Mayer v. East Side Logging Co.

280 P. 343, 278 P. 957, 130 Or. 341, 1929 Ore. LEXIS 202
CourtOregon Supreme Court
DecidedMarch 21, 1929
StatusPublished
Cited by10 cases

This text of 280 P. 343 (Mayer v. East Side Logging Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayer v. East Side Logging Co., 280 P. 343, 278 P. 957, 130 Or. 341, 1929 Ore. LEXIS 202 (Or. 1929).

Opinions

BOSSMAN, J.

This is a suit in which the plaintiffs pray for a decree declaring invalid a certificate issued by the chief engineer of the defendant which determined the several quantities of materials excavated by them under a contract with the defendant, and also pray the court to adjudicate the amount due them for their work. The complaint alleges a contract wherein the plaintiffs undertook to construct the right of way for a logging railroad. All materials removed were to be classified by the chief engineer of the defendant as earth, medium or solid rock, and were to be paid for respectively as follows: Forty cents, sixty cents and $1.10 per cubic yard. The complaint alleges that the plaintiffs excavated 15,234 yards of earth, 32,983 yards of medium, and 27,618 yards of solid rock, but that the engineer allowed them 60,039 yards of earth, 15,447 yards of medium, *343 and 349 yards of solid rock. Their charges of misclassification are accompanied with averments of fraud and of gross mistake. The answer denies all allegations which were intended to impeach the , engineer’s certificate, and, avers that his classifications were correct. The decree of the Circuit Court allowed the plaintiffs a judgment for $18,094.18 above all sums previously paid them; this award was less than the plaintiffs sought. The defendant appealed and thereupon plaintiffs prosecuted a cross-appeal. The testimony is transcribed upon 1,100 pages, in addition to which there are numerous exhibits, including a large quantity of photographs of the various cuts introduced to assist the court in understanding the type of material covered by the contract. An extended statement of our review of this vast quantity of evidence is manifestly impossible if this decision is to be confined within reasonable bounds; the following will therefore have to suffice. The excavation was carried on near Keasey in Columbia County, in the coast range of mountains. It was preceded by the execution of a contract, which in addition to fixing the prices to be paid for the materials excavated, defined “solid rock,” “medium” and “earth” as follows :

“Solid rock shall comprise rock in solid beds or masses in its original position and boulders or detached rock measuring one cubic yard or over, and shall include quartz, limestones, sandstones which do not disintegrate upon exposure, conglomerate when thoroughly compacted and cemented, slate, granite, trap, basalt and similar rocks.
“Medium shall comprise detached masses of rock or stone of not less than one cubic foot or more than one cubic yard, cemented gravel, hard-pan, shale, soapstone or similar material which can be removed *344 by pick and bar without blasting, although blasting and steam shovel may be used in order to facilitate the work.
‘ ‘ Earth shall comprise loam, mold, gravel, sand and all’Other materials of whatever nature which do not come under the classification of ‘Solid Bock’ or ‘Medium.’ ”

The contract conferred broad powers upon the chief engineer of the defendant; it provided that all controversies which might arise between the contractors and the company under the contract should be subject to his decision “and his decision shall be final and conclusive upon both parties.” It provided that the said official- should on the first day of each month, make an estimate of the value of the work up to that time, and that upon the completion of the work he should issue his final certificate, whereupon the entire balance found due to the contractor should be payable within fifteen days’ time. The final certificate determined that the plaintiffs had moved 57,749.53 yards of earth, 14,775.36 yards of medium and 931.77 yards of solid rock. There is no contention that the gross quantity moved was miscalculated; upon the other hand all the witnesses, both for the plaintiffs and for the defendant, accepted that quantity as correctly estimated. Likewise the evidence seems to indicate that the engineer’s general plans were skillfully prepared. He was almost constantly in attendance upon the work, and when absent temporarily, substituted in his stead an assistant with whose ability the plaintiffs found no fault. The work done covered thirty-three cuts of varying sizes and depths. Apparently it was difficult to determine accurately the quantities of the three materials, due to the fact that in practically all of the cuts there was no well-defined line of demarcation between, earth *345 and medium, and between the latter and the alleged rock formations. In all except one or two cuts the surface material gradually blended itself into medium, and the latter, as the lower levels were reached, eventually became sufficiently hard so that some of the witnesses contended it was rock in some of the cuts. Adding further to the difficulties of classification was the fact that materials were encountered which were not specifically named in the above definitions.

The materials found in the cuts we shall now undertake to describe briefly. There was a top soil of a depth varying from two to several feet which gradually merged into a more difficult substance. Most of the witnesses were uncertain as to the geographical name of the latter, but a geologist, who testified on behalf of the plaintiffs, referred to much of it as a soft sandstone formation, or shale. In some of the cuts he found a combination of the two, which he described as “sandy shale,” or “shaley sandstone.” It is agreed that this material as it was encountered directly under the top soil was but slightly indurated. Apparently the moisture seeping down from above, carrying with it chemicals yielded by decomposing vegetation, had in the course of time softened this material to the point where it could be quite readily removed. After the excavation had proceeded deeper, this substance in the major cuts became harder until a point was reached where some of the plaintiffs’ witnesses felt justified in calling it rock. They were not certain whether it was a sandstone in process of formation or in process of decomposition. They readily testified that even the hardest portions of it were not sufficiently indurated to return fire when struck sharply with a pick. These witnesses were reluctant to apply to this material the *346 word “rock” geographically, hut felt that if an engineer’s powder test were applicable these sandstone formations should be considered equivalent to solid rock. This substance soon disintegrated upon removal and exposure to the weather. In fact most of the witnesses could not recall seeing any large pieces in the fills when they made their examinations and calculations; others testified that it soon disintegrated into a pile of sand.

In four of the cuts additional substances were encountered. In the one, plaintiffs’ geologist described the material as blue shale, while Mr. Bollons, the engineer for the defendant, described it as “a compressed sea mud,” and added that it was “full of clam shells and fossils of different kinds”; another witness believed it was soapstone. Whatever may have been its nature the evidence justifies the conclusion that it presented serious difficulties towards removal. In the second of these four cuts there was a substance which the aforementioned geologist called a “softened tuff” and a layman described as “clay and sand” somewhat resembling gumbo; this substance was also difficult of removal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lincoln Construction, Inc. v. Thomas J. Parker & Associates, Inc.
602 P.2d 676 (Court of Appeals of Oregon, 1979)
Krieg v. UNION PACIFIC LAND RESOURCES CORPORATION
525 P.2d 48 (Oregon Supreme Court, 1974)
ANTRIM LUMBER COMPANY v. Bowline
1969 OK 161 (Supreme Court of Oklahoma, 1969)
Clack v. State of California Ex Rel. Dept. Pub. Wks.
275 Cal. App. 2d 743 (California Court of Appeal, 1969)
Clack v. ST. OF CALIFORNIA EX REL. DEPT. PUB. WKS
275 Cal. App. 2d 743 (California Court of Appeal, 1969)
State Highway Commission v. Heintz Construction Co.
423 P.2d 175 (Oregon Supreme Court, 1967)
Rueda v. Union Pacific Railroad Co.
175 P.2d 778 (Oregon Supreme Court, 1946)
J. H. Ferguson Co. v. Keene
200 A. 396 (Supreme Court of New Hampshire, 1938)
United Contracting Co. v. Duby
292 P. 309 (Oregon Supreme Court, 1930)
Mayer v. East Side Logging Co.
280 P. 343 (Oregon Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
280 P. 343, 278 P. 957, 130 Or. 341, 1929 Ore. LEXIS 202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayer-v-east-side-logging-co-or-1929.