKES for the outstanding invoices. In the alternative,

Patriot argued that because the ticket work was outside the original subcontract, the pay-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bennett v. Pippin
74 F.3d 578 (Fifth Circuit, 1996)
Berry v. State
843 A.2d 93 (Court of Special Appeals of Maryland, 2004)
Planning Board v. Mortimer
530 A.2d 1237 (Court of Appeals of Maryland, 1987)
Shelter Mutual Insurance v. Nash
184 S.W.3d 425 (Supreme Court of Arkansas, 2004)
Chirichella v. Erwin
310 A.2d 555 (Court of Appeals of Maryland, 1973)
Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc.
885 A.2d 381 (Court of Special Appeals of Maryland, 2005)
Ryan v. Thurston
347 A.2d 834 (Court of Appeals of Maryland, 1975)
James v. Weisheit
367 A.2d 482 (Court of Appeals of Maryland, 1977)
City of District Heights v. Denny
719 A.2d 998 (Court of Special Appeals of Maryland, 1998)
Frederick Road Ltd. Partnership v. Sturm
756 A.2d 963 (Court of Appeals of Maryland, 2000)
DeLeon v. State
962 A.2d 383 (Court of Appeals of Maryland, 2008)
Henry's Drive-In, Inc. v. Pappas
287 A.2d 35 (Court of Appeals of Maryland, 1972)
Taylor v. University National Bank
282 A.2d 91 (Court of Appeals of Maryland, 1971)
Hoffman v. Glock
315 A.2d 551 (Court of Special Appeals of Maryland, 1974)
All State Home Mortgage, Inc. v. Daniel
977 A.2d 438 (Court of Special Appeals of Maryland, 2009)
Dickerson v. Longoria
995 A.2d 721 (Court of Appeals of Maryland, 2010)
Penowa Coal Sales Co. v. Gibbs & Co.
85 A.2d 464 (Court of Appeals of Maryland, 1969)
Laurel Race Course, Inc. v. Regal Construction Co.
333 A.2d 319 (Court of Appeals of Maryland, 1975)
Prahinski v. Prahinski
540 A.2d 833 (Court of Special Appeals of Maryland, 1988)
Afamefune v. Suburban Hospital, Inc.
870 A.2d 592 (Court of Appeals of Maryland, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Patriot Construction v. VK Electrical, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patriot-construction-v-vk-electrical-mdctspecapp-2023.