White's Electric v. Lewis Constr.

Court of Appeals of Tennessee·Decided August 11, 1999·No. 02A01-9803-CH-00064·Published

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON

WHITE’S ELECTRIC, HEATING, )

FILED

AIR AND PLUMBING, )

) August 11, 1999 Plaintiff/Appellee, ) Madison Chancery No. 51088 ) Cecil Crowson, Jr.

v. ) Appellate Court Clerk )

LEWIS CONSTRUCTION COMPANY, ) Appeal No. 02A01-9803-CH-00064 a/k/a TOMMY LEWIS ) CONSTRUCTION COMPANY AND ) FRONTIER INSURANCE COMPANY, )

)

Defendants/Appellants. )

APPEAL FROM THE CHANCERY COURT OF MADISON COUNTY AT JACKSON, TENNESSEE

THE HONORABLE JOE C. MORRIS, CHANCELLOR

For the Plaintiff/Appellee: For the Defendants/Appellants:

Gerald B. Kirksey Ralph D. Golden J. Timothy Crenshaw Memphis, Tennessee Brentwood, Tennessee

AFFIRMED IN PART, REVERSED IN PART, AND REMANDED

HOLLY KIRBY LILLARD, J.

CONCURS: ALAN E. HIGHERS, J. DAVID R. FARMER, J.

OPINION

This is a construction contract case. The plaintiff subcontractor sued the general contractor and the general contractor’s surety seeking unpaid contract payments and damages for delays in performance of the construction contract. The trial court awarded the plaintiff damages for breach of contract and for disruption and delay. We affirm in part, reverse in part, and remand.

Lewis Construction Company (“Lewis Construction”) was the general contractor for a construction project with the Jackson Housing Authority (“JHA”) to renovate public housing facilities in Jackson, Tennessee. The original contract between the JHA and Lewis Construction contained a project deadline of November 15, 1994, or 278 days. The prime contract deadline was subsequently extended by agreement to September 5, 1995. The project was to be completed in three separate phases, with Phase I to be completed before Phase II began and so forth. Frontier Insurance Company (“Frontier Insurance”) served as Lewis Construction’s surety on the project. Lewis Construction and Frontier Insurance will be referred to collectively as the Defendants. White’s Electric, Heating, Air and Plumbing (“White’s Plumbing”) was the plumbing subcontractor for the construction project.

White’s Plumbing submitted a bid proposal to Lewis Construction in the amount of $151,000. The proposal referenced the plans and specifications for the project contained in a project manual distributed by Lewis Construction to potential subcontractors. White’s Plumbing’s proposal was accepted by Lewis Construction on February 22, 1994. The subcontract between White’s Plumbing and Lewis Construction provided that White’s Plumbing would provide labor, supplies, and material for installation of water lines, sanitary vent lines, plumbing fixtures, and gas lines “per plans and specifications for Jackson Housing Authority Modernization Program.” The subcontract provided that Lewis Construction was to pay White’s Plumbing “per specifications.” The subcontract did not contain a completion date.

White’s Plumbing began work on the project on March 4, 1994, and completed its work on the project on April 18, 1995. Two change orders in the record showed that the parties increased the contract price by $1790, making the total due White’s Plumbing under the contract $152,790. Lewis Construction paid White’s Plumbing $138,651.34 under the subcontract, but withheld the $14,138.66 retainage.

White’s Plumbing filed a lawsuit on October 13, 1995 against Lewis Construction and Frontier Insurance. The complaint alleged that Lewis Construction caused damages to White’s Plumbing by delaying White’s Plumbing’s completion of its work on the project, thereby increasing White’s Plumbing’s costs and decreasing its profits. White’s Plumbing asserted that Lewis Construction caused delay by failing to perform necessary site work and clean up, making changes in the normal sequence for completion of the work, and failing to coordinate the work of other subcontractors. White’s Plumbing also alleged that Lewis Construction had refused to pay for work that White’s Plumbing performed under various change orders to the subcontract. White’s Plumbing contended that Lewis Construction violated the Prompt Pay Act, Tennessee Code Annotated § 66- 34-101 to -703, by failing to pay White’s Plumbing in a timely manner after it received payments from the JHA. White’s Plumbing’s claims against Frontier Insurance were based on the contractor’s bond issued by Frontier Insurance for Lewis Construction, pursuant to Tennessee Code Annotated § 12-4-201. A copy of the bond was attached to White’s Plumbing complaint. White’s Plumbing sought $15,551 in unpaid contract payments and retainage, and $84,329 for delay, disruption and impact damages.

Lewis Construction and Frontier Insurance filed a joint answer. Frontier Insurance admitted that it was Lewis Construction’s surety, but denied that it issued a contractor’s bond to Lewis Construction pursuant to Tennessee Code Annotated § 12-4-201. The Defendants denied that Lewis Construction breached the subcontract with White’s Plumbing, that Lewis Construction was responsible for any delays to the subcontract, or that Lewis Construction owed White’s Plumbing any monies under the subcontract. The Defendants raised several affirmative defenses, including lack of subject matter jurisdiction, failure to state a claim on which relief could be granted, the statute of frauds, and failure to give timely notice of the claim as required by Tennessee Code Annotated § 12-4-205.

The Defendants later filed an amended answer in which they asserted the defense of unclean hands. The Defendants alleged that White’s Plumbing committed the first material breach of the contract, and thus they were not liable to White’s Plumbing for any damages. The Defendants also alleged that White’s Plumbing was not properly licensed by the Tennessee Contractor’s Licensing Board for the construction project, that White’s Plumbing failed to mitigate its damages, and that White’s Plumbing failed to pay required county and city business taxes and to obtain the required

county and city business licenses pursuant to Tennessee Code Annotated § 67-4-217. Finally, the Defendants asserted that White’s Plumbing waived the claims set forth in its complaint.

The case was heard in a bench trial. Jerry White (“White”), the owner of White’s Plumbing, testified that he understood the completion date for the subcontract to be November 15, 1994, based on the original completion date in the project manual and the contract between the JHA and Lewis Construction. White said that he calculated his bid based on his estimate of the materials needed and the plans and specifications for the job, including the completion date. He considered the completion date to be an important factor in preparing his bid because of his knowledge that both the general contractor and the subcontractors would be subject to liquidated damages if the project were not completed on time.

White testified that it is the general contractor’s duty to coordinate the subcontractors on the project, and that Lewis Construction failed to do so. He explained that Lewis Construction never met with the subcontractors to let them know when to show up at the job site, nor did it provide the subcontractors with a schedule. White said that he would be told to begin work at one job site and then, a few days later, Lewis Construction would send White’s Plumbing to another job site across town. He described the job site as “just chaos.” He testified that he experienced delays and difficulties due to the large turnover in personnel under Lewis Construction’s supervision, including twenty-four painters, twenty-two carpenters, fifty-one laborers, and six sheetrock finishers: “You didn’t know from one day to the next who the next guy was. Every day you’d come in and you’d have to reintroduce yourself to the painter and tell him where you was and whether you had that lavatory hung, for him to paint behind it or not.”

Free access — add to your briefcase to read the full text and ask questions with AI

White's Electric v. Lewis Constr., (Tenn. Ct. App. 1999).

White's Electric v. Lewis Constr. (White's Electric v. Lewis Constr.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
Estate of Walton v. Young
950 S.W.2d 956 (Tennessee Supreme Court, 1997)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Gredig v. Tennessee Farmers Mutual Insurance Co.
891 S.W.2d 909 (Court of Appeals of Tennessee, 1994)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
McCaleb v. Saturn Corp.
910 S.W.2d 412 (Tennessee Supreme Court, 1995)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
APAC-Tennessee, Inc. v. J.M. Humphries Construction Co.
732 S.W.2d 601 (Court of Appeals of Tennessee, 1986)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Wal-Board Supply Co., Inc. v. Daniels
629 S.W.2d 686 (Court of Appeals of Tennessee, 1981)
Whitaker v. Whitaker
957 S.W.2d 834 (Court of Appeals of Tennessee, 1997)
Sime Construction Co. v. Washington Public Power Supply System
621 P.2d 1299 (Court of Appeals of Washington, 1981)
Industrial Commission v. Arizona Power Co.
295 P. 305 (Arizona Supreme Court, 1931)
Beedy v. San Mateo Hotel Co.
150 P. 810 (California Court of Appeal, 1915)