Gibbs v. School District of Girardville

46 A. 91, 195 Pa. 396, 1900 Pa. LEXIS 655
CourtSupreme Court of Pennsylvania
DecidedApril 23, 1900
DocketAppeal, No. 29
StatusPublished
Cited by3 cases

This text of 46 A. 91 (Gibbs v. School District of Girardville) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gibbs v. School District of Girardville, 46 A. 91, 195 Pa. 396, 1900 Pa. LEXIS 655 (Pa. 1900).

Opinion

Opinion by

Mb. Justice Mestbezat,

By an agreement dated March 18, 1896, the plaintiffs contracted to erect for the defendant a school building in the borough of Girardville, in Schuylkill county, for the sum of $13,238, “subject to additions and deductions as provided” in the contract. The contractors were to provide the materials and perform the work in accordance with the plans, drawings, details and specifications prepared by the architect. This work was to be done and the materials were to be furnished by “ the contractor under the direction and to the satisfaction of the board of school directors and P. Rudrauff, architect, acting for the purposes of the contract as agent of the said owners.” Article 2 of the contract provides that the architect shall furnish the contractors with such other drawings or explanations as may be necessary to detail and illustrate the work to be done, and requires the contractors to conform to the same as part of the contract so far as they may be consistent with the original drawings and specifications. Article 3 is as follows: “No alterations shall be made in the work shown or described by the drawings and specifications except upon a written order of the architect, and when so made, the value of the work added or omitted shall be computed by the architect and the amount so ascertained shall be added to or deducted from the contract price. In the case of dissent from such award by either party hereto, the valuation of the work added or omitted shall be referred to three disinterested arbitrators, one to be appointed by each of the parties to this contract and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of the parties hereto shall pay one half of the expenses of such conference.” Article 4, provides that the contractors “ shall, within twenty-four hours after receiving written notice from the architect to that effect, proceed to remove from the grounds or buildings, all materials condemned by them, whether worked or unworked, and to take down all portions of the work which the architect shall by like written notice, condemn as unsound or improper, or as in any [400]*400way failing to conform with the drawings and specifications.” Article 5 provides that if the contractors shall fail in any respect to prosecute the work with diligence or in the performance of any part of the agreement, and being so certified by the architect, the owners may, after five days’ written notice, provide labor and materials and deduct the costs thereof from any money due the contractors, and if the architect shall certify that such failure is sufficient ground for such action, the owners may terminate the employment of the contractors and complete the contract at their expense. The certificate of the architect as to the expense incurred by the owners is conclusive upon the parties. The specifications require the contractors to “ lay up all foundation walls and piers to grade line with best large mountain quarry stone of sufficient size beds and builds to make a first class piece of masonry in all respects,” and “ no less than fifteen per cent of entire stones to be headers, passing entirely through the walls.” In the specifications it is provided that “ if any errors are found on the plans, thejr must be referred to the architect for correction before proceeding with the work.” A few days after the contract was signed by the parties, the contractors began work. The old building on the lot was removed, excavations made, and the foundation walls were built. The work proceeded until the contractors discovered an error of six feet in the walls on the foundation plans of the building. On May 25,1896, within a few days after the mistake had been discovered, the contractors notified the architect in writing of the error, and requested him to correct it before they proceeded with the work. On the following day a notice was sent the school board that an error liad been discovered and that the architect had been requested to correct it. The contractors also notified the school board in writing about June 1, 1896, that by a mistake of the architect, an error had been discovered in the walls of the building; that by reason thereof their work on the building had been delayed over a week, and that they would hold the defendant responsible for the loss and expense occasioned by the delay. Under objection the court admitted a paper offered by the plaintiffs, diited May 12,1896, signed by the contractors and witnessed by Thomas L. Evans, in which the contractors acknowledge that certain broken range stone work was omitted by them, and in lieu thereof agreed to cement [401]*401the wall or, on failure to do so to the satisfaction of the architect, that $150 should be deducted from money due them, and such change in the wall should not affect the contract. A bout June 11, 1896, the contractors notified the school board that it had committed a vital breach of the contract, and that such conduct on the part of the defendant was taken by the contractors as a rescission of the agreement, and that an action would be brought for a breach thereof. This notice also acknowledged the receipt of defendant’s notice to remove portions of the wall, denied that the contractors had not erected the walls according to the plans and specifications, also denied that the removal of the wall was an “ alteration ” as provided for in the contract, and set forth wherein the plans and specifications were alleged to be defective.

The architect notified the contractors in writing on May 17, 1896, to remove all the stone not up to the standard, and to carry out broken range work on the rear of the building above ground within twenty-four hours. On the following day he wrote the contractors a complaining letter in which, while admitting he gave them permission to use surface stone instead of quarried stone, he says he is compelled to resort to extreme measures to prevent the use of inferior stone in the foundation walls and if such conduct was persisted in, he would refuse to grant them a certificate. By a written notice of June 8,1896, the architect called the contractors’ attention to the fact that fifteen per cent of the stone and the broken range work did not pass entirely through the walls as called for in the specifications, and notified them to remove such parts of the walls as did not conform to the specifications and to rebuild the same at once. By a notice from the architect of the same date, the contractors were required to begin the work of the removal and restoration of the walls within twenty-four hours, and their attention was directed to article 4 of the contract. To this notice was attached a blue print showing the portions of the foundation walls to be removed. On or about June 16, 1896, the school board, in a written notice, reciting the refusal of the contractors to comply with the notices given them by-the architect and their abandonment of the work, notified the contractors to begin the work referred to in said notice within ten days as provided in article 5 of the contract.

[402]*402The contractors abandoned the contract, pursuant to their notice to the school board of June 11, 1896, and on June 22 brought this action. In the statement, they aver that' their claim is for -15,000 for work done and materials furnished in pursuance of, and in accordance with, the contract; that the architect was incompetent and furnished plans and specifications improper and impossible for the performance of the work; that the defendant refused to furnish proper plans and specifications, and thereby committed a breach of the contract and prevented plaintiffs from performing the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wagner v. Graziano Construction Co.
136 A.2d 82 (Supreme Court of Pennsylvania, 1957)
Turner Concrete Steel Co. v. Chester Construction & Contracting Co.
114 A. 780 (Supreme Court of Pennsylvania, 1921)
Snedaker v. Torpey
41 Pa. Super. 312 (Superior Court of Pennsylvania, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
46 A. 91, 195 Pa. 396, 1900 Pa. LEXIS 655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gibbs-v-school-district-of-girardville-pa-1900.