Centex/Worthgroup, LLC v. Worthgroup Architects, L.P.

2016 NMCA 013, 9 N.M. 262
CourtNew Mexico Court of Appeals
DecidedSeptember 10, 2015
DocketS-1-SC-35549; Docket 32,331
StatusPublished
Cited by5 cases

This text of 2016 NMCA 013 (Centex/Worthgroup, LLC v. Worthgroup Architects, L.P.) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centex/Worthgroup, LLC v. Worthgroup Architects, L.P., 2016 NMCA 013, 9 N.M. 262 (N.M. Ct. App. 2015).

Opinion

OPINION

KENNEDY, Judge.

I. INTRODUCTION

{1} This appeal involves a dispute between a general contractor, Centex/Worthgroup, LLC (Centex), and a subcontractor, Worthgroup Architects, L.P. (Architect). Centex and Architect entered into a contractual relationship which, among other things, governed the construction of a Mechanically Stabilized Earth (MSE) Wall. The MSE Wall ultimately failed, and Centex brought this suit against Architect and Terracon, Inc., claiming over $6,000,000 in damages for redesign and repair costs that it incurred. Centex asserted that Architect is required to cover the costs Centex incurred in redesigning and repairing the MSE Wall. Architect conversely asserted that its monetary obligations to Centex have been satisfied by the payment of proceeds of insurance coverage that it was contractually obligated to procure and maintain.

{2} Centex appeals a grant of summary judgment to Architect, in which the district court apparently determined that a limitation of liability clause in a prime contract flowed down to the subcontract by virtue of a flow-down clause. We reverse. We note that Centex contends genuine issues of material fact remain, but, for the reasons that follow, we decline to consider whether this is the case and remand so that the district court can consider the facts and arguments in light of the holding in this Opinion.

II. BACKGROUND

{3} In February 2002, the Inn ofthe Mountain Gods Resort and Casino (Owner) contracted with Centex for an expansion and renovation project. These parties defined the terms of their business relationship in a second amended design/build construction contract (the prime contract). Centex then entered into a subcontract with Architect, where Architect agreed to perform design work on the project. Both the prime contract and the subcontract are relevant to our analysis in this case. 1

{4} We begin with a brief overview of the prime contract and subcontract, continue with an account of the proceedings in district court, and end with a discussion of the law relevant to our holding.

A. The Prime Contract

{5} The prime contract governs the contractual relationship between Owner and Centex with regard to the project. The first section of the prime contract that the parties have termed the “limitation of liability” clause 2 is relevant to this appeal. The limitation of liability clause provides:

In addition to all other insurance requirements set forth in this Agreement, Design/Builder shall require its design professional Subcontractor(s) to obtain and maintain professional errors and omissions coverage with respect to design services in accordance herewith. . . . [S]uch coverage shall be for each such design professional Subcontractor in an amount not less than $3,000,000. Owner agrees that it will limit Design/Builder liability to [0]wner for any errors or omissions in the design of the Project to whatever sums Owner is able to collect from the above described professional errors and omissions insurance carrier.

B. The Subcontract

{6} The subcontract, which governs the contractual relationship between Centex and Architect with regard to the project, contains an incorporation by reference clause, which requires Architect to perform the design work in strict accordance with the prime contract and incorporates the prime contract by reference. The subcontract reflects Centex’s and Architect’s intent that “all the terms of all documents are to be considered as complementary.” Should such an interpretation be impossible, however, the parties provide the desired sequence for use of the documents, hereinafter referred to as the order of precedence clause.

[T]he order of precedence of the documents,... shall be: (1) the most current approved edition of the [cjonstruction [djocuments; (2) modifications to [the subcontract]; (3) [the subcontract], unless the [prime contract] imposes a higher standard or greater requirement on the parties, in which case the [prime contract]; (4) the [prime contract], unless the provisions of (3) apply.

{7} The subcontract also includes a provision—referred to by the parties as a flow-down clause 3 —which states:

In respect of the [d]esign [w]ork, [Architect] shall, except as otherwise provided herein, have all rights toward [Centex] which [Centex] has under the [prime contract] towards the Owner and [Architect] shall, to the extent permitted by applicable laws and except as provided herein, assume all obligations, rislcs[,] and responsibilities toward [Centex] which [Centex] has assumed towards the Owner in the [prime contract] with respect to [the d]esign [w]ork.

The central dispute between the parties revolves around the meaning and reach of this provision.

{8} The subcontract also provides a general liability clause, which makes Architect responsible for “[Redesign costs and additional construction costs of [Centex] and/or the [contractor required to correct [Architect’s] errors or omissions,” but specifies that Architect’s “responsibility shall not preclude the pursuit of available insurance proceeds on account thereof[.]”

{9} Finally, the subcontract assigns rights and obligations to the parties regarding insurance and liability. For instance, Architect is required to procure “insurance coverage from insurers acceptable to [Centex]” and “shall be responsible for all deductibles relating to claims under all applicable insurance policies on account of the [d]esign [w]ork, including the [professional [liability [ijnsurance provided by Design Builder.” Architect is further required to name Centex, the [contractor, and Owner as “additional insureds” on the insurance coverage and maintain the coverage “until expiration of [Architect’s] obligations” under the subcontract. Another section of the subcontract requires Architect to “provide a [pjroject [p]olicy for [professional [liability insurance with [l]imits of [liability of $3,000,000 per occurrence and $3,000,000 Aggregate.”

C. Construction And Failure of the MSE Wall

{10} Construction of the MSE Wall began in June 2003. The MSE Wall began to fail in April 2004, causing damage to various “adjacent structures and ground-supported elements.” Owner demanded that Centex remedy the defects and damage. Despite having demanded that Architect redesign the MSE Wall and repair any damage that resulted from the wall’s failure, Centex spent over $6,000,000 for others to redesign and repair the MSE Wall in September 2004. Centex, as a named insured, requested payment of the available policy limits from Lexington Insurance Company (Lexington) and received payment in the amount of $3,000,000, representing the full policy limit for the claim submitted.

D. District Court Proceedings

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Almarez v. Erbes
New Mexico Court of Appeals, 2022
Tunis v. Country Club Estates
New Mexico Court of Appeals, 2019
L.D. Miller Construction, Inc. v. Kirschenbaum
New Mexico Court of Appeals, 2016
Sherrill v. Farmers Insurance Exchange
2016 NMCA 056 (New Mexico Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 NMCA 013, 9 N.M. 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centexworthgroup-llc-v-worthgroup-architects-lp-nmctapp-2015.