Laurel Race Course, Inc. v. Regal Construction Co.

333 A.2d 319, 274 Md. 142
CourtCourt of Appeals of Maryland
DecidedApril 4, 1975
Docket[No. 134, September Term, 1974.]
StatusPublished
Cited by48 cases

This text of 333 A.2d 319 (Laurel Race Course, Inc. v. Regal Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laurel Race Course, Inc. v. Regal Construction Co., 333 A.2d 319, 274 Md. 142 (Md. 1975).

Opinion

Levine, J.,

delivered the opinion of the Court.

The dispute which has resulted in this appeal was spawned from the lofty but earnest ambition of appellant, Laurel Race Course, Inc. (Laurel), to build “the best [race] track in the United States.” To the extent that it might not have fully attained such preeminence, it undoubtedly faults appellee, Regal Construction Company, Inc. (Regal), with whom it had contracted to rebuild its track. Its dissatisfaction with the quality of Regal’s performance under that contract led to Laurel’s refusal to pay a portion of the sum claimed for those services. As a consequence, Regal brought suit and, following a nonjury trial in the Circuit Court for Prince George’s County (Bowen, J.), obtained a judgment against Laurel in the amount of $67,276.17. This appeal followed.

As the first step in its quest, Laurel, in March 1972, engaged an internationally renowned engineering firm, Watkins and Associates, Inc. (Watkins) of Lexington, Kentucky. Later that spring, Laurel and Watkins entered into a contract whereby the latter agreed to design a plan for the reconstruction of the Laurel track and the installation of a complete drainage system. Watkins had achieved success in designing such “all-weather” tracks for a number of *144 racing courses throughout the world. In addition to preparing a design, a set of specifications and other similar documents, Watkins was to have personnel in attendance during the construction phase.

In June 1972, Regal submitted a bid proposal for the construction work. In doing so, it agreed to perform “in strict accordance with the terms and conditions of the specifications and contract documents . . . and the plans . . . and do such other work incidental thereto as [might] be ordered by the Engineer, at the unit or lump sum prices quoted in the attached ‘Bid Schedule.’ ” It also declared that it had “examined the site of the work and informed [it]self fully in regard to all conditions pertaining to the place where the work [was] to be done; [and] that [it had] examined the plans, specifications, and contract documents .. . .” It also agreed to “substantially complete all work on or before September 1, 1972, and to finish the job by September 15, 1972.” This document and the contract itself expressly made time of the essence.

After becoming the successful bidder, Regal executed the usual panoply of documents which regularly attend such transactions. Among them was the “General Conditions” which defined Watkins’s status as the “Engineer.” It was to “have general inspection and direction of the work as the authorized representative of the owner [Laurel].” It had “authority to reject work and materials which [did] not conform to the plans, specifications and contract documents, .. . [and to] decide all engineering questions . . . .” It was also charged with the duty to “interpret the meaning and requirements” of those documents and to “decide all disputes” that might arise thereunder.

In order to “protect itself from loss,” Laurel was permitted to withhold partial payments from Regal if the latter failed “to remedy defective work” and for “other causes which in the opinion of the Engineer would justify [Laurel] in withholding such . . . payments.” In addition, the General Conditions allowed Laurel to “retain not less than [ten percent] of the amount [of each partial payment] until final completion and acceptance of all work covered by this *145 contract.” The General Conditions concluded with a guarantee by Regal of “all construction against defective materials, equipment and workmanship for a period of twelve months . . . .” This included a commitment to “replace such defective parts without cost to the Owner.”

Essentially, the work to be performed by Regal consisted of the rehabilitation of both the dirt and turf tracks, and the installation of a surface and underground drainage system, including proposed lakes, most of which was designed primarily to provide a “faster” track under “all-weather” conditions. The specifications detailed rather minutely the gradation requirements for the various materials to be used in the base, subbase and cushion of the main track. In this connection, the specifications provided: “If any over-size rock, or other deleterious materials that could be harmful to a running horse, are incorporated within the base material during the storage, mixing, or hauling of the base soil, such harmful material shall be removed by the Contractor at his own expense.” With respect to the storm drainage system, the specifications provide that “[a] 11 pipes shall be laid with ends abutting and true to line and grade,” and that the “space between pipes shall be filled with a concrete mortar of proper consistency” as therein specified.

Both the subbase and blended base materials were to “be paid for at the contract unit price in-place and compacted to the required density.” Payment under the entire contract was to be made on a “unit price” basis, whereby the total amount to be paid Regal was to be determined by applying the unit prices contained in the bid proposal to the actual quantities “certified by the Engineer for the items enumerated in the Bid Schedule . . . .”

The contract was dated July 3, 1972, and Regal apparently commenced its work shortly thereafter. Performance was neither substantially completed by September 1 nor fully completed by September 15. Regal professes to have substantially completed the work in accordance with the contract terms by September 25, and claims that it ultimately rendered complete performance. On September 28, 1972, after “turning over” the track to Laurel on the 25th, *146 Regal received a “punch list” of 18 items requiring its attention. After Regal claimed in late November that it had remedied those deficiencies and therefore demanded payment in full, Watkins forwarded its recommendation that payment be withheld because:

“During the construction of the base the Contractor permitted a large amount of rock and oversize material to become mixed with the clay and sand which were hauled from the source of supply and, in spite of repeated requests, did not make a reasonable effort to remove this material from the base while it was being placed. . . . [I]t has been necessary for [Laurel’s] crew to perform a large amount of maintenance work that would not have been required had the base been properly blended and compacted.
“The condition of the track for the first three weeks resulted in justifiable complaints from the horsemen and could be traced directly to the failure of the Contractor to obtain adequate compaction and proper shaping of the inside ditch and drainage.”

Having received the recommendation from Watkins that payment of the balance due be retained, Laurel refused to pay the sum of $110,931.91, representing the amount then claimed by Regal as the unpaid balance on the total contract amount of $786,401.35. The latter brought suit for this amount plus interest in February 1973. By the time of the trial in April 1974, the amount claimed by Regal under the written contract had been reduced to $49,648 plus interest because Laurel had made additional payments during the intervening period.

In its declaration, Regal sought payment under two express contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hess Construction v. Francis O'Day Co.
Court of Special Appeals of Maryland, 2025
Wildewood Operations v. WRV Holdings
Court of Special Appeals of Maryland, 2023
Patriot Construction v. VK Electrical
Court of Special Appeals of Maryland, 2023
White Marlin Open, Inc. v. Heasley
262 F. Supp. 3d 228 (D. Maryland, 2017)
MCG, Inc. v. MGSJ Holdings, Inc.
648 F. App'x 372 (Fourth Circuit, 2016)
Gebhardt & Smith LLP v. Maryland Port Administration
982 A.2d 876 (Court of Special Appeals of Maryland, 2009)
All State Home Mortgage, Inc. v. Daniel
977 A.2d 438 (Court of Special Appeals of Maryland, 2009)
Phoenix Services Ltd. Partnership v. Johns Hopkins Hospital
892 A.2d 1185 (Court of Special Appeals of Maryland, 2006)
Bi-Tech North, Inc. v. Lockheed Martin Corp.
129 F. App'x 9 (Fourth Circuit, 2005)
B & P ENTERPRISES v. Overland Equipment Co.
758 A.2d 1026 (Court of Special Appeals of Maryland, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
333 A.2d 319, 274 Md. 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laurel-race-course-inc-v-regal-construction-co-md-1975.