Koch v. Construction Technology, Inc.

924 S.W.2d 68, 1996 Tenn. LEXIS 320
CourtTennessee Supreme Court
DecidedMay 20, 1996
StatusPublished
Cited by26 cases

This text of 924 S.W.2d 68 (Koch v. Construction Technology, Inc.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koch v. Construction Technology, Inc., 924 S.W.2d 68, 1996 Tenn. LEXIS 320 (Tenn. 1996).

Opinion

OPINION

DROWOTA, Justice.

This case involves a contract dispute between Mark Koch (d/b/a Commercial Painting Company, Inc.) and Construction Technology, Inc., (CTI), the former a painting subcontractor and the latter the general contractor on a construction project owned by the Memphis Housing Authority (MHA). The issues for our determination are as follows: (1) whether the Court of Appeals erred in construing the “pay when paid” clause in the subcontract as a condition precedent, thereby making Koch’s right to payment dependent upon CTI’s receipt of payment from MHA; and (2) whether the Court of Appeals erred in construing the bond given by CTI to Koch as a statutory bond rather than a common law bond, which had the effect of precluding Koch’s right of action against Fidelity and Deposit Company of Maryland (FDCM), the surety on the bond. For the following reasons, we hold that the Court of Appeals erred on both issues; therefore, we reverse the judgment of that court and remand the cause for further proceedings.

FACTS AND PROCEDURAL HISTORY

On March 17, 1988, CTI and the MHA entered into a contract in which CTI agreed to make improvements to the Dixie Homes Housing Development in Memphis. On March 80,1988, CTI subcontracted the painting portion of the project to Koch; CTI also provided a performance and payment bond to him through FDCM. The subcontract included a “payment” clause, which provides in pertinent part, that:

Partial payments subject to all applicable provisions of the Contract shall be made when and as payments are received by the Contractor. The Subcontractor may be required as a condition precedent to any payment to furnish evidence satisfactory to the Contractor that all payrolls, material bills, and other indebtedness applicable to the work have been paid.

Koch completed all work required by the contract on July 31, 1989; and he was paid $148,110.96 for this work by CTI. However, because the amount of actual work performed exceeded this total, and because CTI refused to make any additional payments, Koch brought an action against it for breach of contract in the Shelby County Circuit Court. In its answer, CTI cited the payment clause as an affirmative defense, alleging that “CTI has not been paid in full by MHA and, therefore, is not obligated to pay plaintiff since payment to CTI by MHA is a condition precedent to CTI’s obligation to pay plaintiff.”

Koch’s complaint also included a claim against FDCM based on the performance and payment bond. In its answer, FDCM alleged that Koch’s claim was barred by the six month limitations period applicable to statutory bonds, and that Koch had failed to comply with the notice provisions applicable to such bonds.

After a bench trial, the trial court found, in pertinent part, as follows:

This contract [between Koch and CTI] provided that the work performed by Plaintiff would be paid when defendant CTI received payment from MHA.
[[Image here]]
Based on the sign-off sheets numbers and the actual observations and measurements of the project made by the plaintiff and/or his employees as it relates to the painting work, the Court finds that MHA has paid CTI $28,307.22 for work actually performed by plaintiff in addition to the $148,-110.96 already paid to plaintiff by CTI. This amount ... does not include any amounts for other work actually performed by plaintiff for which CTI has not been paid by MHA.
[[Image here]]
The plaintiff, Mark Koch d/b/a Commercial Painting Company, is awarded a judgment against the defendant CTI in the amount of $28,307.22.
Pursuant to motion made at the close of plaintiffs proof, the defendant FDCM is *70 dismissed from this action with full prejudice.
[[Image here]]
This judgment may be amended by proper application upon final adjudication by a court of competent jurisdiction concerning the total quantities to be paid for by MHA to defendant CTI for painting work performed by plaintiff on the Dixie Homes project.

The last paragraph of the order was presumably included because CTI and MHA were then involved in litigation in another division of the Shelby County Circuit Court concerning MHA’s liability to CTI for its work on the Dixie Homes project. Brown v. Bay Architectural Service, Inc., (Shelby Circuit Court, No. 30132). After the Brown litigation had concluded, Koch filed a motion requesting that the trial court increase the judgment to $39,650.14, arguing that the un-controverted evidence presented at trial in the instant case showed this to be the total amount due him under the subcontract. CTI responded by filing a motion to reduce the judgment, in which it asserted that based upon the trial court’s findings in Brown, Koch was due only $21,789.93 on the subcontract. The trial court denied both motions, and Koch appealed to the Court of Appeals.

The Court of Appeals affirmed the judgment.' As to Koch’s claim against CTI, the Court relied heavily upon Hussey v. Crass, 53 S.W. 986 (Tenn.Chan.App.1899), in determining that the “pay when paid” clause was a condition precedent to CTI’s promise to pay. With respect to Koch’s claim against FDCM, the court concluded that the bond executed by CTI to Koch was a statutory bond, and that Koch had neither brought its claim on the bond in a timely fashion, nor adhered to the notice provisions applicable to such bonds. We granted Koch’s application for permission to appeal to address these issues.

I.

A. Construction of the Payment Clause

The first issue for our determination is whether the payment clause in the subcontract establishes MHA’s payment to CTI as a condition precedent to CTI’s obligation to pay Koch. Koch argues that the lower courts erred in so construing the clause. Although conceding that the Hussey court construed similar language as a conditional promise, he argues that an overwhelming majority of jurisdictions reject that position, and instead hold that such language establishes an absolute promise to pay on the part of the general contractor', but simply affords it a reasonable amount of time to make the payments. This majority position is sound public policy, Koch contends, because it is inequitable to make the subcontractor’s right to payment dependent upon the owner’s performance, which might not be forthcoming for any number of reasons out of the subcontractor’s control. Because Hussey is at odds with the compelling majority position, Koch concludes, it should be overruled and the majority rule adopted in its place.

CTI responds that the law of other jurisdictions is of no consequence, and that Hus-sey — the only reported Tennessee decision addressing the issue — controls this case. Therefore, it concludes, the lower courts’ construction of the payment clause should be affirmed.

Because the parties and the lower courts relied so heavily upon Hussey, we must first examine it in some detail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shelley v. Brandt
M.D. Tennessee, 2022
Michael Bennett v. Chattanooga Properties, LLC
Court of Appeals of Tennessee, 2021
Beal Bank Nevada v. NorthShore Center THC, LLC
2016 IL App (1st) 151697 (Appellate Court of Illinois, 2016)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Lemoine Co. of Alabama v. HLH Constructors, Inc.
62 So. 3d 1020 (Supreme Court of Alabama, 2010)
Champion Home Builders Co. v. Johnson
993 So. 2d 875 (Supreme Court of Alabama, 2008)
Ex Parte Johnson v. Sabrina Johnson
993 So. 2d 875 (Supreme Court of Alabama, 2008)
Federal Insurance Co. v. I. Kruger, Inc.
829 So. 2d 732 (Supreme Court of Alabama, 2002)
White's Electric v. Lewis Constr.
Court of Appeals of Tennessee, 1999
Main Electric, Ltd. v. Printz Services Corp.
980 P.2d 522 (Supreme Court of Colorado, 1999)
Henry Andrews v. Lubricon
Court of Appeals of Tennessee, 1998
Printz Services Corp. v. Main Electric, Ltd.
949 P.2d 77 (Colorado Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
924 S.W.2d 68, 1996 Tenn. LEXIS 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koch-v-construction-technology-inc-tenn-1996.