Perdoni Brothers Inc v. Concrete Sytems Inc

Procedural entryThis page is a short order in Perdoni Brothers Inc v. Concrete Sytems Inc. Read the opinion of the Court — 35 F.3d 1
Court of Appeals for the First Circuit·Decided September 6, 1994·No. 93-2178·Published

Opinion

USCA1 Opinion


UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT

____________________
No. 93-2178

PERDONI BROTHERS, INC.,

Plaintiff, Appellee,

v.

CONCRETE SYSTEMS, INC.,

Defendant, Appellant.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Joyce L. Alexander, U.S. Magistrate Judge]
_____________________

____________________

Before

Breyer,* Chief Judge,
___________

Campbell, Senior Circuit Judge,
____________________

and Cyr, Circuit Judge.
_____________

____________________

John M. Lovely, with whom Daniel F. Cashman and Gelerman &
_______________ ___________________ ___________
Cashman were on brief for appellant.
_______
Valeriano Diviacchi, with whom Diviacchi Law Office was on brief
___________________ ____________________
for appellee.

____________________

September 2, 1994

____________________

____________________

*Chief Judge Stephen Breyer heard oral argument in this matter,
but did not participate in the drafting or the issuance of the panel
opinion. The remaining two panelists therefore issue this opinion
pursuant to 28 U.S.C. 46(d).

CYR, Circuit Judge. Defendant-appellant Concrete
CYR, Circuit Judge
______________

Systems, Inc. (CSI), a New Hampshire producer of pre-cast con-

crete products, contracted in 1985 with plaintiff-appellee

Perdoni Brothers, Inc. (Perdoni), a Massachusetts-based construc-

tion firm, to manufacture and deliver 121 custom-designed man-

holes, at a total contract price of $51,670.47, for installation

in a new sewer system in the Town of Ashland, Massachusetts. CSI

contends that the district court committed reversible error in

denying its post-verdict motion for judgment as a matter of law.

See Fed. R. Civ. P. 50. For the reasons hereinafter discussed,
___

we affirm the district court judgment.

I
I

BACKGROUND
BACKGROUND
__________

The first five manholes were delivered to the Perdoni

job site by CSI on July 2, 1985. The remaining 116 manholes were

delivered intermittently in twenty-six shipments extending over

the next thirteen months and invoiced by individual shipment.

Dissatisfied with the CSI manholes (which leaked and

had to be patched),1 Perdoni brought this diversity action in

____________________

1Sewer line manholes must be watertight. A common point of
leakage is the area where the sewer lines enter the manhole
structure. Precise casting, as well as installation of rubber
"boots" to ensure a tight fit between the wall of the structure
and the sewer line itself, is necessary to ensure the integrity
of the manhole. At trial, Perdoni adduced evidence that CSI had
used a defective hole former to cast the manholes for the Ashland
project. Consequently, the pipe openings in the sides of the
manholes were misshapen and the seals between the boot and rim of
the openings were not watertight.

2

federal district court on April 25, 1990, demanding $134,000 in

compensatory damages for breach of the implied warranties of

merchantability and fitness for a particular purpose (implied

warranty claims), see Mass. Gen. L. ch. 106 2-314, 2-315, and
___

additional damages based on a deceptive trade practices claim

under Mass. Gen. L. ch. 93A ("Chapter 93A"). CSI counterclaimed

for $18,561 allegedly due from Perdoni on the Ashland project and

another contract.

Trial was held before a magistrate judge, with the

consent of the parties. See 28 U.S.C. 636(c). The implied
___

warranty claims were tried to a jury, while the Chapter 93A claim

was tried to the presiding magistrate judge. It was not until

after the close of all the evidence that CSI first moved for

judgment as a matter of law on the implied warranty claims

relating to 108 of the 121 manholes. The uncontroverted evidence

demonstrated that only 13 manholes had been delivered by CSI

within four years of the commencement of the present action. CSI

accordingly contended that Perdoni's implied warranty claims

relating to the other 108 manholes were time-barred under Mass.

Gen. L. ch. 106 2-725(1) (prescribing four-year limitation on

Uniform Commercial Code warranty actions); id. 2-725(2) (action
___

for breach of warranty under UCC accrues on "tender of delivery"

of goods). The magistrate judge denied CSI's motion for judgment

as a matter of law.

Thereafter, the magistrate judge convened a charge

conference to consider the jury instructions, including the

3

instruction on the statute-of-limitations defense. Neither party

requested an instruction on the law governing the severability-
___

entirety issue. Although Perdoni unsuccessfully sought an

instruction that the contract should be considered an entirety,

CSI made no corresponding request for an instruction that the

contract be considered severable. Consequently, the magistrate

judge simply instructed the jury that CSI had the burden of

Free access — add to your briefcase to read the full text and ask questions with AI

Perdoni Brothers Inc v. Concrete Sytems Inc, (1st Cir. 1994).

Perdoni Brothers Inc v. Concrete Sytems Inc (Perdoni Brothers Inc v. Concrete Sytems Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Curtis v. Loether
415 U.S. 189 (Supreme Court, 1974)
Veiga v. McGee
26 F.3d 1206 (First Circuit, 1994)
Wolverine Insurance Co. v. Tower Iron Works, Inc.
370 F.2d 700 (First Circuit, 1966)
Systemized of New England, Inc. v. Scm, Incorporated
732 F.2d 1030 (First Circuit, 1984)
Chat Phav v. Trueblood, Inc.
915 F.2d 764 (First Circuit, 1990)
Fowler v. Land Management Groupe, Inc.
978 F.2d 158 (Fourth Circuit, 1992)
Scruggs v. Quality Electric Services, Inc.
320 S.E.2d 49 (Court of Appeals of South Carolina, 1984)
Manzaro v. McCann
519 N.E.2d 1337 (Massachusetts Supreme Judicial Court, 1988)
Carlo Bianchi & Co. v. Builders' Equipment & Supplies Co.
199 N.E.2d 519 (Massachusetts Supreme Judicial Court, 1964)
Bay State-Spray & Provincetown Steamship, Inc. v. Caterpillar Tractor Co.
533 N.E.2d 1350 (Massachusetts Supreme Judicial Court, 1989)
1901 Wyoming Avenue Cooperative Ass'n v. Lee
345 A.2d 456 (District of Columbia Court of Appeals, 1975)
In Re the Estate of Wilson
405 N.E.2d 220 (New York Court of Appeals, 1980)