Perdoni Brothers Inc v. Concrete Sytems Inc

35 F.3d 1, 1994 WL 466008
CourtCourt of Appeals for the First Circuit
DecidedSeptember 6, 1994
Docket93-2178
StatusPublished
Cited by41 cases

This text of 35 F.3d 1 (Perdoni Brothers Inc v. Concrete Sytems Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perdoni Brothers Inc v. Concrete Sytems Inc, 35 F.3d 1, 1994 WL 466008 (1st Cir. 1994).

Opinion

CYR, Circuit Judge.

Defendant-appellant Concrete Systems, Inc. (CSI), a New Hampshire producer of pre-cast concrete products, contracted in 1985 with plaintiff-appellee Perdoni Brothers, Inc. (Perdoni), a Massachusetts-based construction firm, to manufacture and deliver 121 custom-designed manholes, at a total contract price of $51,670.47, for installation in a new sewer system in the Town of Ashland, Massachusetts. CSI contends that the district court committed reversible error in denying its post-verdict motion for judgment as a matter of law. See Fed.R.Civ.P. 50. For the reasons hereinafter discussed, we affirm the district court judgment.

I

BACKGROUND

The first five manholes were delivered to the Perdoni job site by CSI on July 2, 1985. The remaining 116 manholes were delivered intermittently in twenty-six shipments extending over the next thirteen months and invoiced by individual shipment.

Dissatisfied with the CSI manholes (which leaked and had to be patched), 1 Perdoni brought this diversity action in federal district court on April 25, 1990, demanding $134,000 in compensatory damages for breach of the implied warranties of merchantability and fitness for a particular purpose (implied warranty claims), see Mass. Gen.L. ch. 106 §§ 2-314, 2-315, and additional damages based on a deceptive trade practices claim under Mass.Gen.L. ch. 93A (“Chapter 93A”). CSI counterclaimed for $18,561 allegedly due from Perdoni on the Ashland project and another contract.

Trial was held before a magistrate judge, with the consent of the parties. See 28 U.S.C. § 636(c). The implied warranty claims were tried to a jury, while the Chapter 93A claim was tried to the presiding magistrate judge. It was not until after the close of all the evidence that CSI first moved for judgment as a matter of law on the implied warranty claims relating to 108 of the 121 manholes. The uncontroverted evidence demonstrated that only 13 manholes had been delivered by CSI within four years of the commencement of the present action. CSI accordingly contended that Perdoni’s implied warranty claims relating to the other 108 manholes were time-barred under Mass. Gen.L. ch. 106 § 2-725(1) (prescribing four-year limitation on Uniform Commercial Code warranty actions); id. § 2-725(2) (action for breach of warranty under UCC accrues on “tender of delivery” of goods). The magistrate judge denied CSI’s motion for judgment as a matter of law.

Thereafter, the magistrate judge convened a charge conference to consider the jury instructions, including the instruction on the statute-of-limitations defense. Neither party requested an instruction on the law governing the severability-entirety issue. Although Perdoni unsuccessfully sought an instruction that the contract should be considered an entirety, CSI made no corresponding request for an instruction that the contract be considered severable. Consequently, the magistrate judge simply instructed the jury that CSI had the burden of proving that the action was time-barred, and that the four-year limitation period ran from the “time of delivery.” Although both parties argued the severability-entirety issue, the court made no explicit reference to it and neither party *3 objected to the jury instruction as given. 2

The jury found in favor of Perdoni for $48,961, and in favor of CSI for $18,561 on its counterclaim. CSI then renewed its Rule 50 motion for judgment as a matter of law and, alternatively, moved for a new trial under Fed.R.Civ.P. 59. The magistrate judge did not address the merits of the CSI motion, however, ruling instead that CSI had waived its severability claim, both by failing to object to the jury instruction and by failing to raise the severability argument in its pre-verdict Rule 50 motion. 3 Nonetheless, the magistrate judge, sitting as trier of fact, found Perdoni’s Chapter 93A claim time-barred as it pertained to 108 of the 121 manholes. CSI appealed the denial of its post-verdict motion for judgment as a matter of law or for a new trial on the implied warranty claims. See Fed.R.Civ.P. 50(b), 59. CSI’s primary appellate target is the district court’s waiver ruling on the severability issue.

II

DISCUSSION

Leaving aside CSI’s failure to object to the jury instruction on the statute-of-limitations defense, the district court waiver ruling is fully supported by CSI’s failure to raise the severability argument in its pre-verdict motion for judgment as a matter of law. The law is crystal clear that a “party may not base its motion for a judgment n.o.v. on a ground that was not argued in its motion for directed verdict.” Sweeney v. Westvaco Co., 926 F.2d 29, 37 (1st Cir.) (citing Systemized of New England, Inc. v. SCM, Inc., 732 F.2d 1030, 1035 (1st Cir.1984)), cert. denied, — U.S. —, 112 S.Ct. 274, 116 L.Ed.2d 226 (1991); see also 9 Charles A. Wright & Arthur R. Miller, Federal Practice & Procedure § 2537 (1971) (“Since it is technically only a renewal of the motion ... made at the close of evidence, [a post-verdict Rule 50 motion] cannot assert a ground that was not included in the motion for a directed verdict.”); 5A James W. Moore, Moore’s Federal Practice ¶ 50.08 (2d ed. 1994) (same). Sweeping invocations of conclusory theories or abstract principles will not suffice: “The motion must ... be made with sufficient specificity to allow the district court to understand precisely why the evidence is insufficient.” Wells Real Estate, Inc. v. Greater Lowell Bd. of Realtors, 850 F.2d 803, 810 (1st Cir.), cert. denied, 488 U.S. 955, 109 S.Ct. 392, 102 L.Ed.2d 381 (1988); Pstragowski v. *4 Metropolitan Life Ins. Co., 553 F.2d 1, 3 (1st Cir.1977) (where Rule 50 motion was silent as to the legal theory that plaintiff was obliged to establish malice on the part of the defendant, there was no basis for an appellate challenge to the sufficiency of the evidence on the element of malice). Ultimately, of course, “[a]ppellate review may be obtained only on the specific ground stated in the motion for directed verdict.” Wells Real Estate, 850 F.2d at 810; Pstragowski, 553 F.2d at 3 (same).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reiss v. Baron
S.D. New York, 2022
Covidien LP v. Esch
D. Massachusetts, 2019
MAZ Partners LP v. Shear
265 F. Supp. 3d 109 (D. Massachusetts, 2017)
Baker v. Goldman Sachs & Co.
949 F. Supp. 2d 298 (D. Massachusetts, 2013)
Klairmont v. Gainsboro Restaurant, Inc.
465 Mass. 165 (Massachusetts Supreme Judicial Court, 2013)
Empire Today, LLC v. National Floors Direct, Inc.
788 F. Supp. 2d 7 (D. Massachusetts, 2011)
Professional Services Group, Inc. v. Town of Rockland
515 F. Supp. 2d 179 (D. Massachusetts, 2007)
Massachusetts Eye and Ear Infirmary v. QLT, INC.
495 F. Supp. 2d 188 (D. Massachusetts, 2007)
Chrabaszcz v. Johnston School Committee
474 F. Supp. 2d 298 (D. Rhode Island, 2007)
Werderman v. Liberty Ventures, LLC
857 N.E.2d 320 (Appellate Court of Illinois, 2006)
Attrezzi, LLC v. Maytag Corporation
436 F.3d 32 (First Circuit, 2006)
RGJ Associates, Inc. v. Stainsafe, Inc.
338 F. Supp. 2d 215 (D. Massachusetts, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
35 F.3d 1, 1994 WL 466008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perdoni-brothers-inc-v-concrete-sytems-inc-ca1-1994.