Shapiro Engineering Corp. v. Francis O. Day Co.

137 A.2d 695, 215 Md. 373, 1958 Md. LEXIS 345
CourtCourt of Appeals of Maryland
DecidedJanuary 22, 1958
Docket[No. 125, September Term, 1957.]
StatusPublished
Cited by11 cases

This text of 137 A.2d 695 (Shapiro Engineering Corp. v. Francis O. Day Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shapiro Engineering Corp. v. Francis O. Day Co., 137 A.2d 695, 215 Md. 373, 1958 Md. LEXIS 345 (Md. 1958).

Opinion

Henderson, J.,

delivered the opinion of the Court.

This appeal in a non-jury case is from a judgment for $12,412.23, in an action for breach of a written contract, dated December 2, 1954, whereby the appellee, plaintiff, agreed to construct storm sewers in Oakwood Knolls Subdivision, Bethesda, Maryland, and the appellant, defendant, to pay therefor an aggregate price of $43,000.00 The subdivision was laid out in two sections. Tots had been sold and some houses were under construction in the first section, so that construction was urgent. No lots had been sold in Section II. After completing substantially all of the work in the first section, the plaintiff declined to perform the work in the second section, on the ground that the defendant had failed to pay for the work performed and materials furnished in the first section, and had failed to obtain the necessary permits to enable it to perform the work in the second. It brought suit to recover the balance due and damages. The appellant defended on the ground that it was justified in refusing payment until all the work was fully completed, alleging that the contract was entire and indivisible, and that the *376 plaintiff committed an anticipatory breach of the contract by indicating its intention not to proceed with work in the second section at a time when there was a bona fide dispute as to payment for the work completed. The appellant also contends that the court applied the wrong measure of damages, and the proof did not support the damages allowed.

The contract is not a model of clarity. The construction work was required to be in conformity with the standards and specifications of the Montgomery County Department of Public Works and in conformity with a permit issued November 12, 1954, by the State Roads Commission. Under the heading “ARTICLE II, SCHEDULE OF PAYMENTS”, it was provided that the builder “shall submit a requisition for any portion of his work completed thru 25th of each month in accordance with this schedule of payments and shall be paid for the requisition on the following 10th of month (less 10%) and title to all said material, whether placed in warehouse or on building site or building itself shall immediately vest in the owner of the property”. A form of progress payments was deleted, and typed in its place was the following: “The work completed for any monies requisitioned shall have the same ratio to the total work and the total contract price respectively.” Article I C. provided: “The term work as referred to herein shall include all labor, material, and equipment necessary to the prosecution of this contract.” (Italics supplied.) Another article provided that final payment was to be made on the 10th of the month following acceptance by the public authorities. Work was to commence not later than December 6, 1954, and that portion outlined on a designated “Paving Plan” was to be completed within forty working days. Presumably, this referred to Section I. There was no provision as to the time for commencing or completing Section II, although there was testimony of an oral understanding that the builder would proceed with Section II as soon as Section I was completed.

Attached to the contract was an addendum, signed by the defendant only, wherein the defendant undertook to furnish an engineer who would supply cut sheets and do all layout work. The addendum also provided that if rock was en *377 countered a price for its removal would be negotiated. The addendum also contained this clause: “Section I which is outlined on the Paving Plan shall amount to Twenty three thousand dollars ($23,000.00), and Section II will amount to Twenty thousand dollars ($20,000.00), for purposes of paying on account of this contract only.”

The plaintiff began work immediately, but there were delays occasioned by the failure of the engineer supplied by the defendant, as the trial court found, to perform his work “with that degree of skill which the plaintiff had a right to expect”. Specifically, the complaints were that the outlets were not properly staked out on the ground, and that the outfall shown on the plan was actually located on the property of an adjoining owner. On December 26, 1954, the plaintiff submitted its bill for $11,681.00 for work allegedly performed in accordance with the contract. On January 13, 1955, the defendant paid $10,619.00 on account, with an accompanying letter in which it complained that the requisition set forth quantities of material, labor, equipment and profit, and deducted 10% from the gross amount. The letter stated that the requisition “has no bearing on the contract because the contract is a lump sum, contract with payments due on the tenth of the month for any portion of the work completed through the 25th of the previous month less 10% retainer for final payment. Based on the above we estimate your completion as of December 25, 1954 as 51.3% for a gross amount due $11,719.00 (sic) less retainer of $1,179.90, making an, amount due this payment of $10,619.10 for Section 1.”

On January 25, 1955, the plaintiff submitted its bill for $8,439.00 for additional work claimed to have been completed. This bill was not paid, nor was any explanation given as to why it was not paid. The plaintiff claims that it had then completed all of the work in Section I which it could perform, and that it could not finish the work completely because the outfall shown on the plan was actually' located on the land of another owner, who would not permit it to enter until a right of way was procured. This right of way had apparently not been obtained at the time suit was filed on June 28, 1955. The plaintiff also claims that no *378 permit had been procured for the work in Section II, and that in fact no permit was obtained until the summer of 1955.

No payment has ever been received on the requisition of January 25, 1955. There was testimony that the plaintiff declined to do the work in Section II because of the failure to pay for the work performed in Section I, and because of the failure to procure a permit for Section II within a reasonable time. There was testimony that it kept equipment on the job for at least a month after Section I was completed. (This was probably in April, after the County’s approval was obtained for all the work, except the outfall.) The defendant maintained that its reason for not paying the requisition was because the plaintiff had declared its intention not to go ahead with the work in Section II, which it relies on as an anticipatory breach. It also claimed that some of the work done in Section I was not up to standard, that the requisition was not based on work completed, and that there were offsets to the claim. It is undisputed, however, that no permit for the work in Section II was obtained until June 27, 1955, the last permit being in September, 1955.

The trial court found no justification for the failure of the defendant to pay the requisition of January 25, 1955, or a substantial part thereof. We agree. The items set out in the requisitions were within the fair meaning of “work” as defined, and the fact that title passed as to materials not yet in place supports this construction. The garbled clause as to a ratio between total work and total contract price could hardly change the meaning of “work completed” into a percentage of overall completion of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mardirossian Family Enterprises v. Clearail, Inc.
596 A.2d 1018 (Court of Appeals of Maryland, 1991)
Pioneer Roofing Co. v. Mardian Construction Co.
733 P.2d 652 (Court of Appeals of Arizona, 1986)
Bart Arconti & Sons, Inc. v. Ames-Ennis, Inc.
340 A.2d 225 (Court of Appeals of Maryland, 1975)
Fairchild Stratos Corporation v. Lear Siegler, Inc.
337 F.2d 785 (Fourth Circuit, 1964)
K & G CONSTRUCTION CO. v. Harris
164 A.2d 451 (Court of Appeals of Maryland, 1960)
Fromm Sales Co. v. Troy Sunshade Co.
159 A.2d 860 (Court of Appeals of Maryland, 1960)
Petropoulos v. Lubienski
152 A.2d 801 (Court of Appeals of Maryland, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
137 A.2d 695, 215 Md. 373, 1958 Md. LEXIS 345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shapiro-engineering-corp-v-francis-o-day-co-md-1958.