Slaw Construction Corp. v. Brady (In re Slaw Construction Corp.)

28 B.R. 540, 1983 Bankr. LEXIS 6555
CourtUnited States Bankruptcy Court, E.D. Pennsylvania
DecidedMarch 23, 1983
DocketBankruptcy No. 80-00759G; Adv. No. 80-0405G
StatusPublished
Cited by1 cases

This text of 28 B.R. 540 (Slaw Construction Corp. v. Brady (In re Slaw Construction Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slaw Construction Corp. v. Brady (In re Slaw Construction Corp.), 28 B.R. 540, 1983 Bankr. LEXIS 6555 (Pa. 1983).

Opinion

OPINION

WILLIAM A. KING, Jr., Bankruptcy Judge:

The issue at bench is whether the debtor has completed all the terms and fulfilled all of the conditions of a contract with the defendant for certain paving work to entitle the debtor to the final payment due under that contract. We conclude that the debtor has completed all the terms and fulfilled all the conditions of the contract and is, thus, entitled to the final payment.

The facts of the instant case are as follows: 1 On June 27,1979, Slaw Construction [542]*542Company (“the debtor”) and Warren A. Brady, Jr., t/a Warren A. Brady Excavating (“Brady”) entered into a written agreement wherein the debtor agreed to perform certain paving work at a parking lot under construction for the sum of $62,900.00. In addition to the aforesaid agreement, the debtor rented equipment to Brady during the period of June 6,1979, through June 19, 1979, pursuant to a separate oral agreement. On June 20, 1979, the debtor commenced work under the terms of the written paving contract and finished the work on July 7,1979. The debtor thereafter rendered its invoices to Brady for the paving work in the amount of $62,900.00 and for the rental of equipment in the amount of $4,245.23. Brady paid $3,683.63 to the debt- or for the equipment rental. However, when the debtor demanded payment of the $62,900.00 from Brady, he advised the debt- or that he had not been paid by his contractor, Anthony DiAntonio, Inc. (“DiAntonio”), but that arrangements had been made to have DiAntonio pay the debtor directly and DiAntonio would, in turn, charge Brady’s account for the $62,900.00.2 The debtor received two (2) checks from DiAntonio, one dated July 31, 1979, in the amount of $40,-000.00 and another check post-dated August 16, 1979, for $22,900.00. The debtor presented the $40,000.00 check for payment, but said check was returned to the debtor marked “payment stopped.” The debtor then informed Brady that the $40,000.00 check from DiAntonio had not been honored and Brady thereafter delivered to the debt- or a certified check for $40,000.00 and said check was cashed. Brady then advised the debtor to present the second DiAntonio check for $22,900.00 for payment but when the debtor did so, that check was also returned marked “payment stopped.” Consequently, the debtor demanded that Brady pay the balance due of $22,900.00, but was told by Brady that he would pay when he collected funds he claimed were due him from DiAntonio. On July 28, 1980, the debtor filed the instant complaint against Brady demanding judgment against Brady in the amount of $23,261.60,3 plus interest and costs. On September 4, 1980, Brady filed an answer wherein he alleges that the debtor agreed to look to DiAntonio for payment for the paving and that DiAntonio agreed to make said payment. The answer also contained “third party claim” against “additional defendant” DiAntonio alleging that DiAntonio is alone liable or liable over to Brady for the amount if any, due the debtor.

At the outset, we note that the debtor and Brady are the only signatories to the paving contract,4 which provides, in pertinent part:

(1) the lump sum price is $62,900.00
* * * * * *
(6) Billing to be once a month, payment within 5 days, 10% retainage
(7) Retainage to be paid within 30 days of satisfactory completion of this contract. Payment of retainage must not be effected by work or conditions not covered by this contract
* * * * * *

Nevertheless, Brady maintains that the aforesaid contract required: (1) that the debtor look to DiAntonio for payment for the work done; and (2) that the work performed by the debtor was subject to approval and acceptance by DiAntonio. Brady so contends despite the fact that the paving contract makes absolutely no mention of DiAntonio and contains no provision for third party acceptance of the work performed. The Supreme Court of Pennsylva[543]*543nia, in East Crossroads Center, Inc. v. Mellon-Stuart Co., 416 Pa. 229, 230-31, 205 A.2d 865, 866 (1965), has held:

When a written contract is clear and unequivocal, its meaning must be determined by its contents alone. It speaks for itself and a meaning cannot be given to it other than that expressed. Where the intention of the parties is clear, there is no need to resort to extrinsic aids or evidence.

This is precisely the case at hand. The paving contract is precise and unambiguous and the only two parties who signed it are bound “by its contents alone.” Since the paving contract made no provision for third party acceptance of the work done or for payment from a third party, we conclude that the paving contract obligated Brady to pay the debtor $62,900.00 upon satisfactory completion of work performed within the time specified therein.

In addition, we are unable to conclude that the paving contract was in any way modified to change the result reached above. Brady testified, regarding the payment-within-5-days provision contained in paragraph six (6) of the paving contract, that he told the debtor’s president that “I can’t pay you in five days because I don’t have that kind of money. When I get paid you’ll get paid” (N.T. 10/26/81 at 32). Brady further testified that the debtor’s president replied “Fine. It’s a formality” (N.T. id.). While we are mindful that parties may modify a written contract which they previously have entered into by subsequent oral agreement,5 we can find no evidence of any modification of the paving contract involved herein other than the testimony of Brady recited above. This testimony, standing alone, does not constitute adequate proof that Brady and the debtor agreed to modify the five-day provision contained in paragraph six (6) of the paving contract.

As to Brady’s contention that the work done by the debtor was not, in fact, performed satisfactorily, we are unable to find any evidence in the record, beyond Brady’s allegations, which establishes that the paving project was not properly completed. To the contrary, the debtor introduced photographs of the work in question which show, to our satisfaction, that the paving was performed and completed in a workmanlike manner.6 In any event, we find it disposi-tive that Brady produced no photographic evidence of faulty workmanship or expert testimony establishing the same. In short, Brady adduced no credible evidence to contradict the debtor’s demonstration that the paving work was satisfactorily completed. To the contrary, Brady himself tendered a certified check for $40,000.00 to the debtor for the alleged “unsatisfactory work”.7

We next consider the debtor’s contention that it is owed a balance of $361.60 for the equipment rental. Brady testified that his check to the debtor for $3,683.63 represented payment in full under the oral equipment rental agreement (N.T. 10/26/81 at 34). The record establishes that Brady and the debtor did, in fact, modify the rental agreement to reflect a $200.00 credit given to Brady by the debtor for fuel supplied by Brady to run a rented bulldozer (N.T. 10/26/81 at 18). This modification is evidenced by an appropriate notation on the $3,683.63 check deducting the $200.00 from the amount owed for the bulldozer rental.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Franks
95 B.R. 346 (E.D. Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
28 B.R. 540, 1983 Bankr. LEXIS 6555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slaw-construction-corp-v-brady-in-re-slaw-construction-corp-paeb-1983.