APAC-Tennessee, Inc. v. J.M. Humphries Construction Co.

732 S.W.2d 601, 1986 Tenn. App. LEXIS 3187
CourtCourt of Appeals of Tennessee
DecidedJuly 29, 1986
StatusPublished
Cited by23 cases

This text of 732 S.W.2d 601 (APAC-Tennessee, Inc. v. J.M. Humphries Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
APAC-Tennessee, Inc. v. J.M. Humphries Construction Co., 732 S.W.2d 601, 1986 Tenn. App. LEXIS 3187 (Tenn. Ct. App. 1986).

Opinion

CRAWFORD, Judge.

This case involves a dispute between a subcontractor and a contractor on a public improvement job. Plaintiff, APAC-Ten-nessee, Inc., 1 filed its complaint against, among others, defendant, J.M. Humphries Construction Co., seeking, inter alia, contract retainage, interest on contract retain-age and additional price adjustment payments for bituminous materials supplied for the project. Humphries’ answer joined issue on the complaint’s allegations and subsequently Humphries filed a counterclaim seeking a refund of the amount it had paid APAC because of an alleged bookkeeping error.

This case was tried in two stages. The first stage was a trial before the court on the liability issues presented by the complaint and counter-complaint. The second stage was a hearing before the Master pursuant to the reference by the trial court after ruling on the liability issues.

The issues presented for review on this appeal concern primarily the first stage of the proceedings. The case was tried on a stipulation of evidence consisting of the following documents:

Exhibit 1 Proposal Contract between State of Tennessee and Humphries, dated March 29, 1978;
Exhibit 2 Tennessee Department of Highways, Standard Specifications for Road and Bridge Construction, which apply to Exhibit 1 and are a part thereof;
Exhibit 3 Subcontract between Hum-phries and O’Neal Paving Company (“O’Neal”) dated April 5, 1978;
Exhibit 4 Transmittal letter dated May 25, 1978, and approved subcontract form between Humphries and O’Neal, dated May 25, 1978;
Exhibit 5 Subcontract between Hum-phries and Warren Brothers Company (“Warren Brothers”) dated April 5, 1978; and
Exhibit 6 Transmittal letter dated May 25, 1978, and approved subcontract form between Humphries and Warren Brothers, dated May 24, 1978;

The prime contract between Humphries and the state was executed on or about March 29, 1978, and was for certain road improvements to Warford Street in Memphis consisting of grading, drainage, installation of bridges and guard rails and paving work. Humphries was obligated to provide the labor, materials and eqhipment as necessary to complete the project and as specifically listed in the contract as separate items. Included within the separate items listed were certain materials referred to as bituminous materials which were used in the asphalt paving portion of the contract. Regarding the bituminous materials, the contract had a provision entitled “Special Provision Regarding Price Adjustment For Bituminous Material” which was designated as Section 335. This special provision set forth a method to adjust the price to be paid by the state for the bituminous materials specifically listed and re *603 quired under the contract. Although the formula for the adjustment price was somewhat complicated, it basically provided for a price at the beginning of the contract and thereafter, if the actual price of the materials either increased or decreased more than five percent on a monthly basis, there would be an adjustment in the unit price paid by the state to the contractor for the bituminous materials covered by the contract provision.

By contracts dated April 5, 1978, Hum-phries subcontracted to Warren and to O’Neal the asphalt paving work to be performed under its contract. The subcontracts utilized the American Institute of Architects’ standard form of agreement between contractor and subcontractor. We quote the parts of the subcontracts pertinent to the issues involved in this appeal:

ARTICLE 1
THE CONTRACT DOCUMENTS
The Contract Documents for this Subcontract consist of this Agreement and any Exhibits attached hereto, the Agreement between the Owner and Contractor dated March 29, 1978, the Conditions of the Contract between the Owner and Contractor (General, Supplementary and other Conditions), Drawings, Specifications, all Addenda issued prior to execution of the Agreement between the Owner and Contractor, and all Modifications issued subsequent thereto.
All of the above documents are a part of this Subcontract and shall be available for inspection by the Subcontractor upon his request.
The only Addenda and Modifications issued prior to the execution of this Subcontract and applicable to it are as follows:
ARTICLE 2
THE WORK
The Subcontractor shall furnish all materials, supplies, labor, equipment, engineering services and other necessary items to do and perform for Contractor the following items of work on the above mentioned project for the following contract prices ... [Here are listed the specific items as described in the prime contract and the specific sums to be paid to the subcontractors for the performance of the subcontract as to those items].
******
ARTICLE 4
THE CONTRACT SUM
The Contractor shall pay the Subcontractor in current funds for the performance of the Work, subject to additions and deductions by Change Order, in accordance with the unit prices as set out in Article 2. It is understood and agreed that the quantities set out in said articles are estimates only and that the Contractor will pay the Subcontractor for all quantities actually produced by the Subcontractor and approved for payment by the State of Tennessee Department of Transportation.
ARTICLE 5
PROGRESS PAYMENTS
The Contractor shall pay the Subcontractor monthly progress payments ... [l]ess ten percent (10%) retained, within seven (7) days after receipt of monthly progress payment from owner.
* * * * * *
ARTICLE 11
SUBCONTRACTOR’S RESPONSIBILITIES
11.1 The Subcontractor shall be bound to the Contractor by the terms of this Agreement and of the Contract Documents between the Owner and Contractor, and shall assume toward the Contractor all the obligations and responsibilities which the Contractor, by those Documents, assumes toward the Owner, and shall have the benefit of all rights, remedies and redress against the Contractor which the Contractor, by those Documents, has against the Owner, insofar as applicable to this Subcontract, provided that where any provision of the *604 Contract Documents between the Owner and Contractor is inconsistent with any provision of this Agreement, this Agreement shall govern.
* *****
ARTICLE 12
CONTRACTOR’S RESPONSIBILITIES

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael J. Boeh v. Arthur M. Dial
Court of Appeals of Tennessee, 2022
Centex/Worthgroup, LLC v. Worthgroup Architects, L.P.
2016 NMCA 013 (New Mexico Court of Appeals, 2015)
C.F. Property, LLC v. Rachel Scott
Court of Appeals of Tennessee, 2011
Ingram v. Cendant Mobility Financial Corp.
215 S.W.3d 367 (Court of Appeals of Tennessee, 2006)
Thomas G. Hyde v. Ishikawa Gasket America
Court of Appeals of Tennessee, 2003
Pitt v. Tyree Organization Ltd.
90 S.W.3d 244 (Court of Appeals of Tennessee, 2002)
Harriet & Henderson Yarns, Inc. v. Castle
75 F. Supp. 2d 818 (W.D. Tennessee, 1999)
White's Electric v. Lewis Constr.
Court of Appeals of Tennessee, 1999
Jennifer Kensinger vs.s James Kensinger
Court of Appeals of Tennessee, 1999
Knoble v. Taylor
Court of Appeals of Tennessee, 1999
Dick Moore v. GreenTree Financial
Court of Appeals of Tennessee, 1998
Robert Martin v. Union Planters
Court of Appeals of Tennessee, 1998
Charles Crews v. Dexter Road Partners
Court of Appeals of Tennessee, 1998
Someday Baby, Inc. v. Entertainment Int'l.
Court of Appeals of Tennessee, 1998
Union Planters National Bank v. American Home Assurance Co.
865 S.W.2d 907 (Court of Appeals of Tennessee, 1993)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
732 S.W.2d 601, 1986 Tenn. App. LEXIS 3187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apac-tennessee-inc-v-jm-humphries-construction-co-tennctapp-1986.