State Highway Commission v. Heintz Construction Co.

423 P.2d 175, 245 Or. 530, 1967 Ore. LEXIS 638
CourtOregon Supreme Court
DecidedFebruary 1, 1967
StatusPublished
Cited by13 cases

This text of 423 P.2d 175 (State Highway Commission v. Heintz Construction Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Commission v. Heintz Construction Co., 423 P.2d 175, 245 Or. 530, 1967 Ore. LEXIS 638 (Or. 1967).

Opinion

DENECKE, J.

The defendants were joint venturers who performed the grading contract for the plaintiff Highway Commission in the construction of nine miles of Interstate 5. The Commission brought this action to recover an alleged overpayment of $75,000 made to *532 the defendants. The joint venturers counterclaimed for the $72,000 retainage held by the Commission. The jury returned a verdict in favor of the Commission for the entire amount sought. The trial court granted defendants’ motion for a new trial and plaintiff appeals.

The motion for a new trial stated many alleged grounds. The order granting the new trial and the parties’ briefs are limited to the issues of whether the instructions given were correct, whether the jury was adequately instructed, and whether the forms of verdict submitted to the jury were correct.

As in most construction contract cases, the issues are technical, difficult for laymen to comprehend and ill-adapted for jury determination. The experienced trial judge commented: “This has been the most amazing lawsuit I have ever tried, factualwise and legal-wise.”

The contract was to construct the roadbed and did not include placing the road surface. Performance involved cutting through the hills and filling in the valleys, thus bringing the bed to a grade or elevation fixed by the Commission.

Prior to the putting out the job for bids, the Commission made a detailed study of the work to be done and prepared plans and specifications. These included the approximate quantities of materials to be excavated and handled. For example, general excavation, 1,688,000 cubic yards; toe trench excavation, 20,400 cubic yards. The primary portion of the bids was an offer to perform the work at a price per unit of the work estimated to be done. For example, the toe trench excavation was bid at 50 cents per cubic yard; based upon the estimated amount of 20,400 cubic yards of such excavation to be required, the bid on this item *533 was $10,200. When the work is actually performed it must be determined how many cubic yards of toe trench excavation has been done and the contractor will be paid 50 cents per cubic yard of cubic yards for such work whether it is more or less than the quantity originally estimated.

The performance of construction work such as this takes a long period of time; therefore, contracts covering such work customarily provide, as does this contract, for monthly payments based upon an estimate of the amount of work performed during the past month. A small percentage of the amount estimated due is kept by the Commission as retainage, a form of surety. The joint venturers received 16 monthly payments. When the entire job was completed and computation of the total cost of the work was made by the Commission, it was of the opinion that the joint venturers had been overpaid by $147,000. The Commission demanded the return of $75,000 and stated its intention to permanently retain the retainage in the amount of $72,000.

The principal cause of the dispute was excavation below subgrade and then the backfilling of such space. The joint venturers’ job was to prepare the roadbed to subgrade. (Another contract would be let to lay a base course on the subgrade and surface the road at finish grade.) The plans called for the contractor to excavate 18 inches below subgrade and replace such excavated area with selected subgrade material. Under the contract the joint venturers were to be paid at the general excavation unit price for this below subgrade work plus 10 cents per cubic yard for selected sub-grade material. The Commission’s resident engineer testified:

“We used the select subgrade material to re *534 inforce the road. In other words, when the native material is not suitable or we do not consider that it has sufficient bearing capacities to support the gravel, the pavement, and the traffic that will be on the road, then we will excavate out these inferior materials and replace them with the selected subgrade material.”

The specifications provided that these selected subgrade materials would be of granular nature. The materials could come from excavation made in constructing the road bed or from “borrow areas.”

All agree that when the job was initially staked out, before any work began, the stakes were placed and marked to indicate that the contractor should excavate to 18 inches below subgrade, i.e., in accordance with the original plans.

The resident engineer testified that after the work commenced, he determined by visual observation that in the seven rock cuts and in one other area the native material, rock, had suitable bearing capacity to hold the finish course and the subsequent traffic. Therefore, he testified he verbally instructed the contractor not to excavate below subgrade in those areas and not to place selected subgrade materials. Commission witnesses testified that these areas were restaked to indicate that the contractor should only excavate to subgrade, and not 18 inches lower. Contrary to the provisions of the contract, this alleged change in the work to be performed was not by written order. The alleged writing on the stakes the Commission claims were reset does not constitute that permanent record that the contract contemplated when it required changes to be in writing. Courtney v. Provincial Exhibition Commission, 41 Nova Scotia 71 (1906).

*535 The defendants’ witnesses testified that the areas had not been restaked and no instructions had been received to grade only to subgrade and not 18 inches lower. Defendants’ foreman testified he asked the Commission’s engineer if he had to excavate certain rock 18 inches below subgrade. He stated that the engineer said it all had to be excavated, otherwise with some subgrade solid and others filled it would settle unevenly and result in bumps in the pavement. The defendants’ witnesses testified that the contractor did excavate to 18 inches below subgrade and placed selected subgrade materials in these areas.

After the contractor started performance and monthly estimates and payments were made, the resident engineer approved payments for general excavation 18 inches below subgrade and for the placing of selected subgrade materials in those areas in which he testified he had instructed the contractor not to excavate below subgrade. His explanation was that his personnel made their computations of what the contractor had performed on the basis of the computations from the original plans which required excavating to 18 inches below subgrade and the placing of selected subgrade materials. He stated: “* * * It was an error on my part that I did not eliminate these overexcavations, if you will, or this 18 inches, from those areas early in the project. The simple truth of the matter is, I completely forgot about the stuff.”

Eventually, the resident engineer realized the contractor had been paid for excavation and material placement that the engineer had testified he ordered the contractor not to do and that it did not do. He had an assistant compute the amount of excavation and *536

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Clay
29 P.3d 1101 (Oregon Supreme Court, 2001)
Crown Northwest Equipment, Inc. v. Donald M. Drake Co.
620 P.2d 946 (Court of Appeals of Oregon, 1980)
Lincoln Construction, Inc. v. Thomas J. Parker & Associates, Inc.
602 P.2d 676 (Court of Appeals of Oregon, 1979)
Nyman v. City of Eugene
593 P.2d 515 (Oregon Supreme Court, 1979)
Krieg v. UNION PACIFIC LAND RESOURCES CORPORATION
525 P.2d 48 (Oregon Supreme Court, 1974)
McHorse v. Portland General Electric Company
521 P.2d 315 (Oregon Supreme Court, 1974)
State v. Devore
479 P.2d 1013 (Court of Appeals of Oregon, 1971)
State v. Fogle
459 P.2d 873 (Oregon Supreme Court, 1969)
A. H. Barbour & Son, Inc. v. State Highway Commission
433 P.2d 817 (Oregon Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
423 P.2d 175, 245 Or. 530, 1967 Ore. LEXIS 638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-commission-v-heintz-construction-co-or-1967.