Clarke Baridon, Inc., and Cross-Appellant v. Merritt-Chapman & Scott Corporation, and Cross-Appellee

311 F.2d 389, 1962 U.S. App. LEXIS 3199
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 28, 1962
Docket8605_1
StatusPublished
Cited by22 cases

This text of 311 F.2d 389 (Clarke Baridon, Inc., and Cross-Appellant v. Merritt-Chapman & Scott Corporation, and Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clarke Baridon, Inc., and Cross-Appellant v. Merritt-Chapman & Scott Corporation, and Cross-Appellee, 311 F.2d 389, 1962 U.S. App. LEXIS 3199 (4th Cir. 1962).

Opinion

HAYNSWORTH, Circuit Judge.

A second-tier subcontractor sought additional compensation from the first-tier subcontractor arising out of work performed on the Truax Air Force Base at Madison, Wisconsin, and at Fort Custer, Michigan. The District Judge allowed some claims, allowed others in part and denied still others. The defendant has appealed from the partial allowance of certain of the claims, while the plaintiff has cross-appealed from the denial of others.

The United States employed Western Electric Company to design and construct buildings and other facilities at certain military bases for use as part of the Semi Automatic Ground Environment System (SAGE). Later Western entered into fixed price contracts with Merritt-Chapman & Scott Corporation for the actual construction of the buildings and facilities at Truax Air Force Base and at Fort Custer. Merritt, the first-tier subcontractor, the defendant here, in turn entered into a contract with Clarke Baridon, Inc., a second-tier subcontractor and plaintiff here, for the insulation of pipes and duct work at Truax and at Fort Custer. Baridon’s insulation contract for Truax was for a fixed price of $159,000, while its insulation contract for Fort Custer was on a fixed price basis of $99,000.

Commencement of the work at Truax was delayed by soil conditions necessitating additional excavation, a delay in the driving of piles and by a strike. It was prolonged and complicated by a large number of change orders amounting to approximately thirty per cent of the original contract price. Change orders are expected by contractors such as Merritt and Baridon, though the record indicates that the value of change orders usually does not exceed ten per cent of the contract price, and provision was made for compensation to Baridon to the extent that direct change orders im *392 posed additional cost upon it. With respect to the work at each place, therefore, Baridon has been paid the original contract price increased by compensation attributable to change orders directed to it. Additionally, it has received certain other sums on account of increased costs at Truax, such as $6,464.21 paid to it on account of increased board expense of its employees working upon that project. In addition to all of that, Baridon submitted claims for additional compensation at Truax aggregating $81,952.81 and another claim on account of an alleged “excess labor” cost which it finally evaluated at $24,239.75, making a total claim of $106,192.56 1 at Truax. It filed two claims aggregating $9,992.02 for additional compensation in connection with the work at Fort Custer.

Generally, Baridon’s claims for additional compensation on account of increased costs were submitted by Merritt to Western with recommendations that they be accepted. Western investigated the claims and allowed the Truax claims to the extent of $26,467.70. On account of these claims, Merritt has actually paid to Baridon the sum of $31,412.75.

The District Court found that Baridon was entitled to additional compensation at Truax in the amount of $1,824.95 for increased labor costs, $2,562.45 for material cost increases, $16,940 on account of board expense for nonresident labor, that amount being in addition to the amounts previously paid on that account, $4,344.45 for overtime work costs, $12,-000 for excess labor, $1,895.84 for the insulation of hubs at Truax, $879.75 for payroll taxes, insurance costs and overhead on the overtime pay claims, and $8,805.81 for overhead and profit on the other items. After crediting Merritt with the $31,412.75 previously paid, the District Court allowed prejudgment interest of $8,640.50 computed at the rate of six per cent per annum upon the net balance which it found to be due. Accordingly, it entered judgment for the plaintiff in the sum of $22,479.03.

I

Baridon has appealed from so much of the judgment below as denied it recovery on its claim of $13,653.42 for the installation of brattice cloth at Truax, its claim of $6,182.73 for the use of wire mesh at Truax, its claim of $8,973.12 for the installation of brattice cloth at Fort Custer, and its claim of $1,018.90 for the insulation of hubs, at Fort Custer.

A

Brattice Cloth at Truax Western’s contract with Merritt was based upon Merritt’s bid, with respect to the insulation of duct work, of 10$ per square foot for both exposed and unexposed duct with an additional charge of 400 per square foot for surfaces finished with plaster. It invited bids from insulation contractors on the basis of the same categories. It originally received from Baridon a bid which, to the extent here relevant, provided:

Merritt declined to accept this bid, reporting that it had no unit price for brattice cloth from Western. Merritt insisted that the categories fixed by Western be accepted by Baridon, and presumably by other bidders for the insulation subcontract. Though the specifications plainly provided that, when the insulation coating on exposed duct work is still wet, a layer of brattice cloth should be embedded in it and given a finish-coat of white insulation coating, Baridon did not change its bid of 54$ and 62$ on the exposed duct work, but deleted the special item of brattice cloth *393 from its bid. It did so with the understanding that Merritt would attempt to obtain a special unit price for brattice cloth from Western, but Merritt was unsuccessful in that endeavor.

Brattice cloth is a heavy, loosely woven cotton fabric filled with a flame resistant material. To finish duct insulation with brattice cloth is approximately as expensive as to finish it with plaster, but, because Baridon bid less for exposed duct work, though the specifications required brattice cloth on all such duct work, at a lower sum than for plaster finish, it claimed additional compensation of $13,653.42 on account of brattice cloth installed at Truax.

In denying this claim, the District Court referred to the testimony of Clarke Baridon:

“The wording was very ambiguous. When we came back on the thing, they said, ‘We have already submitted the unit prices that are in our schedule to Western Electric. You will have to accept those figures.’ In other words, we were boxed. We had a choice of forgetting the whole contract or leave it go.”

On appeal, Baridon contends that this testimonial statement related to additional charges of ten per cent for overhead and ten per cent for profit, to which Mr. Baridon had referred immediately before the quoted statement. However, it is plain from the testimony of both Clarke Baridon and Richard Baridon that they were informed before the contract was entered into that the bidding had to be based upon one unit price for exposed duct work without any separate price for brattice cloth finish. Baridon could have increased its unit prices for exposed duct work or it could have withdrawn from the bidding. When it chose to do neither and thereafter entered into a formal contract based upon its quoted unit prices, there is no basis for a claim that it misinterpreted the invitation or that it inadvertently omitted a unit price for brattice cloth.

B

Wire Mesh at Truax

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Port East Transfer, Inc. v. Liberty Mutual Insurance
624 A.2d 520 (Court of Appeals of Maryland, 1993)
Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc.
439 F. Supp. 671 (E.D. Pennsylvania, 1977)
Three Rivers Motors Company v. Ford Motor Company
374 F. Supp. 620 (W.D. Pennsylvania, 1974)
John W. Johnson, Inc. v. Basic Construction Co.
429 F.2d 764 (D.C. Circuit, 1970)
Johns Hopkins University v. Hutton
297 F. Supp. 1165 (D. Maryland, 1968)
Clifton D. Mayhew, Inc. v. George A. Fuller Co.
234 A.2d 599 (Court of Appeals of Maryland, 1967)
Wallace Process Piping Co. v. Martin-Marietta Corp.
251 F. Supp. 411 (E.D. Virginia, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
311 F.2d 389, 1962 U.S. App. LEXIS 3199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clarke-baridon-inc-and-cross-appellant-v-merritt-chapman-scott-ca4-1962.