Sweet v. . Morrison

22 N.E. 376, 116 N.Y. 19, 26 N.Y. St. Rep. 445, 71 Sickels 19, 1889 N.Y. LEXIS 1306
New York Court of Appeals·Decided October 8, 1889·Published·Cited by 76 cases

Opinion

Vann, J.

The person selected by the parties to make the estimate was in the employ of neither, yet, as chief engineer of the railroad company, he sustained such a relation to both *27 as to make it the interest of each that his estimate as to the materials furnished and work done by the plaintiffs should be-as large as possible, for it determined the amount of the-plaintiffs’ compensation as sub-contractors and of the defendant’s profits thereon as contractors. This case, therefore, is unlike those, so frequently arising, in which the certificate or estimate is required from an architect or engineer in the employment of one of the parties. In that class of cases the danger that the person acting as an arbitrator might favor his employers is obvious. While neither natural nor legal disabilities hinder a person from being an arbitrator, provided the fact is known to the parties at the time of the submission, still, as he is the agent of both parties alike, and impartiality is the fundamental requisite, the corn'ts closely scrutinize the action of an arbitrator whose relation to one of ' the parties was-such as to naturally influence the judgment even of an honest man. (Morse on Arb. and Award, 99; Bussell on Arb. 105.)-

In this case, however, there was no reason why the person selected should not be wholly disinterested and impartial. The-parties stood upon an equal footing, their contract was without legal objection, and the arbitration clause is as binding and should be enforced the same as any other provision. In one-sense, as was said in a case somewhat analogous, the submission to the determination of the engineer is more obligatory than any ordinary submission to arbitration, inasmuch as, being upon consideration, it is not revocable, and the obligation upon the defendants to pay did not, by the terms of the contract, arise until the estimate was made by the engineer. (Herrick v. Vermont C. R. Co., 27 Vt. 673, 679.) A valid award or estimate operates as a final and conclusive judgment, and however disappointing it may be, the parties must abide by it. (Id.; Perkins v. Giles, 50 N. Y. 228; Fudickar v. Mut. Life Ins. Co., 62 id. 392; Kidwell v. B. & O. R. R. Co., 11 Gratt. 676; O’Reilly v. Kerns, 52 Penn. St. 214; Vanderwesker v. Vermont Central R. R. Co., 27 Vt. 130; Ranger v. Great Western Railway Co., 5 H. of L. Cas. 71; 2 Wood’s Railway Law. 995 ; 1 Bedfield’s Law of Railways, 438.)

*28 The estimate made by the chief engineer should not, therefore, be set aside or disregarded unless some good reason is shown for such action. The trial court, without deciding that there was any error in the estimate, adjudged, by its interlocutory •decree, that, if upon the reference ordered, any error should •appear in the estimate, it should be corrected, and that the party in whose favor a balance then appeared should recover the same from the other. The only reason appearing in the findings or suggested by the evidence for thus disturbing that which the parties had expressly stipulated should be final, is, that the chief engineer did not personally measure the work, and that when the final estimate was about to be signed he refused to allow the plaintiffs to call a witness to contradict the statements already made to him by the subordinate engineers. This involves an inquiry into the nature of the power intrusted to the chief engineer. Was he an arbitrator, as that term is understood at common law, or was it his duty in estimating quantities to simply make a summary computation, as held by the learned General Term ? The answer to this question must be found in the contract, which is both the source and limit of the power under consideration. The contract, however, is to be construed in the light of the surrounding circumstances, and in connection with the agreement with the railroad company, and the actual intention of the parties thus ascertained. The power in question was confided to a man, who, as engineer in •chief,was building a railroad extending from the Missouri river to the Pacific ocean. The single division of the road to which the contracts related was more than two hundred miles long, and it was to be completed between the 29th of September, 1871, •and the 1st of July, 1872. Could it have been within the contemplation of the .parties that the head of so great an enterprise should make the measurements himself, or even personally superintend them when made by others ? The plaintiff’s contract provided that the “ square timber and plank in structures and flattened timber in structure, as well as for all pile and trestle, and all other timber structures required on the road-bed of the Dakota division, “ should be paid for at so *29 much per thousand feet, board measure; ” piling at a certain price “ per lineal foot of piles driven ; ” and “ all iron used in above work, at ten cents per pound.” The bridges were to be paid for at.so much per lineal foot, with an increase of price as the spans increased in length.

Free access — add to your briefcase to read the full text and ask questions with AI

Sweet v. . Morrison, 22 N.E. 376, 116 N.Y. 19, 26 N.Y. St. Rep. 445, 71 Sickels 19, 1889 N.Y. LEXIS 1306 (N.Y. 1889).

22 N.E. 376 (Sweet v. . Morrison) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

BOARD OF WATER & SEWER COM'RS v. Bill Harbert Const. Co.
870 So. 2d 699 (Supreme Court of Alabama, 2003)
Ratchford v. Proprietors' Insurance
546 N.E.2d 1299 (Ohio Supreme Court, 1989)
John W. Johnson, Inc. v. Basic Construction Co.
429 F.2d 764 (D.C. Circuit, 1970)
Gold Plastering Co. v. 200 East End Avenue Corp.
282 A.D. 1073 (Appellate Division of the Supreme Court of New York, 1953)
Frank Nordone Contracting Co. v. City of New York
269 A.D. 1035 (Appellate Division of the Supreme Court of New York, 1945)
City of San Antonio v. McKenzie Const. Co.
138 S.W.2d 568 (Court of Appeals of Texas, 1940)
Gioia v. Gioia
171 Misc. 683 (New York Supreme Court, 1939)
City of New York v. National Dredging Co.
254 A.D. 530 (Appellate Division of the Supreme Court of New York, 1938)
Moran Bros. Contracting Co. v. City of New York
158 Misc. 677 (New York Supreme Court, 1936)
Dowd v. State
239 A.D. 141 (Appellate Division of the Supreme Court of New York, 1933)
Barash v. Board of Education
226 A.D. 249 (Appellate Division of the Supreme Court of New York, 1929)
Mayer v. East Side Logging Co.
280 P. 343 (Oregon Supreme Court, 1929)
Wilson v. County of Buchanan
298 S.W. 842 (Supreme Court of Missouri, 1927)
Matter of Casualty Co. of Am. (Rubin Claim)
155 N.E. 735 (New York Court of Appeals, 1927)
Duffy Bros. v. Bing & Bing, Inc.
217 A.D. 10 (Appellate Division of the Supreme Court of New York, 1926)
Marine Ins. v. McLanahan
5 F.2d 773 (Fourth Circuit, 1925)
Stefano Berizzi Co. v. Krausz
146 N.E. 436 (New York Court of Appeals, 1925)