John W. Johnson, Inc. v. Basic Construction Co.

429 F.2d 764, 139 U.S. App. D.C. 85
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 22, 1970
DocketNos. 22813, 22814, 22836, 22837
StatusPublished
Cited by20 cases

This text of 429 F.2d 764 (John W. Johnson, Inc. v. Basic Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John W. Johnson, Inc. v. Basic Construction Co., 429 F.2d 764, 139 U.S. App. D.C. 85 (D.C. Cir. 1970).

Opinion

MacKINNON, Circuit Judge:

This is an appeal in a breach of contract case brought by John W. Johnson, Inc., a painting subcontractor, against Basic Construction Co., the prime contractor, and Edward Durell Stone, the architect. The project involved the construction of several buildings for the State University of New York at Albany. Basic Construction Company (hereinafter Basic) contracted to construct these buildings for a compensation of approximately $25 million, and subcontracted out the painting and wall-covering work to John W. Johnson, Inc. (hereinafter Johnson), a Washington, D. C. corporation, for $375,000. The architect, Edward Durell Stone (Stone) was the agent of the owner, the State University Construction Fund (hereinafter the Fund), and was in charge of supervising the construction. Jurisdiction is vested in this court by D.C.Code §§ 11-101 and 11-521. The amount in controversy exceeds $10,000 exclusive of interest and costs.

Johnson commenced work under its subcontract in April of 1965. By September, some peeling of the paint on the ceilings in the Biology Building had been observed, and by October the condition had worsened to the point where Johnson was directed to stop painting all the ceilings.1 At this time no one knew the cause of the peeling. The architect called in a research firm which eventually determined that the peeling was caused by the presence of stearic acid on the ceiling. Stearic acid had been employed by Basic as a release agent in removing the temporary molds used in forming the concrete arches which constituted the ceilings. The research firm recommenced that either the stearic acid be removed or that a primer coat of paint be applied which would permit a secure bond for the two final coats. Because the stearic acid was difficult to remove, the architect after some time spent in experimenting adopted the solution of removing the peeling paint and then applying the additional coat of primer paint. However, on December 20, 1965 he ordered that Basic bear this cost on the ground that it was its responsibility under its contract to remove foreign substances from the ceilings before painting. Basic disputed this liability and appealed to the Fund under a Disputes Clause in the prime contract; meanwhile on December 22nd it ordered Johnson to proceed with the application of the additional paint in accordance with the architect’s directive.2 The ar[767]*767chitect’s directive stated the work was “in lieu of, not in addition to, original contract requirements” and that “No extra to contract will be approved by this office, for this work.” Johnson denied any responsibility for the failure, on request , submitted an estimate as to the cost of the extra painting, requested a change order or other definite assurance of payment it claimed it was entitled to under its contract, and started the painting under protest without relinquishing its right to compensation. Basic did agree to advance Johnson $1,500 a month to assist the latter to meet some of the cost of the additional painting. However, Basic expressly conditioned its advances with the reservation that same did not constitute an acknowledgment of liability to Johnson for the disputed painting work.

The Fund then on January 10, 1966 rendered its decision upon the appeal by Basic. It determined that the stearic acid had been used with the architect’s knowledge and approval, that the removal of the stearic acid by means of “exotic” cleaning compounds was not anticipated under its contract with Basic,3 and that the Fund would therefore bear the cost of the additional coat of primer. However, apparently as a compromise with Basic, the Fund held that Basic was responsible for removing the defective coat of paint on the ground that it should have tested the adhesiveness of the paint before commencing the painting operations. Although Basic denied this liability, it nevertheless agreed to continue work and to resolve the matter at a later date.4

In summary, there was at this point an unresolved three-way dispute as to who should bear the cost of removing the original coat of paint. The Fund had ruled that Basic should bear the cost; this was disputed by Basic who contended the responsibility should lie on the Fund. Johnson was caught in this cross fire — it had denied liability entirely and was interested primarily in receiving some assurance of payment for the extra work it was being directed to perform and of being absolved from liability for the expense of removing the paint in the peeling areas.

Another element was then injected into this unstable situation. Painting had been stopped, first for strikes in July and August, and secondly since early October while the cause of the peeling was being determined, and the Fund thereafter became increasingly upset over the slow progress being made in the painting due to the fact that Johnson was not employing what the Fund considered to be an adequate number of painters to meet completion deadlines. The Fund put pressure on Basic to speed up the work and Basic in turn warned Johnson that more painters would be needed to meet the approaching completion deadlines. During this time Johnson was complaining that he had not received the change orders required by his subcontract before he could be assured of payment for the extra work, that he had not been absolved of responsibility for the cost of removing the ceiling paint in the Biology Building and that to accelerate the work by adding the additional workmen being required by the Fund would decrease their efficiency and substantially increase his cost, for which he should also receive some assurance that he would be compensated. A temporary working arrangement was reached between Johnson [768]*768and Basic to gradually build up the painting crews, but apparently this was not enough to satisfy the architect, Edward Stone, who recommended to the Fund that Johnson’s contract be can-celled. The Fund agreed, and on February 9, 1966, the architect Stone wrote Basic directing it to cancel its subcontract with Johnson and advising that no extension of time would be granted for this cancellation.5

Basic, however, was reluctant to discharge Johnson. Basic did notify Johnson by telephone of the February 9th directive it had received to cancel his contract but recommended that Johnson come in to discuss the matter. This Johnson refused to do, and the next day informed Basic that unless it received an assurance of payment for the extra work, it would quit the job.

Again on February 12th, Johnson, according to Basic’s memorandum of a telephone conversation, demanded that Basic send him a telegram or letter “cancelling his contract if that was what he intended to do.” Later in the day, Johnson’s attorney orally informed Basic that Johnson was not financially able, even if he so desired, to carry the burden of increasing the number of painters to 60 or 80 without some help and agreed that Johnson would submit information as to the extra cost for the third coat of paint and for escalating of the work. On February 14th Basic wrote the Fund and requested them to conform to the contract and to state they had determined that Johnson was “incompetent, careless or uncooperate [uncooperative]”, if they had so determined.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tower Insurance Company of New York v. davis/gilford, a Joint Venture
967 F. Supp. 2d 72 (District of Columbia, 2013)
3A Industries, Inc. v. Turner Construction Co.
869 P.2d 65 (Court of Appeals of Washington, 1993)
Commerical v. Gilbane
First Circuit, 1993
Vermont Marble Co. v. Baltimore Contractors, Inc.
520 F. Supp. 922 (District of Columbia, 1981)
McKinney Drilling Co. v. Collins Co., Inc.
517 F. Supp. 320 (N.D. Alabama, 1981)
Blake Construction Co. v. C. J. Coakley Co.
431 A.2d 569 (District of Columbia Court of Appeals, 1981)
Sime Construction Co. v. Washington Public Power Supply System
621 P.2d 1299 (Court of Appeals of Washington, 1981)
United States v. Snooks
493 F. Supp. 1364 (W.D. Missouri, 1980)
Larionoff v. United States
365 F. Supp. 140 (District of Columbia, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
429 F.2d 764, 139 U.S. App. D.C. 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-w-johnson-inc-v-basic-construction-co-cadc-1970.