Crown Northwest Equipment, Inc. v. Donald M. Drake Co.

620 P.2d 946, 49 Or. App. 679, 1980 Ore. App. LEXIS 3875
CourtCourt of Appeals of Oregon
DecidedDecember 8, 1980
DocketA7803-03653, CA 16052
StatusPublished
Cited by4 cases

This text of 620 P.2d 946 (Crown Northwest Equipment, Inc. v. Donald M. Drake Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crown Northwest Equipment, Inc. v. Donald M. Drake Co., 620 P.2d 946, 49 Or. App. 679, 1980 Ore. App. LEXIS 3875 (Or. Ct. App. 1980).

Opinion

*681 GILLETTE, P. J.

This is an action at law in which plaintiff sought to recover damages from the defendant for breach of contract. On April 1, 1976, the plaintiff, as a subcontractor, entered into two written subcontracts with the defendant, who was the general contractor for the construction of a bus garage facility. The facility, known as the "Powell Satellite Operating Garage,” was to be built for the Tri-County Metropolitan Transportation District (Tri-Met). Plaintiff agreed to install at the garage two bus washing systems, at a cost of $113,400, and a vacuum cleaning system, at a cost of $26,500. On June 30, 1976, the defendant cancelled each of the subcontracts prior to any performance by plaintiff. Plaintiff then brought this action for breach of contract. The trial court found for the plaintiff with respect to the bus-washing subcontract and for the defendant with respect to the vacuum cleaning subcontract. The defendant appeals from that portion of the judgment for plaintiff and plaintiff cross-appeals. We affirm.

This case turns on the application of the specifications issued by Tri-Met for the construction of the Powell garage. These specifications were lengthy and contained a detailed description of the requirements for each aspect of the garage. The subcontracts between plaintiff and defendant specifically incorporated the Tri-Met specifications, insofar as those specifications were relevant.

The Tri-Met specifications concerning the bus washing system provided, in pertinent part:

"BW-1 Bus Washing 9 water Reclamation System.
"1. General: Furnish and install two 'Drive-Thru Bus Wash Systems’ to automatically clean roofs, sides, front and rear of standard transit buses driven through the system.
"Wash system to be Hanna Industries Model 5100 P-H Brush Washer Package with complete water reclamation system.” (Section 15490, Paragraph 2.02 B)

The Tri-Met specifications concerning the vacuum cleaning system provided, in pertinent part

"Vacuum Cleaning System: Manufacturer: Hanna Industries, 20 HP Heavy Duty Vacuum System, others subject to prior approval.” (Section 11051, Paragraph 2.01)

*682 The specifications also contained the following general provision:

"Specified Materials: The use of brand names in specifying materials is for purposes of description and fixing quality. Unless otherwise noted, articles equal in quality and suitability will not be discriminated against. See Section 01800, 1.09 for approvals of substitutions.”

This provision appears to be in response to ORS 279.017(1), which prohibits specifications for public contracts from requiring a specific product by brand name or mark, or from requiring the product of a particular manufacturer or seller. 1

Section 01800, paragraph 1.09, of the Tri-Met specifications governs the substitution of materials:

"A. General: All requests for substitution of materials in lieu of those specified or shown shall be submitted in writing and be received in the office of the Engineer not less than 7 days before date of submission of bid as established by the Contract. All approvals granted are subject to complete compliance with the Contract Documents. Requests shall be accompanied by samples, catalog cuts and complete technical data pertaining to the request and any other data the Engineer may require. Incomplete data will be subject to rejection. No verbal approvals will be given and all approvals will be issued in writing before such date of submission of bid. The following definitions of phrases stated after listed items (materials or products) in the Specifications determine the extent to which substitutions may be proposed.
"B. ’OR APPROVED SUBSTITUTION’: These items require specific approvals outlined above.
"C. ’OR EQUAL’ OR ’SIMILAR TO’: These items do not require prior approval as they are considered items of standard manufacture which perform equal function and have equal quality to those specified. Where requested at the start of the job, the Subcontractor or material supplier shall submit for approval items which he considers equal *683 to those specified. The Engineer reserves the right to reject any items which in his judgment are not equal to those specified.
"D. Substitution will not be approved for any item not covered by an indication of an allowable substitution listed above.”

The basic facts in this case are undisputed. At all times it was clear to both parties that plaintiff intended to install both a bus washing system and a vacuum cleaning system different from those specified. On April 1, 1976, when plaintiff and defendant entered into the subcontracts, the time for "prior approval” under paragraph 1.09(A) was long past: The deadline for prior approval of substitutions was February 18, 1976. At the time the subcontracts were signed, both the plaintiff and the defendant knew that the time limit for prior approval had passed; the defendant knew further that the plaintiff had not sought and did not have prior approval for its equipment. Both parties thought that the plaintiff’s systems could and would be approved under the "or equal” provisions of paragraph 1.09(C) of the specifications. Prior approval was not needed under that section; approval could be requested at any time prior to the start of the job. Plaintiff assured the defendant that its equipment was equal in function and quality to the Hanna models specified. On that basis, the parties entered into the subcontracts.

Sometime in early April, 1976, the defendant submitted shop drawings on plaintiff’s systems to Tri-Met’s architects. These shop drawings were routinely required for all aspects of the general contract. The defendant did not indicate to Tri-Met that it was seeking, and in fact it was not seeking, "or equal” substitution for these systems.

On April 14, 1976, Tri-Met’s architect, Thomas Whittaker, wrote to the defendant referring to section 01800, paragraph 1.09(A) of the specifications and saying that plaintiff’s systems had to be rejected because plaintiff had not requested approval prior to bid. Whittaker indicated that, because prior approval had not been sought, TriMet would have to adhere to the Hanna Systems specified. On May 26, 1976, defendant sent plaintiff a copy of Whit-taker’s letter. On June 30, 1976, defendant wrote to plaintiff cancelling the subcontracts because of Tri-Met’s rejection based on lack of prior approval.

*684 The parties agree that the central issue in this case is whether paragraph 1.09(A), the "prior approval” section, or paragraph 1.09(C), the "or equal” section, applies to substitutions for the bus washer and vacuum cleaning systems.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
620 P.2d 946, 49 Or. App. 679, 1980 Ore. App. LEXIS 3875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crown-northwest-equipment-inc-v-donald-m-drake-co-orctapp-1980.