Carlo Bianchi & Co. v. Builders' Equipment & Supplies Co.

199 N.E.2d 519, 347 Mass. 636, 1964 Mass. LEXIS 813
CourtMassachusetts Supreme Judicial Court
DecidedJune 16, 1964
StatusPublished
Cited by39 cases

This text of 199 N.E.2d 519 (Carlo Bianchi & Co. v. Builders' Equipment & Supplies Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlo Bianchi & Co. v. Builders' Equipment & Supplies Co., 199 N.E.2d 519, 347 Mass. 636, 1964 Mass. LEXIS 813 (Mass. 1964).

Opinion

*638 Reardon, J.

These are two actions arising out of a contract for the rental or sale of a concrete batching plant, a track site unloader, and a clamshell bucket, entered into between a construction contractor, Carlo Bianchi & Company, Inc. (Bianchi) and a lessor and seller of construction equipment, Builders’ Equipment & Supplies Company (Builders).

In the first case Bianchi, claiming special damages, sues for breach of express and implied warranties. The second case is an action by Builders for rent due on the equipment, attorney’s fees, services rendered, and expenses. After consolidation for trial the cases were heard by an auditor whose findings of fact were not to be final. 2 The auditor found breach of express and implied warranties and assessed damages for Bianchi at $28,017.23 plus $3,157.87 for a total of $31,175.10. He also made findings on the value of rent, repairs, incidental expenses, and attorney’s fees but left to the court the determination of Bianchi’s liability for those items. At a subsequent trial before a judge sitting without jury the evidence consisted of the auditor’s report and certain other testimony, and there was a finding for Bianchi in the first case in the sum of $36,881.01 ($28,017.23 only plus interest) and one for Builders in the second case in the sum of $13,206.35. The cases are here upon numerous exceptions by both parties to rulings of the trial judge.

The auditor found as follows. Bianchi, a contractor with many years of experience, has engaged in a great deal of heavy construction on large projects, including work on concrete paving. While Bianchi has handled “concrete on a large scale regularly for forty or fifty years ... [it has] conducted concrete paving operations only as general contractor supervising a subcontractor, during the last twenty years or so. This removal from direct contact with paving as a division of concrete operations was to some extent a cause of delay in synchronizing the work on the two jobs *639 considered in . . . [these cases].” In the spring of 1957 Bianchi had two United States Government contracts for paving, one for about 12,000 cubic yards at Grenier Air Force Base at Manchester, New Hampshire (Grenier), and a second for about 10,000 cubic yards at Laurence G. Hans-com Field in Bedford, Massachusetts (Hanscom). Bianchi made inquiry through Fermo Bianchi, its treasurer, of one Mulkerin, vice-president of Builders, to determine whether an old batching plant which Bianchi owned “could be put in shape to operate under two Government contracts. ’ ’ Builders arranged for an examination of the old plant through one Brennet of Erie Strayer Company, a manufacturer of construction equipment, and submitted an estimate of cost by letter to Bianchi on April 9, 1957. On April 4 Bren-net, who was northeastern district representative of Erie Strayer, called at Bianchi’s office in company with one Harkins of Builders and talked with Peter Bianchi. Bren-net, having informed Peter Bianchi that the cost of repairing the old plant “would not be reasonable,” then “opened up the subject of Erie Strayer’s new Port-O-Matic plant and in the conversation stated that . . . [this] plant would batch 34 cubic feet (1% cubic yards) in . . . [forty-five] seconds. He stated that it had recording devices and would meet Government specifications. ’ ’ 3 Brennet thought delivery could be made in early June when Peter Bianchi stated he would need it. Brennet then showed Peter Bianchi a picture of the plant and enclosed with the letter to Bianchi of April 9,1957, a list of its specifications.

On April 13 Brennet called again at the Bianchi office in company with one Kazanjian, the president of Builders, and saw Fermo Bianchi, who stressed the importance of early delivery “to meet a construction schedule to start the first week in June.” Descriptive literature on the plant inclusive of pictures was left with Bianchi. On April 19 Kazan-jian called Fermo Bianchi and said that a Port-O-Matic *640 plant could be shipped by May 26 “if the order was placed promptly. [Ferma] Bianehi said he would place an order, but he wanted a penalty clause in the event there was delay in shipment . . . [and] wanted to arrange a time purchase plan, and a discount on the Port-O-Matic plant and the other machinery which Bianehi was buying from Builders. Kazanjian asked for a copy of the Government Specifications relating to batching concrete.” These were sent to him. “Kazanjian sent a copy of the rental purchase form ... to Bianehi on April 23 or 24 and placed the order for the Port-O-Matic plant with Erie Strayer on April 25. . . . On April 30, 1957, Bianehi gave Builders instructions on routing the shipment of the . . . plant.”

6 Late in May 1957, Builders prepared and sent to Bianehi two documents relating to the purchase and sale of the Port-O-Matic plant and other equipment” (emphasis supplied). One was entitled a “Rental Contract” (exhibit 13) and provided for “a guaranteed rental period of thirty (30) months” at a total of $1,809.60 a month for the three pieces of equipment. The other (exhibit 15) was typewritten, and in referring to the “Rental Contract” (and another rental contract not in issue here), granted Bianehi the option at any time during the life of the contract of remitting the unpaid balance and becoming the owner of the equipment. It contained certain other provisions relating to payment for the equipment, including one for a special discount on final payment. These documents, signed by Builders when received by Bianehi on May 29,1957, were signed by Bianehi on June 4,1957.

The selling prices of the several pieces of equipment subject to the negotiations were: (1) the Port-O-Matic plant, $47,680; (2) the track site unloader, $3,428; and (3) the clamshell bucket, $3,180, for a total of $54,288. The monthly rental of $1,809.60 was that total divided by thirty, representing the thirty months of guaranteed rent. There was never a dispute as to the operation of the track site unloader and the clamshell bucket.

The Port-O-Matic batching plant was a unit designed to aggregate together in stated quantities sand, two sizes of *641 stone, and dry cement. It contained scales and recording devices for regulating and tabulating the weight of the materials employed. Trucks delivered the dry mix to a dual drum paver which added water and completed the mixing of the concrete. The paver had a capacity for laying 1% cubic yards of concrete on the paving strip every forty-five seconds. Without detailing the auditor’s painstaking description of the entire process, it suffices to say a “paving operation is a highly mechanized, highly synchronized operation, which requires proper functioning and coordination of many machines and many persons in order to proceed without delays. . . . All of the operations from that of the paver on must be done within the time limits of the hardening of concrete.”

The plant was shipped from Erie, Pennsylvania, on May 27,1957, in accordance with Bianchi’s instructions. Due to delay in shipment the main part did not arrive until June 13 and 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AGUSTIN M. FLORIAN v. BORIS BERGUS & Another.
Massachusetts Appeals Court, 2026
Solmetex, LLC v. Dube
110 N.E.3d 1219 (Massachusetts Appeals Court, 2018)
Beliveau v. Ware
87 Mass. App. Ct. 617 (Massachusetts Appeals Court, 2015)
Latham v. Homecomings Financial LLC
27 Mass. L. Rptr. 3 (Massachusetts Superior Court, 2010)
MCS Enterprises, Ltd. v. Henry
2006 Mass. App. Div. 47 (Mass. Dist. Ct., App. Div., 2006)
Lederer v. JOHN SNOW, INC.
411 F. Supp. 2d 25 (D. Massachusetts, 2006)
Calloway v. Granitsas
2004 Mass. App. Div. 53 (Mass. Dist. Ct., App. Div., 2004)
East Coast Mechanical v. O'Leary
1997 Mass. App. Div. 66 (Mass. Dist. Ct., App. Div., 1997)
Ahepa Charitable Corp. v. Marlborough West Associates Ltd. Partnership
1995 Mass. App. Div. 15 (Mass. Dist. Ct., App. Div., 1995)
Town & Country Fine Jewelry Group, Inc. v. Hirsch
875 F. Supp. 872 (D. Massachusetts, 1994)
Marine Midland Bank, NA v. Moran
1994 Mass. App. Div. 167 (Mass. Dist. Ct., App. Div., 1994)
Schinkel v. Maxi-Holding, Inc.
565 N.E.2d 1219 (Massachusetts Appeals Court, 1991)
Lang v. Bradley
1990 Mass. App. Div. 202 (Mass. Dist. Ct., App. Div., 1990)
Schwartz v. Schultz
25 Mass. App. Ct. 941 (Massachusetts Appeals Court, 1988)
Berke v. Scammell
1986 Mass. App. Div. 65 (Mass. Dist. Ct., App. Div., 1986)
Kenney v. Rust
462 N.E.2d 333 (Massachusetts Appeals Court, 1984)
Joseph A. Previte, Inc. v. Bower
1983 Mass. App. Div. 242 (Mass. Dist. Ct., App. Div., 1983)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.E.2d 519, 347 Mass. 636, 1964 Mass. LEXIS 813, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlo-bianchi-co-v-builders-equipment-supplies-co-mass-1964.