Bianchi Bros. v. Gendron

198 N.E. 767, 292 Mass. 438, 107 A.L.R. 953, 1935 Mass. LEXIS 1271
CourtMassachusetts Supreme Judicial Court
DecidedNovember 25, 1935
StatusPublished
Cited by26 cases

This text of 198 N.E. 767 (Bianchi Bros. v. Gendron) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bianchi Bros. v. Gendron, 198 N.E. 767, 292 Mass. 438, 107 A.L.R. 953, 1935 Mass. LEXIS 1271 (Mass. 1935).

Opinion

Pierce, J.

Several suits in equity were brought under G. L. (Ter. Ed.) c. 149, § 29, by plaintiffs and interveners [439]*439to enforce claims for labor performed and materials furnished for the construction of two buildings for the city of Worcester. The defendants are Alcide J. Gendron, the general contractor, the Standard Surety and Casualty Company of New York, the surety on the bond given by Gendron to the city of Worcester, and the city of Worcester, which has in its hands and possession money earned by Gendron under the contracts. The work performed consisted in the construction of two buildings, one known as the “sewer building” and the other as the “school house,” and was performed under separate contracts. The only matter here in controversy relates to the work done on the “school house.” The two suits arising out of work done on the school house were consolidated by an interlocutory decree in the Superior Court. The suits were referred to a master under the usual rule. The master made findings in detail as to the amount due each of the claimants.

The appellant in its brief states, and we assume the statement is accurate, that “The claims of the original petitioners and of all intervening petitioners as established by the final decree herein appealed from, with the sole exception of the claim of Israel Nagel, have been settled, those appearing in paragraph 2 of said decree, since the trial of this action, through the payment by defendant Standard Surety & Casualty Company of New York.” This concession of the appellant leaves open only the claim of said Nagel and the claim of the defendant surety against the defendant city, the surety alleging to have been damaged through the failure of the city to retain fifteen per cent of the final contract price, after due allowance had been made for all proper extras and deductions, “$114,865 . . . or $17,229.75, as well as the sum of $7,045.81 retained by the said city under an optional clause in said contract authorizing but not requiring it to retain out of funds otherwise due said contractor sums sufficient to discharge any liens or other unpaid claims for labor and materials of which it should have knowledge, at the time such payments were otherwise due ... as required by the terms of said contract between said city and said contractor.” The appellant further con[440]*440tends that a payment of $10,200 from said retained percentage, being the final payment on list #1 under said contract on July 20, 1932, was an overpayment or premature payment by the city to the contractor, and it claims to have been damaged to said amount through failure of the city to retain that sum so that the same might be available to it for its indemnification and reimbursement, and applied in diminishment of its losses through its having expended the sum of $29,398.18 in discharging valid and enforceable liens, as, it is contended, the city was obligated to do, by the terms of the contract.

An interlocutory decree in the Superior Court confirmed the master’s reports and a final decree dismissed the surety’s claim against the city. The said surety appealed from the rulings of law made by the judge, from all interlocutory decrees entered thereunder, and from the final decree.

On the principal issue of the overpayment or premature payment of $10,200, from the contract itself (incorporated in the record as an exhibit) and the master’s reports the following facts appear: By an instrument dated June 2, 1931, Alcide J. Gendron contracted to build the “shell” of a school house which was to be known as the Heard Street School. Under article I of said contract there is the provision: “All of the work to be performed under this contract is set forth on List #1 hereto attached, which drawings and specifications and bulletins are made a part of this contract and identified by the signatures of the parties hereto.” After certain provisions relative to the manner in which the work was to be carried on, article XV is as follows: “It is hereby mutually agreed between the parties hereto that the sum to be paid by the City to the Contractor for said work and materials shall be $68,000.00 . . . subject to additions and deductions as hereinbefore provided, and that such sum shall be paid in current funds by the City to the Contractor in installments, as follows: The cost of labor and materials incorporated into the building during each month shall be paid on the twentieth day of the succeeding month, except fifteen per cent, thereof shall be retained each month by the City until the [441]*441expiration of the contract, and until all of its conditions and specifications shall have been fulfilled by the Contractor, and provided that all monthly bills shall be presented by noon of the first day of the month next succeeding, and presented in duplicate, and duly approved by the City Auditor of the City of Worcester. The payments shall be made according to the attached List #1 on a ‘percentage of work done’ basis.” Then follows a detailed “Estimate of materials and labor to complete Heard Street School as per proposal for shell” totalling $68,000. “The final payment shall not be made within sixty-one days after this contract is fulfilled. No payment shall be made without the written certificate of the Architects to the effect that such payment has become due. If at any time there shall be evidence of any lien or other claim for which, if established, the City or the said premises might become liable, directly or indirectly, and which is chargeable to the Contractor, the City shall have the right to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify its [sic] against any such claim. Should there prove to be any such claim after all payments are made, the Contractor shall refund to the City all moneys that the latter may be compelled to pay in discharging any such claim made obligatory in consequence of the Contractor’s default.”

At the end of the contract, before the signatures thereto, the following paragraph appears: “It is further mutually agreed that if the City of Worcester appropriates sufficient money therefor on or before December 31, 1931, that the Contractor will complete said Heard Street School by furnishing all the labor and material necessary to do all the work enumerated on List #2, attached hereto and made a part hereof, for the additional price of $44,865.00. All the additional work contemplated by this paragraph shall be performed in full compliance with the plans, specifications and bulletins referred to above and all the terms of the main contract.” Next follows detailed “Estimate of materials and labor to complete Heard St. School as per proposal #2.” By letter dated February 4, 1932, the superintendent of [442]*442public buildings of the city of Worcester notified Alcide J. Gendron of the appropriation of money by the city for the work under list #2 as follows: “You are advised that the City Council appropriated sufficient money to complete the Heard Street School, December 21, 1931, approved by the Mayor, December 23, 1931. According to the contract which you have with the City of Worcester and as stated in that contract on Page 5, following Art. XXIV, then you are to furnish all the labor and material necessary to do all the work enumerated on List #2, attached to and made a part of your contract for the sum stated in said contract. By the appropriation of the money, List #2 is made a part of the main contract and is subject to all the terms, agreements and conditions of the main contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coady v. Wellfleet Marine Corp.
816 N.E.2d 124 (Massachusetts Appeals Court, 2004)
Flannery v. Flannery
705 N.E.2d 1140 (Massachusetts Supreme Judicial Court, 1999)
In Re Camptown, Ltd.
96 B.R. 352 (M.D. Florida, 1989)
In Re Gardinier, Inc.
50 B.R. 491 (M.D. Florida, 1985)
Potter & McArthur, Inc. v. City of Boston
446 N.E.2d 718 (Massachusetts Appeals Court, 1983)
Katz v. Pulaski Savings & Loan Ass'n
546 S.W.2d 24 (Missouri Court of Appeals, 1976)
Cannon, Namroc & Associates, Inc. v. Max Sontz Co.
59 Mass. App. Dec. 64 (Mass. Dist. Ct., App. Div., 1976)
Norton v. McIntosh
461 P.2d 348 (Court of Appeals of Washington, 1969)
Carlo Bianchi & Co. v. Builders' Equipment & Supplies Co.
199 N.E.2d 519 (Massachusetts Supreme Judicial Court, 1964)
Bowden v. Elias
21 Mass. App. Dec. 45 (Mass. Dist. Ct., App. Div., 1961)
Shapiro Engineering Corp. v. Francis O. Day Co.
137 A.2d 695 (Court of Appeals of Maryland, 1958)
Holiday Homes, Inc. v. Briley
122 A.2d 229 (District of Columbia Court of Appeals, 1956)
Faust v. General Finance & Loan Co.
84 S.E.2d 118 (Court of Appeals of Georgia, 1954)
Levine v. Reynolds
54 A.2d 514 (Supreme Judicial Court of Maine, 1947)
Board of Com'rs of Kingfisher County v. Vahlberg
1947 OK 100 (Supreme Court of Oklahoma, 1947)
Brightwater Paper Co. v. Monadnock Paper Mills
68 F. Supp. 714 (D. Massachusetts, 1946)
Kilham v. O'Connell
54 N.E.2d 181 (Massachusetts Supreme Judicial Court, 1944)
Durant v. Snyder
151 P.2d 776 (Idaho Supreme Court, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
198 N.E. 767, 292 Mass. 438, 107 A.L.R. 953, 1935 Mass. LEXIS 1271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bianchi-bros-v-gendron-mass-1935.