Wagner v. Graziano Construction Co.

136 A.2d 82, 390 Pa. 445
CourtSupreme Court of Pennsylvania
DecidedNovember 18, 1957
DocketAppeal, 175
StatusPublished
Cited by52 cases

This text of 136 A.2d 82 (Wagner v. Graziano Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wagner v. Graziano Construction Co., 136 A.2d 82, 390 Pa. 445 (Pa. 1957).

Opinion

Opinion by

Mr. Justice Musmanno,

Edward J. Wagner entered into a contract with Graziano Construction Company to paint and supply materials in connection with the construction of the Heights Plaza Shopping Center in Natrona Heights by the Graziano Company as general contractors. The agreement between Wagner and Graziano provided, inter alia: “Without invalidating this contract the Contractor may add to or reduce the work to be performed hereunder. No extra work or changes from plans and specifications under this contract will be recognized or paid for, unless agreed to in writing before the extra work is started or the changes made, in which written order shall be specified in detail the extra work or *447 changes desired, the price to be paid or the amount to be deducted should said change decrease the amount to be paid hereunder.”

Wagner claims that while fulfilling his obligations under the contract he was orally requested by the defendant’s general superintendent to perform some extra work and supply additional material, the superintendent assuring him that such orders did not need to be in writing, despite the provision to that effect in the contract. Wagner states that then after acceding to the oral demands of the defendant’s general superintendent, Graziano refused to pay for the supplemental work and additional materials. He accordingly brought suit against Graziano for the amount of $5,192.22. Graziano filed preliminary objections, demurring on the ground that the complaint failed to state a cause of action because it was based on oral orders which were excluded by the contract. The lower Court sustained the objections and dismissed the complaint. Wagner appealed.

In his complaint Wagner averred: “In directing plaintiff to perform work not within the scope of work to be performed under the written contract, defendant’s general superintendent refused to sign written work orders as required by said written contract: he informed plaintiff that written work orders signed by him would not be required and directed him to perform the extra work without the written work orders, informing plaintiff that appropriate adjustments would be agreed upon at a later date.”

For the purposes of the demurrer, this allegation, together with those averring the superintendent’s authority, must be accepted as established fact. Thus, if we assume that the defendant’s authorized agent in-formed Wagner that the requirement for written orders for extra work was being waived, we are then con *448 cerned only with a determination of the question as to whether parties to a written contract may alter it by an oral understanding. There is nothing sacrosanct about a written agreement. Granted that writing makes for specificity and clarity, reduces the chances for errors, and allows for constant reference as to what was agreed upon, it nevertheless holds no superior position over an oral compact in the realm of authoritative utterances, except where the Statute of Frauds intervenes or is invoked. The most ironclad written contract can always be cut into by the acetylene torch of parol modification supported by adequate proof. In Achenbach v. Stoddard, 253 Pa. 338, this Court held: “ ‘It is always competent for the parties to a written contract to show that it was subsequently abandoned in whole or in part, modified, changed, or a new one substituted. And this may be shown by parol by showing either an express agreement or actions necessarily involving the alterations.’ ”

Even where the contract specifically states that no non-written modification will be recognized, the parties may yet alter their agreement by parol negotiation. The hand that pens a writing may not gag the mouths of the assenting parties. The pen may be more precise in permanently recording what is to be done, but it may not still the tongues which bespeak an improvement in or modification of what has been written. In the case of Prudden-Winslow v. Stipp, 76 Pa. Superior Ct. 530, the contract there under consideration provided: “No verbal understanding or agreement not contained in writing on the face of the order (and these conditions) shall be considered of any force whatever.” A dispute later arose between the parties as to whether this provision of the contract had been violated. Judge Maxey of the Court of Common Pleas of Lackawanna County (later Chief Justice of this Court.) held that *449 modification of a contract was always in order. The Superior Court affirmed his position, Judge Trexler saying: “Notwithstanding the written contract, the parties were still free agents. They could change it if they so desired.”

In the case of Knight v. Gulf Refining Co., 811 Pa. 357, 360, Justice Kephart (later Chief Justice) said': “Parties may, by subsequent oral agreement, modify a written contract which they previously have entered into. The new contract thus agreed upon is a substitute for the original one in so far as it alters, modifies or changes it.”

We, therefore, hold that G-raziano’s agent and Wagner could legally covenant to waive a specific stipulation in the contract. Minds may meet in the field of oral concord as well as between the borders of parchment or paper.

Having resolved the first problem we come to the query: Did Wagner’s complaint sufficiently allege a modification or waiver of a condition in the contract by a duly authorized agent of the defendant Graziano? We are satisfied that it did. The complaint alleges: (1) that defendant’s general superintendent “was the duly authorized agent of defendant and was acting within the scope of his authority” in entering into subsequent verbal agreements for extras, (2) that this agent “had actual and implied authority to bind defendant and to enter into verbal contracts with plaintiff modifying and supplementing the terms of said written contract between plaintiff and defendant, particularly with respect to the addition or reduction of work to be performed by plaintiff in fulfillment of his obligations under said contract”, and (3) that the plaintiff performed extra work pursuant to verbal agreements which waived the necessity for written work orders, “entered into between plaintiff and defendant, *450 through defendant’s said agent who was acting within the scope of his authority, actual or implied. . .

Graziano contends that the allegations as to authority, etc., are immaterial because “it was not within the power of an agent for the defendant contractor to vary the terms of the contract by any oral promise or agreement.” Whether or not Graziano’s general superintendent, as alleged in the complaint, possessed the authority to waive terms of the agreement, or whether his actions in this respect were adopted by Graziano as authorized actions, would be matters of proof to be presented by the plaintiff. Neither the case of Gillison v. Wanamaker, 140 Pa. 358 relied on by the lower Court nor the case of Gibbs v. School District of Girardville, 195 Pa. 396 relied on by Graziano controls the question before us, for those cases merely decided that an architect as such has no ostensible power to authorize performance of extra work except in accordance with terms of the written agreement. Nor is the case of Malone v. Philadelphia, 147 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Environmental Group, Inc. v. GKK McKnight, LP
176 A.3d 946 (Superior Court of Pennsylvania, 2017)
Scungio Borst v. 410 Shurs Lane Developers, LLC
106 A.3d 103 (Superior Court of Pennsylvania, 2014)
Scungio Borst v. 410 Shurs Lane
Superior Court of Pennsylvania, 2014
Newby, D. v. Newby, D.
Superior Court of Pennsylvania, 2014
Crown Coal & Coke Co. v. Powhatan Mid-Vol Coal Sales, L.L.C.
929 F. Supp. 2d 460 (W.D. Pennsylvania, 2013)
Dechant v. Dechant
24 Pa. D. & C.5th 211 (Bucks County Court of Common Pleas, 2011)
Mitsubishi Corp. v. Goldmark Plastic Compounds, Inc.
446 F. Supp. 2d 378 (W.D. Pennsylvania, 2006)
Angel Medical Center, Inc. v. Abernathy
159 F. Supp. 2d 215 (W.D. North Carolina, 2000)
Truhe v. Turnac Group, L.L.C.
1999 SD 118 (South Dakota Supreme Court, 1999)
Beal v. Krock
First Circuit, 1998
Empire Properties, Inc. v. Equireal, Inc.
674 A.2d 297 (Superior Court of Pennsylvania, 1996)
In Re H & G Distributing, Inc.
158 B.R. 959 (E.D. Pennsylvania, 1993)
Delaware River Port Authority v. Thornburgh
585 A.2d 1123 (Commonwealth Court of Pennsylvania, 1991)
In Re Chateaugay Corp.
116 B.R. 887 (S.D. New York, 1990)
LTV Corp. v. Aetna Casualty & Surety Co.
116 B.R. 887 (S.D. New York, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
136 A.2d 82, 390 Pa. 445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wagner-v-graziano-construction-co-pa-1957.