Petropoulos v. Lubienski

152 A.2d 801, 220 Md. 293
CourtCourt of Appeals of Maryland
DecidedJune 25, 1959
Docket[No. 216, September Term, 1958.]
StatusPublished
Cited by12 cases

This text of 152 A.2d 801 (Petropoulos v. Lubienski) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petropoulos v. Lubienski, 152 A.2d 801, 220 Md. 293 (Md. 1959).

Opinion

*296 Hornby, J.,

delivered the opinion of the Court.

In a suit by Helen A. U. Rubienski, executrix of the estate of Paul S. Rubienski (the builder) against George P. Petropoulos and Georgette Z. Petropoulos, his wife (the owners) for damages arising out of the breach of a building contract, the Circuit Court for Montgomery County sitting without a jury entered a judgment in favor of the builder against the owners. The owners appealed. In addition to the initial argument, there was a limited reargument.

On April 15, 1955, the owners and builder entered into a written contract whereby the builder agreed to build a house for the owners in accordance with attached plans and specifications for $43,000, less an allowance of $350.

When the owners became dissatisfied with the builder’s work in September of 1955 because requested changes had not been made and certain items of work were not in accordance with the contract, the builder submitted a bill for the “extras” he claimed. Claiming that some of the extras had not been authorized and that some of the claimed extras were not in fact extras, the owners refused to pay the bill as rendered.

When the parties were unable to adjust their differences, the owners notified the builder that they wished to have the controversy submitted to arbitration in accordance with the terms of the contract. After considerable bickering, each party chose his respective arbitrator and the two chose an umpire or referee as the third member of the panel. When differences arose between the arbitrators as to the method of procedure and the time they should devote to arriving at an award, the arbitrator chosen by the owners resigned, whereupon the owners not only claimed a right to replace their arbitrator but insisted on the selection of a new arbitration board. The builder declined to accede to the selection of a new panel and the remaining arbitrators made their report two days later. The report allowed the builder $3,475 for extras—subsequently reduced to $2,475 by the court when it declined to allow $1,000 for certain plans—which the owners would not pay. When the owners refused to accept the award for extras, the builder countered by refusing to complete the house. The *297 owners thereupon made other arrangements to have the house finished at a cost of $14,150 plus $1,250 for completion plans.

The builder filed suit for breach of contract on July 18, 1956. He died in March of 1957, and his executrix was substituted as party plaintiff. There were four claims in the declaration: (1) a claim for the whole contract price; (2) a claim for the extras; (3) a claim for the arbitration award; and (4) a claim for moneys payable under the common counts. The owners counterclaimed for the cost of completing the house, damages for delay in completion and the cost of correcting defective work.

At the trial the parties were able to agree and it was stipulated that the builder had expended at least $25,359.75 for materials furnished and work done in the construction of the house. In addition to this sum, the builder offered proof that he had also expended $12,624.86 for other materials, work and “administrative costs or overhead,” but the trial court allowed only $10,925.11 for these additional charges. The stipulated sum, plus the additional charges allowed, totaled $36,284.86. While the record is not entirely clear, it appears —indeed it was conceded at the reargument—that this total of $36,284.86 includes the value of certain materials and work for which a promissory note of $1,784 had been given by the owners to the builder for certain extras as well as the sum of $2,475 which the arbitrators allowed for other extras. There is a dispute as to whether the note, although not paid, was included in the stipulated credits referred to below. The builder claims that it was included; the owners insist that it was not. A re-examination of the record on this point since the reargument certainly indicates that the note was not included in the stipulated sum of $31,397, representing credits due the owners. It also appears that the trial court excluded the note. In addition to the sum stipulated it was further agreed that the owners had paid $510 on account of a mechanics’ lien the builder allowed to be filed against the house. And the court also allowed the owners a credit of $740 for defective work on the stairway and for other miscellaneous items. The total credits were therefore $32,647.

The trial court, in arriving at the amount of its judgment *298 nisi apparently proceeded on the theory that, the owners having refused to perform their part of the contract, the builder was entitled to rescind the contract and sue on quantum meruit, i. e., for as much as he deserved. But, in addition to finding that the builder had expended $36,284.86 for materials furnished and work done and for administrative costs and overhead, the court added a 10% profit, or $3,628.48, and erroneously also added the $1,784 note and the $2,475 arbitration award—both of which, it is now conceded, were included in the figure of $36,284.86—in its computation of total charges of $44,172.34. On the excess of the charges over the credits, or $11,525.34, the court allowed interest from July 18, 1956, the date of the filing of the suit, and entered a judgment nisi on September 10, 1958, for $12,920.62.

The owners, contending that it was the builder, and not they, who had breached the building contract, insist that the trial court erred when it found to the contrary. The owners further contend that the court did not apply the correct measure of damages. We agree that the trial court did err in several respects, all of which can be rectified without a remand. But we do not agree that the court was wrong when it found that the owners had breached the contract.

(i)

The owners claim that they refused to accept the arbitration award because the arbitrators refused to hear testimony as to whether the claimed extras had been authorized by the owners; because the arbitrators refused to consider the plans and specifications as a part of the building contract; because the arbitrators had included in the award a charge of $1,000 for plans which had been included in the contract price; and because the award had not been made by a panel of three arbitrators. The record shows that it was the owners, who, by letter dated October 13, 1955, had notified the builder to cease all work and to accept that letter as a demand for arbitration. The record also shows that after the owners’ arbitrator had resigned, the owners, in addition to requesting an opportunity to replace him, also demanded the selection of a “new” arbitration board. The builder declined to accede to the demand for *299 a new board, and, when the owners refused to pay the award for extras, he would not resume the construction of the house. The trial court, which had an opportunity to see and hear the witnesses and to judge their credibility, found as a fact that the owners’ refusal to pay for the extras was not justified and that the failure to accept the award constituted a breach of the contract which excused further performance by the builder, and we find nothing in the record to show that the trial court, in so finding, was clearly in error. Rule 886 a.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Y.Y. v. State
46 A.3d 1223 (Court of Special Appeals of Maryland, 2012)
Alternatives Unlimited, Inc. v. New Baltimore City Board of School Commissioners
843 A.2d 252 (Court of Special Appeals of Maryland, 2004)
Mogavero v. Silverstein
790 A.2d 43 (Court of Special Appeals of Maryland, 2002)
Woodhaven Homes, Inc. v. Kennedy Sheet Metal Co.
803 S.W.2d 508 (Supreme Court of Arkansas, 1991)
Printers Ii, Inc. v. Professionals Publishing, Inc.
784 F.2d 141 (Second Circuit, 1986)
Murdock-Bryant Construction, Inc. v. Pearson
703 P.2d 1206 (Court of Appeals of Arizona, 1984)
Della Ratta, Inc. v. American Better Community Developers, Inc.
380 A.2d 627 (Court of Special Appeals of Maryland, 1977)
Royal Manor Apartments v. Powell
523 S.W.2d 909 (Supreme Court of Arkansas, 1975)
Hoffman v. Glock
315 A.2d 551 (Court of Special Appeals of Maryland, 1974)
A. S. Abell Co. v. Barnes
265 A.2d 207 (Court of Appeals of Maryland, 1970)
Weinberg v. Desser
221 A.2d 66 (Court of Appeals of Maryland, 1966)
Mangione v. Braverman
199 A.2d 225 (Court of Appeals of Maryland, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
152 A.2d 801, 220 Md. 293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petropoulos-v-lubienski-md-1959.