Mardirossian Family Enterprises v. Clearail, Inc.

596 A.2d 1018, 324 Md. 191, 1991 Md. LEXIS 169
CourtCourt of Appeals of Maryland
DecidedOctober 10, 1991
Docket161, September Term, 1990
StatusPublished
Cited by4 cases

This text of 596 A.2d 1018 (Mardirossian Family Enterprises v. Clearail, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mardirossian Family Enterprises v. Clearail, Inc., 596 A.2d 1018, 324 Md. 191, 1991 Md. LEXIS 169 (Md. 1991).

Opinion

KARWACKI, Judge.

The issue in this case is whether a subcontractor, seeking to establish a mechanics’ lien pursuant to Maryland Code (1974, 1988 Repl.Yol.) §§ 9-101 through 9-114 of the Real Property Article, timely notified the owner of the building under construction of its intention to claim a lien. Such notice is required by § 9-104 of the Real Property Article, which provides in pertinent part:

“(a) Notice required to entitle subcontractor to lien.—(1) A subcontractor doing work or furnishing materials or both for or about a building other than a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 90 days after doing the work or furnishing the materials, the subcontractor gives written notice of an intention to claim a lien substantially in the form specified in subsection (b) of this section____
“(c) Notice by mail or personal delivery.—The notice is effective if given by registered or certified mail, return receipt requested, or personally delivered to the owner by the claimant or his agent____
“(e) Notice by posting.—If notice cannot be given on account of absence or other causes, the subcontractor, or his agent, in the presence of a competent witness and *194 within 90 days, may place the notice on the door or other front part of the building. Notice by posting according to this subsection is sufficient in all cases where the owner of the property has died and his successors in title do not appear on the public record of the county.
“(f) Payments by owner to contractor after notice; limitation on lien against certain single family dwell ings.—(1) On' receipt of notice given under this section, the owner may withhold, from sums due the contractor, the amount the owner ascertains to be due the subcontractor giving the notice____”

The Circuit Court for Montgomery County ruled that the timely notice of intention to claim a lien required by § 9-104 had not been given and dismissed the subcontractor’s petition to establish and enforce a mechanics’ lien. That judgment was reversed by the Court of Special Appeals. Clearail v. Mardirossian, 84 Md.App. 497, 581 A.2d 36 (1990). We granted the property owner’s writ of certiorari and shall reverse the judgment of the intermediate appellate court.

I.

In the Court of Special Appeals the parties filed a joint election to proceed on an expedited basis pursuant to Maryland Rule 8-207. Accordingly, they filed the following agreed statement of the case, including the essential facts, as prescribed by Md.Rule 8-413(b):

“Pursuant to a subcontract with a general contractor, Clearail, Inc. (“Clearail”) supplied labor and materials for the installation of clear glass block railings during the construction of an office building at 18757 North Frederick Road, Gaithersburg, Montgomery County, Maryland. The owner of the property was Mardirossian Family Enterprises (“MFE”), a general partnership.
“In a petition to establish and enforce a mechanic’s lien filed in the Circuit Court for Montgomery County, Clear-ail alleged that it supplied the labor and materials from April 20, 1989 through July 19, 1989. MFE filed an *195 answer to petition denying, among other things, that Clearail gave timely notice of its intention to claim a lien under Md. Real Property Code Ann., Sec. 9-104.
“A hearing was held on March 7,1990. At the hearing, Clearail’s attorney proffered that within 90 days of July 19, 1989, he mailed two notices dated October 5, 1989, of Clearail’s intention to claim a mechanics’ lien by certified mail, return receipt requested, to MFE at the property address and to MFE’s previous office address. The certified mail receipts were postmarked October 12, 1989. 1 Both of the notices were returned with the envelopes unopened to Clearail’s attorney, and were marked by the U.S. Postal Service as “unclaimed.” On the post office receipts attached to the envelopes were the following notations:
Date
1st notice
10/20
2nd Notice
10/30
Return
“After the unclaimed notices were returned to him, Clearail’s attorney engaged a private process server to serve the notice personally on a partner in MFE. On December 11, 1989, more than 140 days after Clearail stopped its work, the process server personally delivered the notice to Aris Mardirossian, a general partner in MFE.
“It was undisputed that Clearail did not post a notice of intent to claim a lien on the building. It was also undisputed that MFE did not receive Clearail’s notice of intention to claim a lien until December 11, 1989, when a copy *196 of the notice was personally served on Aris Mardirossian.” 2

II.

A notice requirement imposed upon subcontractors who intend to establish a mechanics’ lien on property which they have improved by supplying material or labor has been included in every version of the mechanics’ lien law since the first applicable to property in this State was adopted by Ch. 205 of the Acts of 1838. Barry Properties v. Fick Bros. 277 Md. 15, 17-18, 353 A.2d 222, 224-25 (1976). We have consistently construed these notice statutes as ones enacted “for the protection of the property owner.” Barry Properties, supra at 36-37, 353 A.2d at 234-35; Himelfarb v. B & M Weld. Iron Wks., 254 Md. 37, 42, 253 A.2d 842, 844 (1969); District Hgts. Apts. v. Noland Co., 202 Md. 43, 51, 95 A.2d 90, 94 (1953); Kenly Use of Otto v. Sis. of Char., 63 Md. 306, 309 (1885). As was stated by the Kenly Court over a century ago:

“The foundation of the lien, in a case like the one before us, is the prior notice to be given to the owner. It is required for the protection of the owner, who is authorized to retain in his hands the amount due to the party giving notice. It must be given in writing and served on the owner, or his agent, if they are resident of the city or county where the building is erected. If such notice cannot be given personally on account of absence, or other causes, the claimant may then place the notice on the building____”

63 Md. at 309.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roskelly v. Lamone
912 A.2d 658 (Court of Appeals of Maryland, 2006)
Rockwood Casualty Insurance v. Uninsured Employers' Fund
867 A.2d 1026 (Court of Appeals of Maryland, 2005)
Lohman v. Lohman
613 A.2d 1015 (Court of Special Appeals of Maryland, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
596 A.2d 1018, 324 Md. 191, 1991 Md. LEXIS 169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mardirossian-family-enterprises-v-clearail-inc-md-1991.