Clearail, Inc. v. Mardirossian Family Enterprises

581 A.2d 36, 84 Md. App. 497, 1990 Md. App. LEXIS 158
CourtCourt of Special Appeals of Maryland
DecidedOctober 30, 1990
Docket808, September Term, 1990
StatusPublished
Cited by4 cases

This text of 581 A.2d 36 (Clearail, Inc. v. Mardirossian Family Enterprises) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clearail, Inc. v. Mardirossian Family Enterprises, 581 A.2d 36, 84 Md. App. 497, 1990 Md. App. LEXIS 158 (Md. Ct. App. 1990).

Opinion

BISHOP, Judge.

Clearail, Inc. (“Clearail”) appeals the dismissal by the Circuit Court for Montgomery County of its petition to establish and enforce a mechanics’ lien on property of appellee, Mardirossian Family Enterprises (“MFE”), a general partnership. The court found that appellant had not complied with the notice requirements of Md.Real Property *499 Code Ann. § 9-104. Since this case is proceeding under the expedited appeal procedures of Maryland Rule 8-207, the parties have filed an agreed statement of the case and essential facts.

ISSUE

The issue is whether appellant’s written notice of intention to claim a mechanics’ lien, sent within the statutory period by certified mail, return receipt requested, but not received by appellee until served by personal service after the statutory period, satisfies the requirements of Md.Real Property Code Ann. § 9-104.

FACTS

The following is the agreed statement:

Pursuant to a subcontract with a general contractor, Clearail, Inc. (“Clearail”) supplied labor and materials for the installation of clear glass block railings during construction of an office building at 18757 North Frederick Road, Gaithersburg, Montgomery County, Maryland. The owner of the property was Mardirossian Family Enterprises (“MFE”), a general partnership.
In a petition to establish and enforce a mechanics’ lien filed in the Circuit Court for Montgomery County, Clear-ail alleged that it supplied the labor and materials from April 20, 1989 through July 19, 1989. MFE filed an answer to the petition denying, among other things, that Clearail gave timely notice of its intention to claim a lien under Md.Real Property Code Ann. § 9-104.
A hearing was held on March 7, 1990. At the hearing, Clearail’s attorney proffered that within 90 days of July 19, 1989, he mailed two notices dated October 5, 1989 of Clearail’s intention to claim a mechanics’ lien by certified mail, return receipt requested, to MFE at the property address and to MFE’s previous office address. The certified mail receipts were postmarked October 12, 1989. Both of the notices were returned with the envelopes *500 unopened to Clearail’s attorney, and were marked by the U.S. Postal Service as “unclaimed”. On the post office receipts attached to the envelopes were the following notations:
Date 10/U
1st Notice 10/20
2nd Notice 10/S0
Return [1]
After the unclaimed notices were returned to him, Clearail’s attorney engaged a private process server to serve the notice personally on a partner in MFE. On December 11, 1989, more than 140 days after Clearail stopped its work, the process server personally delivered the notice to Aris Mardirossian, a general partner in MFE.
It was undisputed that Clearail did not post a notice of intent to claim a lien on the building. It was also undisputed that MFE did not receive Clearail’s notice of intention to claim a lien until December 11, 1989, when a copy of the notice was personally served on Aris Mardirossian.
Based upon the above facts, the Circuit Court for Montgomery County dismissed Clearail’s petition on the ground that Clearail had not complied with the notice requirements of § 9-104. Clearail appeals from the dismissal of its petition.

DISCUSSION

A.

Mechanics’ Liens in Maryland

In 1791 Maryland was the first state to enact a mechanics’ lien statute. 1791 Md.Laws, Ch. 45, § 10. This statute *501 was enacted to protect workers engaged in the construction of the nation’s capital. 2 In 1838 a mechanics’ lien statute was enacted for Baltimore City and gradually the remedy was extended to other jurisdictions within the State. 1838 Md.Laws, Ch. 205. See also, 36 Md.L.Rev. 733,736 (1977). Although mechanics’ liens were unknown at common law 3 , they exist “by virtue of a Damoclean statutory remedy within the precise ambit of which [a] claimant must place himself.” Frederick Contractors, Inc. v. Bel Pre Medical Center, Inc., 274 Md. 307, 313, 334 A.2d 526 (1975) (citations omitted). This statutory remedy functioned in approximately the same fashion for nearly two hundred years, until the Maryland Court of Appeals decided Barry Properties, Inc. v. Fick Brothers Roofing Co., 277 Md. 15, 353 A.2d 222 (1976).

The Barry case involved a mechanics’ lien obtained by Fick Brothers Roofing Co. (“Fick”), a subcontractor, on a building owned by Barry Properties, Inc. (“Barry”). Although Fick complied in all respects with the mechanics’ lien procedure then in force, Barry argued that the lien statute was incompatible with the due process clauses of Article 23 of the Maryland Declaration of Rights 4 and the *502 Fourteenth Amendment of the United States Constitution 5 because it unconstitutionally deprived Barry of its property without procedural due process of law.

The Court preliminarily determined that “mechanics’ liens involve state action since they are created, regulated and enforced by the State.” Barry, supra, at 22, 353 A.2d 222 (citations omitted). After examining four analogous Supreme Court decisions involving prejudgment creditor remedies 6 , the Court concluded that the imposition of a mechanics’ lien deprived an owner of a significant property interest without due process of law and, therefore, the Maryland statute was unconstitutional. The Court refrained from striking down the entire act, however, finding that the act’s provisions were severable. Instead, the Court resolved the constitutional problems by excising certain portions of the statute.

As a result of the Barry case the General Assembly passed emergency legislation to correct the constitutional defects found by the Court. Senate Bill 998 7 repealed and reenacted with amendments sections 9-101 through 9-113 of the Real Property Article of the Annotated Code and provided owners of real property with notice and an opportunity for a hearing prior to subjecting their property to a mechanics’ lien. Section 9-104 currently provides in part: § 9-104. Notice to owner by subcontractor.

(a)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lohman v. Lohman
613 A.2d 1015 (Court of Special Appeals of Maryland, 1992)
Mardirossian Family Enterprises v. Clearail, Inc.
596 A.2d 1018 (Court of Appeals of Maryland, 1991)
Skinner Logsdon Construction & Equipment, Inc. v. First United Church of Jesus Christ
594 A.2d 1245 (Court of Special Appeals of Maryland, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
581 A.2d 36, 84 Md. App. 497, 1990 Md. App. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clearail-inc-v-mardirossian-family-enterprises-mdctspecapp-1990.