L.D. Miller Construction, Inc. v. Kirschenbaum

CourtNew Mexico Court of Appeals
DecidedDecember 1, 2016
Docket34,253
StatusPublished

This text of L.D. Miller Construction, Inc. v. Kirschenbaum (L.D. Miller Construction, Inc. v. Kirschenbaum) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.D. Miller Construction, Inc. v. Kirschenbaum, (N.M. Ct. App. 2016).

Opinion

1 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

2 Opinion Number: ___________

3 Filing Date: DECEMBER 1, 2016

4 NO. 34,253

5 L.D. MILLER CONSTRUCTION, INC.,

6 Plaintiff-Appellee,

7 v.

8 STEPHEN KIRSCHENBAUM 9 and BARBRO KIRSCHENBAUM,

10 Defendants-Appellants.

11 APPEAL FROM THE DISTRICT COURT OF SANTA FE COUNTY 12 Francis J. Mathew, District Judge

13 Thomas E. Chism 14 Albuquerque, NM

15 for Appellee

16 Coberly & Martinez, LLLP 17 Todd A. Coberly 18 Santa Fe, NM

19 for Appellants 1 OPINION

2 ZAMORA, Judge.

3 {1} In this case, we are presented with the question—can an arbitrator designated

4 by the parties to conduct an arbitration be disqualified by the American Arbitration

5 Association (AAA) for cause if the parties do not also explicitly agree in writing that

6 the arbitrator shall function as a non-neutral arbitrator? The district court ruled that

7 he could be disqualified. We affirm.

8 I. PROCEDURAL AND FACTUAL BACKGROUND

9 {2} In the fall of 2011, Stephen and Barbro Kirschenbaum hired L.D. Miller

10 Construction Company (Miller) to do concrete and framing work for a garage and

11 run-in shed on the Kirschenbaums’ property in Santa Fe, New Mexico. Miller

12 contends the construction project was finished in late fall. However, the

13 Kirschenbaums were apparently unsatisfied with the work and hired other contractors

14 to correct Miller’s work.

15 {3} On December 2, 2011, Miller presented the Kirschenbaums with an invoice for

16 $28,576.46, for its work on their property. The Kirschenbaums paid Miller $15,000

17 toward the balance owed, leaving an outstanding balance of $13,576.46, which the

18 Kirschenbaums refused to pay. There is an allegation that the Kirschenbaums also 1 kept possession of a table saw, tools, and other building materials belonging to Miller

2 valued at approximately $800.

3 {4} On December 20, 2011, Miller and the Kirschenbaums entered into a written

4 Arbitration Agreement. The full text of the Agreement is:

5 Contractor and Owner agree to binding arbitration under AAA 6 (American Arbitration Association) for any dispute (claim, work, 7 material, etc.) between Contractor and Owner at the following location:

8 Hacienda del Cerezo 9 100 Camino del Cerezo 10 Santa Fe, New Mexico 87506

11 (And including or for: Hacienda del Cerezo, Ltd., Stephen/Barbro 12 Kirschenbaum)

13 Contractor and Owner agree that the designated arbitrator shall be Roger 14 Lengyel [(Lengyel)].

15 {5} In April 2013 Miller filed a complaint in the First Judicial District Court

16 against the Kirschenbaums for debt and money due concerning its work on the

17 Kirschenbaums’ property. The Kirschenbaums were served with a summons by

18 certified mail. Though the Kirschenbaums responded informally to Miller’s counsel,

19 they did not enter a timely appearance or file a timely answer or other responsive

20 pleading with the district court. In June 2013 Miller filed a motion for default

21 judgment. No response to the motion was filed by the Kirschenbaums and as a result,

2 1 the district court issued an order granting Miller’s motion for default judgment,

2 finding the Kirschenbaums liable for $16,153.98.

3 {6} Represented by counsel, the Kirschenbaums promptly filed an answer to

4 Miller’s original complaint alleging as an affirmative defense that Miller’s court

5 action was barred by the Arbitration Agreement. The Kirschenbaums also moved to

6 compel arbitration and to vacate the default judgment. In November 2013, the court

7 issued an order granting the Kirschenbaums’ motion to vacate the default judgment

8 and granting their motion to compel arbitration. In particular, the order stated:

9 [T]he [o]rder of [d]efault [j]udgment entered on July 2, 2013[,] is 10 vacated, these proceedings are stayed, and that the parties are compelled 11 to arbitrate this matter pursuant to the terms of the December [20,] 12 2011[, A]rbitration [A]greement, requiring binding arbitration under the 13 [AAA] with . . . Lengyel as the designated arbitrator.

14 {7} Apparently the arbitration did not progress smoothly. On January 22, 2014,

15 Miller sent a letter to AAA requesting disqualification and removal of Lengyel as

16 arbitrator “pursuant to [AAA] Rule []20” for refusing to perform his duties pursuant

17 to required procedures, as well as for lack of independence, i.e., non-neutrality, which

18 was not part of the parties’ agreement. In particular, Miller alleged that “ground

19 rules” set by Lengyel to govern the arbitration were mere “recitals” of the

20 Kirschenbaums’ desire to delay the arbitration process, exclude AAA intervention,

21 and limit communication between the parties and Lengyel. Miller also asserted that

3 1 it had become apparent that Lengyel was having ex parte communications with the

2 Kirschenbaums.

3 {8} In response, the Kirschenbaums sent a letter to the AAA contending that

4 Lengyel could not be disqualified pursuant to the district court’s order compelling

5 arbitration and designation of Lengyel as the parties’ arbitrator. In addition, the

6 Kirschenbaums argued that the parties intended to appoint a non-neutral arbitrator not

7 subject to AAA Rule 20.

8 {9} AAA responded to Miller’s complaint stating: “[i]n light of the [c]ourt [o]rder

9 requiring binding arbitration under the [AAA] with . . . Lengyel as the designated

10 arbitrator, [Miller] may seek clarification from the [c]ourt as to AAA’s authority to

11 address this request for removal.” Miller filed a motion with the district court seeking

12 clarification of its order, arguing that all AAA rules had been incorporated into the

13 Arbitration Agreement. At the hearing on Miller’s motion to clarify, the court

14 observed:

15 When I look at the contract that the parties entered into for the purpose 16 of arbitration, I note that Mr. [Lengyel] is designated but not required [to 17 serve as arbitrator]. What is required is that the parties arbitrate under 18 the rules of AAA. . . .

19 If it were the other way around then potentially the AAA rules 20 would have no meaning. If the arbitrator could as a designated arbitrator 21 . . . ignore or avoid those rules at his discretion then that would put at 22 issue the AAA rules and their requirement of the AAA rules under the 23 parties’ agreement.

4 1 {10} The court issued an order on June 4, 2014,1 concluding that “it was the parties’

2 intent that the arbitration between them would be subject to all the rules and

3 procedures of the [AAA], including the rule regarding disqualification of an

4 arbitrator[,]” and ordered that AAA “has the authority to disqualify designated

5 arbitrator . . . Lengyel, if the AAA determines that such a disqualification is warranted

6 under its rules and procedures.”

7 {11} On July 17, 2014, the Kirschenbaums moved, pro se, for reconsideration of the

8 June 4 order. In pertinent part, the Kirschenbaums argued, “[n]ot disclosed by prior

9 counsel was that both parties specifically discussed and agreed to use . . . Lengyel,

10 an architect very well known to them both—which was paramount to anything else.

11 Using the procedures of the AAA was merely an adjunct to their desire to have Mr.

12 Lengyel decide any dispute.” The Kirschenbaums requested an order finding the

13 AAA rule providing for the removal and substitution of an arbitrator did not apply to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horne v. Los Alamos National Security, L.L.C.
2013 NMSC 4 (New Mexico Supreme Court, 2013)
ConocoPhillips Co. v. Lyons
2013 NMSC 9 (New Mexico Supreme Court, 2012)
Rivera v. American General Financial Services, Inc.
2011 NMSC 033 (New Mexico Supreme Court, 2011)
Wells Fargo Bank, N.A. v. City of Gallup
2011 NMCA 106 (New Mexico Court of Appeals, 2011)
Wakeland v. New Mexico Dep't of Workforce Solutions
2012 NMCA 21 (New Mexico Court of Appeals, 2011)
Western Farm Bureau Insurance v. Carter
1999 NMSC 012 (New Mexico Supreme Court, 1999)
Deerman v. Board of County Commissioners of the County of Dona Ana
864 P.2d 317 (New Mexico Court of Appeals, 1993)
Resolution Trust Corp. v. Ferri
901 P.2d 738 (New Mexico Supreme Court, 1995)
Phelps Dodge Corp. v. Guerra
582 P.2d 819 (New Mexico Supreme Court, 1978)
State Ex Rel. Udall v. Colonial Penn Insurance
812 P.2d 777 (New Mexico Supreme Court, 1991)
James v. Brumlop
609 P.2d 1247 (New Mexico Court of Appeals, 1980)
Borst v. Allstate Insurance Co.
2006 WI 70 (Wisconsin Supreme Court, 2006)
Fashion Fabrics of Iowa, Inc. v. Retail Investors Corp.
266 N.W.2d 22 (Supreme Court of Iowa, 1978)
Washington Mutual Bank v. Freitag
259 P.3d 1 (Court of Appeals of Oregon, 2011)
Edens v. Edens
2005 NMCA 033 (New Mexico Court of Appeals, 2005)
Farmers, Inc. v. Dal MacHine & Fabricating, Inc.
800 P.2d 1063 (New Mexico Supreme Court, 1990)
State v. Sanchez
2015 NMSC 18 (New Mexico Supreme Court, 2015)
Centex/Worthgroup, LLC v. Worthgroup Architects, L.P.
2016 NMCA 013 (New Mexico Court of Appeals, 2015)
Walker v. Baker
582 P.2d 7 (Oregon Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
L.D. Miller Construction, Inc. v. Kirschenbaum, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ld-miller-construction-inc-v-kirschenbaum-nmctapp-2016.