McKinney Drilling Co. v. Collins Co., Inc.

517 F. Supp. 320, 1981 U.S. Dist. LEXIS 9814
CourtDistrict Court, N.D. Alabama
DecidedJune 15, 1981
DocketCiv. A. 80-G-0814-S
StatusPublished
Cited by13 cases

This text of 517 F. Supp. 320 (McKinney Drilling Co. v. Collins Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKinney Drilling Co. v. Collins Co., Inc., 517 F. Supp. 320, 1981 U.S. Dist. LEXIS 9814 (N.D. Ala. 1981).

Opinion

MEMORANDUM OPINION

GUIN, District Judge.

This action is for breach of contract, and for recovery under a labor and material payment bond pursuant to § 39-1-1 of the Code of Alabama (1975). Jurisdiction over this action exists under 28 U.S.C. § 1332 by reason of the diversity of citizenship and the amount in controversy. After hearing the evidence at trial and considering the briefs of counsel and applicable law, this court incorporates in this memorandum opinion the appropriate findings of fact and conclusions of law, as authorized by Rule 52 of the Federal Rules of Civil Procedure.

This controversy stems from a subcontract entered into by the parties under which the plaintiff, McKinney Drilling Company (McKinney), agreed to install eight 72-inch diameter drilled caissons 1 for the defendant, The Collins Company (Collins). This subcontract comprised a portion of the work to be performed in the construction of the Dry Creek Wastewater Treatment Plant near Decatur, Alabama. Collins served as the general contractor of that project for the City of Decatur.

The City had previously retained Paul B. Krebs Associates, Inc., consulting engineers, to prepare the construction contract documents, including drawings and specifications, and to oversee the work. After the documents were completed, the project was put out for bids. The Collins Company intended to bid on the project and therefore solicited bids from subcontractors on various aspects of the work. McKinney specializes in drilling work, usually as a subcontractor, and was interested in doing the caisson work for the project.

On April 26, 1979, the date of the bid opening, Hal McKewen, Alabama district manager for McKinney, telephoned The Collins Company to provide it with a bid for installing eight 72-inch diameter caissons at the Dry Creek project. He spoke with a representative of Collins who was receiving telephone bids from subcontractors for that job. McKewen advised him that McKinney’s base price was $110,960.00, and that the base price included all earth excavation to the depth indicated in the caisson drawings, the specified test holes, and one foot of rock excavation per caisson.

Collins was the low bidder and was subsequently awarded the contract by the City, which was not executed until July 24, 1979.

On May 21, 1979, McKinney sent Collins its written proposal for the base price of $110,960.00. The proposal stated that it included all earth excavation, the furnishing and placing of all caisson concrete, the specified test holes, and one foot of rock excavation per caisson. The proposal specified that it be made a part of the subcontract, and also stated that unit prices for additional earth and rock excavation would be negotiated before the work began. McKinney’s written proposal also required that final payment for the caisson work would be due sixty days after McKinney completed its portion of the work.

On July 6,1979, L. D. Collins, president of The Collins Company, discussed with Hal McKewen on the telephone the unit prices for additional earth and rock excavation. It was agreed that the unit prices would be $155.00 per linear foot of earth excavation and concrete fill, and $575.00 per linear foot of rock excavation and concrete fill, the adjustment to be made for more or less excavation. 2

*323 In July, 1979, McKinney received the subcontract for the caisson work. The subcontract was prepared by L. D. Collins, on Collins’ standard subcontract form, except for McKinney’s proposal which was incorporated into the subcontract. The subcontract was dated July 16, 1979.

On July 24, 1979, the same date it executed the general contract, Collins posted the Labor and Material Payment Bond with the City, as required by § 39-1-1 of the Code of Alabama (1975). The defendant United States Fidelity and Guaranty Company (USF&G) executed the bond as surety.

McKinney commenced the caisson work on October 10,1979, and completed pouring the concrete for the last caisson on November 20, 1979. On October 25, 1979, McKinney submitted to Collins its first application for payment which reflected that it had completed 25 percent of the caisson work. Collins paid McKinney the requested payment of $24,966.00 by check dated November 28, 1979.

On November 27, 1979, McKinney submitted to Collins its application for final payment. The application contained a worksheet showing the adjustments McKinney claimed should be made to the base price, and which amounted to an additional sum of $46,955.50 over the base price. These adjustments were recomputed in March of 1980, and mathematical errors were found in the November, 1979 worksheet. It was also discovered that Collins had not been billed for all of the test holes installed. The corrections lowered the additional amount to be added to the base price to $36,424.65. On March 24, 1980, McKinney sent the revised application for final payment to Collins along with the corrected worksheet showing the adjustments made to the base price. These adjustments re-suited in a total subcontract price of $147,-348.65. Since Collins had previously paid the sum of $74,966.00, 3 the final application for payment requested the sum of $72,-418.65.

In early April, 1980, L. D. Collins informed Hal McKewen that The Collins Company would not pay the amount requested by McKinney. On April 15, 1980, McKinney notified USF&G by certified mail, pursuant to § 39-1-1 of the Code of Alabama (1975), that Collins owed it the sum of $72,418.65 for caisson work performed at the Dry Creek Wastewater Treatment Plant. USF&G acknowledged receipt of McKinney’s notice letter. No payment was made by USF&G nor Collins within 45 days. The efforts of the parties’ counsel to settle the dispute failed, and suit was filed on June 24, 1980.

On July 14, 1980, Collins paid McKinney the amount of $34,973.05, which Collins recognized as due. Added to the previous payments, the amount paid by Collins to McKinney totalled $109,939.05. This amount reflected the original contract price, plus an agreed extra of $636.00 for test holes, but minus adjustment of $1,656.95 for less drilling and concrete due to minor changes in caisson elevations.

The case proceeded to trial without any further payments being made. The defendants stipulated at trial that if the court found Collins liable to McKinney, then USF&G would also be liable to McKinney by virtue of the Labor and Material Payment Bond.

The general issue before the court surrounds the interpretation of the subcontract between McKinney and Collins. The court is of the opinion that McKinney correctly interprets the subcontract as requiring the base price to be adjusted for additional rock *324 excavation, and therefore enters judgment in favor of McKinney.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DON PERRY v. ZONING BOARD OF APPEALS OF HULL & others.
100 Mass. App. Ct. 19 (Massachusetts Appeals Court, 2021)
Madison Cnty. v. Evanston Ins. Co.
340 F. Supp. 3d 1232 (N.D. Alabama, 2018)
Centex/Worthgroup, LLC v. Worthgroup Architects, L.P.
2016 NMCA 013 (New Mexico Court of Appeals, 2015)
Smith v. Homes Today, Inc. (In Re Smith)
296 B.R. 46 (M.D. Alabama, 2003)
ERA Commander Realty, Inc. v. Harrigan
514 So. 2d 1329 (Supreme Court of Alabama, 1987)
APAC-Tennessee, Inc. v. J.M. Humphries Construction Co.
732 S.W.2d 601 (Court of Appeals of Tennessee, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
517 F. Supp. 320, 1981 U.S. Dist. LEXIS 9814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckinney-drilling-co-v-collins-co-inc-alnd-1981.