White's Electric v. Lewis Constr.

CourtCourt of Appeals of Tennessee
DecidedAugust 11, 1999
Docket02A01-9803-CH-00064
StatusPublished

This text of White's Electric v. Lewis Constr. (White's Electric v. Lewis Constr.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White's Electric v. Lewis Constr., (Tenn. Ct. App. 1999).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON

WHITE’S ELECTRIC, HEATING, ) FILED AIR AND PLUMBING, ) ) August 11, 1999 Plaintiff/Appellee, ) Madison Chancery No. 51088 ) Cecil Crowson, Jr. v. ) Appellate Court Clerk ) LEWIS CONSTRUCTION COMPANY, ) Appeal No. 02A01-9803-CH-00064 a/k/a TOMMY LEWIS ) CONSTRUCTION COMPANY AND ) FRONTIER INSURANCE COMPANY, ) ) Defendants/Appellants. )

APPEAL FROM THE CHANCERY COURT OF MADISON COUNTY AT JACKSON, TENNESSEE

THE HONORABLE JOE C. MORRIS, CHANCELLOR

For the Plaintiff/Appellee: For the Defendants/Appellants:

Gerald B. Kirksey Ralph D. Golden J. Timothy Crenshaw Memphis, Tennessee Brentwood, Tennessee

AFFIRMED IN PART, REVERSED IN PART, AND REMANDED

HOLLY KIRBY LILLARD, J.

CONCURS:

ALAN E. HIGHERS, J.

DAVID R. FARMER, J. OPINION

This is a construction contract case. The plaintiff subcontractor sued the general contractor

and the general contractor’s surety seeking unpaid contract payments and damages for delays in

performance of the construction contract. The trial court awarded the plaintiff damages for breach

of contract and for disruption and delay. We affirm in part, reverse in part, and remand.

Lewis Construction Company (“Lewis Construction”) was the general contractor for a

construction project with the Jackson Housing Authority (“JHA”) to renovate public housing

facilities in Jackson, Tennessee. The original contract between the JHA and Lewis Construction

contained a project deadline of November 15, 1994, or 278 days. The prime contract deadline was

subsequently extended by agreement to September 5, 1995. The project was to be completed in three

separate phases, with Phase I to be completed before Phase II began and so forth. Frontier Insurance

Company (“Frontier Insurance”) served as Lewis Construction’s surety on the project. Lewis

Construction and Frontier Insurance will be referred to collectively as the Defendants. White’s

Electric, Heating, Air and Plumbing (“White’s Plumbing”) was the plumbing subcontractor for the

construction project.

White’s Plumbing submitted a bid proposal to Lewis Construction in the amount of

$151,000. The proposal referenced the plans and specifications for the project contained in a project

manual distributed by Lewis Construction to potential subcontractors. White’s Plumbing’s proposal

was accepted by Lewis Construction on February 22, 1994. The subcontract between White’s

Plumbing and Lewis Construction provided that White’s Plumbing would provide labor, supplies,

and material for installation of water lines, sanitary vent lines, plumbing fixtures, and gas lines “per

plans and specifications for Jackson Housing Authority Modernization Program.” The subcontract

provided that Lewis Construction was to pay White’s Plumbing “per specifications.” The

subcontract did not contain a completion date.

White’s Plumbing began work on the project on March 4, 1994, and completed its work on

the project on April 18, 1995. Two change orders in the record showed that the parties increased the

contract price by $1790, making the total due White’s Plumbing under the contract $152,790. Lewis

Construction paid White’s Plumbing $138,651.34 under the subcontract, but withheld the

$14,138.66 retainage. White’s Plumbing filed a lawsuit on October 13, 1995 against Lewis Construction and

Frontier Insurance. The complaint alleged that Lewis Construction caused damages to White’s

Plumbing by delaying White’s Plumbing’s completion of its work on the project, thereby increasing

White’s Plumbing’s costs and decreasing its profits. White’s Plumbing asserted that Lewis

Construction caused delay by failing to perform necessary site work and clean up, making changes

in the normal sequence for completion of the work, and failing to coordinate the work of other

subcontractors. White’s Plumbing also alleged that Lewis Construction had refused to pay for work

that White’s Plumbing performed under various change orders to the subcontract. White’s Plumbing

contended that Lewis Construction violated the Prompt Pay Act, Tennessee Code Annotated § 66-

34-101 to -703, by failing to pay White’s Plumbing in a timely manner after it received payments

from the JHA. White’s Plumbing’s claims against Frontier Insurance were based on the contractor’s

bond issued by Frontier Insurance for Lewis Construction, pursuant to Tennessee Code Annotated

§ 12-4-201. A copy of the bond was attached to White’s Plumbing complaint. White’s Plumbing

sought $15,551 in unpaid contract payments and retainage, and $84,329 for delay, disruption and

impact damages.

Lewis Construction and Frontier Insurance filed a joint answer. Frontier Insurance admitted

that it was Lewis Construction’s surety, but denied that it issued a contractor’s bond to Lewis

Construction pursuant to Tennessee Code Annotated § 12-4-201. The Defendants denied that Lewis

Construction breached the subcontract with White’s Plumbing, that Lewis Construction was

responsible for any delays to the subcontract, or that Lewis Construction owed White’s Plumbing

any monies under the subcontract. The Defendants raised several affirmative defenses, including

lack of subject matter jurisdiction, failure to state a claim on which relief could be granted, the

statute of frauds, and failure to give timely notice of the claim as required by Tennessee Code

Annotated § 12-4-205.

The Defendants later filed an amended answer in which they asserted the defense of unclean

hands. The Defendants alleged that White’s Plumbing committed the first material breach of the

contract, and thus they were not liable to White’s Plumbing for any damages. The Defendants also

alleged that White’s Plumbing was not properly licensed by the Tennessee Contractor’s Licensing

Board for the construction project, that White’s Plumbing failed to mitigate its damages, and that

White’s Plumbing failed to pay required county and city business taxes and to obtain the required

2 county and city business licenses pursuant to Tennessee Code Annotated § 67-4-217. Finally, the

Defendants asserted that White’s Plumbing waived the claims set forth in its complaint.

The case was heard in a bench trial. Jerry White (“White”), the owner of White’s Plumbing,

testified that he understood the completion date for the subcontract to be November 15, 1994, based

on the original completion date in the project manual and the contract between the JHA and Lewis

Construction. White said that he calculated his bid based on his estimate of the materials needed and

the plans and specifications for the job, including the completion date. He considered the completion

date to be an important factor in preparing his bid because of his knowledge that both the general

contractor and the subcontractors would be subject to liquidated damages if the project were not

completed on time.

White testified that it is the general contractor’s duty to coordinate the subcontractors on the

project, and that Lewis Construction failed to do so. He explained that Lewis Construction never

met with the subcontractors to let them know when to show up at the job site, nor did it provide the

subcontractors with a schedule. White said that he would be told to begin work at one job site and

then, a few days later, Lewis Construction would send White’s Plumbing to another job site across

town. He described the job site as “just chaos.” He testified that he experienced delays and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
Estate of Walton v. Young
950 S.W.2d 956 (Tennessee Supreme Court, 1997)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Gredig v. Tennessee Farmers Mutual Insurance Co.
891 S.W.2d 909 (Court of Appeals of Tennessee, 1994)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
McCaleb v. Saturn Corp.
910 S.W.2d 412 (Tennessee Supreme Court, 1995)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
APAC-Tennessee, Inc. v. J.M. Humphries Construction Co.
732 S.W.2d 601 (Court of Appeals of Tennessee, 1986)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Wal-Board Supply Co., Inc. v. Daniels
629 S.W.2d 686 (Court of Appeals of Tennessee, 1981)
Whitaker v. Whitaker
957 S.W.2d 834 (Court of Appeals of Tennessee, 1997)
Sime Construction Co. v. Washington Public Power Supply System
621 P.2d 1299 (Court of Appeals of Washington, 1981)
Industrial Commission v. Arizona Power Co.
295 P. 305 (Arizona Supreme Court, 1931)
Beedy v. San Mateo Hotel Co.
150 P. 810 (California Court of Appeal, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
White's Electric v. Lewis Constr., Counsel Stack Legal Research, https://law.counselstack.com/opinion/whites-electric-v-lewis-constr-tennctapp-1999.