Howdeshell, Inc. v. Kline Corp. (In Re Howdeshell, Inc.)

56 B.R. 122, 1985 Bankr. LEXIS 4724
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedDecember 20, 1985
DocketBankruptcy No. 83-1620, Adv. No. 84-83
StatusPublished
Cited by1 cases

This text of 56 B.R. 122 (Howdeshell, Inc. v. Kline Corp. (In Re Howdeshell, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howdeshell, Inc. v. Kline Corp. (In Re Howdeshell, Inc.), 56 B.R. 122, 1985 Bankr. LEXIS 4724 (Fla. 1985).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND MEMORANDUM OPINION

ALEXANDER L. PASKAY, Chief Judge.

THIS IS a Chapter 11 case and the matter under consideration is an adversary proceeding commenced by Howdeshell, Inc. (Debtor) against Kline Corporation (Kline) and United States Fidelity and Guarantee Company (USF & G). The original Complaint was filed on February 22, 1984, but was later amended by the Debtor on February 23, 1984. In its Amended Complaint, the Debtor seeks to recover the reasonable value of labor and materials it furnished under a subcontract agreement with Kline prior to the termination of that agreement together with attorney fees. In due course, Kline filed its answer to the Amended Complaint, asserted certain affirmative defenses and also filed a Counterclaim in which it claims that it is entitled to recover a minimum of $54,138.58 because of the alleged breach of contract by the Debtor. Kline also seeks attorney’s fees.

The underlying facts as developed at the final evidentiary hearing and as appear from the entire record, are as follows:

The Debtor is a Florida corporation engaged primarily as a subcontractor in large commercial construction projects involving the installation of plumbing, heating and air conditioning systems. The Defendant Kline is a general contractor extensively engaged in constructing major commercial projects. The Defendant USF & G is a bonding company whose prime business is furnishing payment and performance bonds on construction projects, primarily government projects.

On May 26, 1983, the Debtor and Kline entered into a subcontractor’s agreement which involved the construction of a central vocational center for the School Board of Broward County. Kline was the general contractor on the project and under the subcontract, the Debtor was to perform all the duties necessary for the installation of heating, cooling and ventilation for the project as specified by the contract. This subcontract amount, as appears from the documentary evidence, was $1,012,500. The project actually involved five separate buildings, each a part of one single complex. Prior to commencing the work, the Debtor “staged” the job by moving several vans and materials to the job site, and ultimately, the manpower necessary to perform the work.

Although the contract does not so specify, it was Kline’s understanding and inten *124 tion that subcontractors would be paid twice a month for the value of the labor completed and materials stored on the job site as of the last day of each pay period. The subcontractors were required to present their pay requests to Kline on or before the tenth and twenty-fifth of each month in order for Kline to include the subcontractor’s pay request in Kline’s pay request for the pay period to the Broward County School Board (School Board) on the first and fifteenth of each month.

The progress payment procedure followed by Kline, again not specified in the subcontract agreement, was that Kline would review the subcontractor’s pay request and determine what Kline believed was the value of the subcontractor’s work completed and materials stored at the time of each pay request. A Kline representative would then meet with the School Board representative and reach an agreed value for the materials stored and work completed for each portion of the work. After those two parties agreed on a payment amount for each portion, Kline would submit its total pay request in the agreed amount to the School Board.

On June 25, 1983 the Debtor submitted its first payment request to Kline, seeking a payment of $69,037 minus a ten percent retainage for a net of $62,133.30 (Plaintiff’s Exh. # 1). Kline rejected the first request for payment, claiming that it was submitted on the wrong form and directed Howdeshell to resubmit the payment request. In compliance, Howdeshell prepared a new request for payment which it identified as Pay Request # 1-A (Plaintiff’s Exh. # 2). The second request contained a breakdown of the request on a per building basis. Klein rejected Pay Request # 1-A, challenging the amount claimed by Howde-shell for staging the job. According to Howdeshell, its total cost of mobilization was $21,950 and it only sought seventy-five percent of that amount, that is, $16,462. Kline refused to honor that request and agreed to pay only $2,000 of the start-up expense per payment request.

On July 25, 1983 Howdeshell submitted a draw request identified as Pay Request # 1-B, reflecting the reduction in the amount of staging. The total amount requested was $71,074 minus a ten percent retainage for a net request of $66,966.60. Kline included this amount in its Pay Request # 3 to the School Board (Defendant’s Exh. #7) submitted on August 1, 1983. On September 9, 1983 Kline paid Howde-shell $50,571 which represented the approved amount minus an additional ten percent retainage.

On August 10, 1983 the Debtor submitted Pay Request # 2 which covered the period of July 25, 1983 through August 10, 1983 (Plaintiff’s Exh. #4). This request was in the amount of $30,574.80. Kline approved only $2,000 of the request, claiming that the remainder of the request was for payments for materials which were shipped to the job site by Howdeshell from other job sites; certain types of material and items which were not usable on that particular project inasmuch as they did not meet the specification for the heating and air conditioning work. Kline included this amount in its Pay Request #4 to the School Board (Defendant’s Exh. # 9), submitted on August 15, 1983. Although the School Board paid Kline’s Pay Request # 4 on August 20, 1983, at the time Howdeshell left the project on November 4, 1983 the $2,000 minus retainage approved for Pay Request # 2 had not been paid and has not since been paid.

Howdeshell submitted its Pay Request # 3 (Plaintiff’s Exh. # 6) in the amount of $6,824 for the period ending August 25, 1983 to Kline on a timely basis. Kline approved the requested amount and submitted it as part of Kline’s Pay Request # 5 (Defendant’s Exh. # 15) to the School Board on September 1, 1983. The School Board paid Kline for this portion of the heating and air conditioning work on September 15, 1983. Kline paid Howdeshell the approved amount of its Pay Request # 3, less retainage, by check in the amount of $6,142 on October 12, 1983.

*125 The next pay request submitted by Howdeshell covered the period from August 25, 1983 through September 10; 1983 and was in the amount of $7,062 (Plaintiffs Exh. #7). This request was ultimately paid in the reduced amount of $4,950 on or about October 27, 1983. The next request for payment covered the period of September 10, 1983 through September 25, 1983 and was submitted in the amount of $29,-783 (Plaintiffs Exh. # 8). It appears that this original request did not reach Kline or, in any event, they could not locate it. Howdeshell submitted a duplicate request in the same amount (Plaintiffs Exh. # 9). The replacement pay request was ultimately approved by Kline in the reduced amount of $10,685 and submitted to the School Board by Kline on November 1, 1983.

The next pay request submitted by Howdeshell covered the period from September 25, 1983 through October 10, 1983 and was in the amount of $7,459 and showed the prior request unpaid. Kline approved the amount sought in Plaintiffs Pay Request # 6 and included it in its Pay Request # 8 to the School Board (Defendant’s Exh.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
56 B.R. 122, 1985 Bankr. LEXIS 4724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howdeshell-inc-v-kline-corp-in-re-howdeshell-inc-flmb-1985.