Shoreham Developers, Inc. v. Randolph Hills, Inc.

235 A.2d 735, 248 Md. 267, 1967 Md. LEXIS 325
CourtCourt of Appeals of Maryland
DecidedDecember 8, 1967
Docket[No. 680, September Term, 1966.]
StatusPublished
Cited by47 cases

This text of 235 A.2d 735 (Shoreham Developers, Inc. v. Randolph Hills, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shoreham Developers, Inc. v. Randolph Hills, Inc., 235 A.2d 735, 248 Md. 267, 1967 Md. LEXIS 325 (Md. 1967).

Opinion

Finan, J.,

delivered the opinion of the Court.

On June 22, 1962, Randolph Hills, Inc., by its president, Morris Perlmutter, entered into a contract with Shoreham Developers, Inc. On the same day Perlmutter Bros., Inc. also entered into a contract with Shoreham Developers, Inc. Under one of the instruments, known as the sales contract, Randolph Hills agreed to sell to Shoreham Developers a tract of land containing 32.61 acres for a total purchase price of $351,000 of which $10,000 was to be deposited with attorneys for the seller. Of particular importance to the present dispute is paragraph 5 :

“On or before ninety'(90) days from the date hereof or as soon thereafter as a report of title can be obtained if promptly ordered, the Purchaser and Seller *269 agree and shall be required to make settlement of this contract. It is understood that the time of settlement is of the essence. Settlement is to be made at the office of the Purchaser’s choosing, and deposit with said firm of the deed and such other papers or cash payment as may be required by the terms hereof shall be considered good and sufficient performance of the terms. If the Purchaser shall fail or refuse to make settlement in accordance with the provisions of this contract, his deposit may be forfeited as liquidated damages or, without such forfeiture, the Seller may at its option pursue such other legal and equitable remedies for the enforcement hereof as it deems proper.”

The second contract, described as the finishing contract, embodied the terms and conditions relative to the seller processing the land involved in the sales contract into finished lots. Some of the requirements in this contract were conditions precedent to settlement.

It should be understood from the beginning that Perlmutter (the testimony as to this was undisputed) requested that the original contract be separated into two agreements so as to afford Randolph Hills certain tax benefits. Theodore Lerner, vice-president of Shoreham Developers, agreed that Perlmutter could prepare the contract in any manner he wished, so long as it was one overall agreement and reflected all the terms and conditions agreed upon.

Immediately following the execution of the agreements and pursuant to their terms, the purchaser, Shoreham Developers, filed applications with the Veterans Administration and the Federal Housing Administration for approval of the homes they intended to build. In addition it entered into other preliminary agreements, such as ordering a title report, retaining engineering firms and obtaining a standby commitment for construction financing from the Prudential Insurance Company, making a $9,000 deposit for this latter commitment.

In the meantime, Randolph Hills, pursuant to its obligation under the finishing contract, received the approval of the Maryland-National Capital Park and Planning Commission for ninety *270 of the lots covered by the sales contract. However, as September 20, 1962, which was the ninetieth day after the execution of the agreements, drew near, it became increasingly obvious that Randolph Hills would be unable to settle. It had agreed under the finishing contract to sign certain engineering agreements relating to sewerage and water rights of way with the Washington Suburban Sanitary Commission (WSSC) “prior to settlement,” but by September Randolph Hills was unable to obtain WSSC approval.

As the settlement date approached, Perlmutter informed Lerner of the difficulty it was having obtaining the WSSC commitments and suggested an extension of the time for settlement. Lerner verbally agreed to wait until Perlmutter had performed all of the preliminary conditions, and on September 18, 1962, Shoreham Developers sent a letter to Randolph Hills confirming the mutually agreed to modification. The last sentence of this letter read: “Should the aforegoing be agreeable, please sign a copy of this letter and return same to us.” Although the record discloses that Randolph Hills never signed and returned ■a copy of the written modification, it is devoid of any indication that Randolph Hills expressly or impliedly objected to the modification as it appeared in the September 18 letter. The parties discussed going to settlement on numerous occasions between September 20, 1962 and the early part of 1963, however Perlmutter and his company remained unsuccessful in their attempt to obtain WSSC approval. Early in 1963, Perlmutter made a new proposal to Lerner; Randolph Hills would apply with the county for a zoning reclassification which would permit construction of apartment units on the same land which was the subject of the sales contract and the finishing contract. Both parties would then enter into a joint venture to develop the apartments together. Lerner agreed on behalf of Shoreham Developers but only on the condition that the parties revert to the original agreement of June 22, 1962 if the new arrangement •did not go through as planned.

The final chapter to this wayward venture began with the •county approval of the rezoning application on August 4, 1964. Lerner contacted Perlmutter and requested that he prepare the .final documents, but Perlmutter informed him that he was un *271 der no obligation to Lerner with respect to the apartments. Lerner was quite upset at this new twist, but after protesting, inquired as to whether the parties could fall back on the original deal, since there was obviously no agreement regarding the apartments. To this, Perlmutter replied that the original agreement had been “cancelled.” At this final meeting between the parties Perlmutter offered Lerner $50,000 to forget about the whole thing, which offer Lerner rejected.

Shoreham Developers, Inc., and Lerner filed a bill of complaint for specific performance on August 12, 1964. On May 17, 1965, attorney for Randolph Hills sent notice to Lerner that the seller was declaring the original contract null and void and was retaining the $10,000 deposit as liquidated damages. The appellants then filed their amended bill on July 13, 1965. In this pleading, they alleged that at all times after June 22, 1962 they had been ready, willing and able to go to settlement. The case proceeded to trial and at the close of appellants-petitioners’ case, the court granted appellee-respondent’s motion to dismiss under Rule 535. From this dismissal, Shoreham Developers, Inc. and Lerner appealed. We reverse the decision of the lower court.

At the outset, it must be noted that the court below treated both instruments of June 22, 1962 as forming only one contract involving the sale of finished lots. We agree with this construction. Paragraph 10 of the sales contract reads:

“The principals to this contract mutually agree * * *; that this contract contains the final and entire Agreement between the parties hereto and they shall not be bound by any terms, statements or representations not contained herein.”

Notwithstanding the above integration clause, this Court does not find a situation requiring the application of the parol evidence rule to exclude reading the instruments together. It is quite apparent that the parties did not intend the sales contract standing by itself to be a final and complete integration of the agreed upon terms. See Markoff v. Kreiner, 180 Md. 150, 23 A. 2d 19 (1941).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luo v. District of Columbia Department of Employment Services
District of Columbia Court of Appeals, 2025
Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)
WSC/2005 LLC v. Trio Ventures Assocs.
190 A.3d 255 (Court of Appeals of Maryland, 2018)
Baker v. ANTWERPEN MOTORCARS LTD.
807 F. Supp. 2d 386 (D. Maryland, 2011)
Fischbach v. Fischbach
975 A.2d 333 (Court of Special Appeals of Maryland, 2009)
Anderson Adventures, LLC v. Sam & Murphy, Inc.
932 A.2d 1186 (Court of Special Appeals of Maryland, 2007)
Montgomery County v. REVERE NATIONAL CORP., INC.
671 A.2d 1 (Court of Appeals of Maryland, 1996)
B. Frank Joy Co. v. Isaac
636 A.2d 1016 (Court of Appeals of Maryland, 1994)
Mardirossian Family Enterprises v. Clearail, Inc.
596 A.2d 1018 (Court of Appeals of Maryland, 1991)
NSC Contractors, Inc. v. Borders
564 A.2d 408 (Court of Appeals of Maryland, 1989)
Leaf Co. v. Montgomery County
520 A.2d 732 (Court of Special Appeals of Maryland, 1987)
Sidhu v. Shigo
484 A.2d 1033 (Court of Special Appeals of Maryland, 1984)
Miklasz v. G.W. Stone, Inc.
483 A.2d 382 (Court of Special Appeals of Maryland, 1984)
Stevens v. Cliffs at Princeville Associates
684 P.2d 965 (Hawaii Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
235 A.2d 735, 248 Md. 267, 1967 Md. LEXIS 325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shoreham-developers-inc-v-randolph-hills-inc-md-1967.