A. H. Barbour & Son, Inc. v. State Highway Commission

433 P.2d 817, 248 Or. 247, 1967 Ore. LEXIS 406
CourtOregon Supreme Court
DecidedNovember 22, 1967
StatusPublished
Cited by10 cases

This text of 433 P.2d 817 (A. H. Barbour & Son, Inc. v. State Highway Commission) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. H. Barbour & Son, Inc. v. State Highway Commission, 433 P.2d 817, 248 Or. 247, 1967 Ore. LEXIS 406 (Or. 1967).

Opinion

LUSK, J.

This is an action by a contractor to recover additional compensation from the State of Oregon acting by and through its State Highway Commission for work done under a contract for the maintenance cleaning and painting of all structural steel in the three steel spans below the roadway slab of the Yaquina Bay Bridge at Newport, Oregon.

In a trial before the court without a jury the court entered findings of fact and conclusions of law and a judgment in favor of the plaintiff in the sum of $37,468.96. Defendant has appealed from the judgment so far as it exceeds the sum of $2,968.96.

The contract contained this provision:

“All metal surfaces shall be cleaned and conditioned by sand blasting. The cleaning shall be done in accordance with ‘Steel-Structures Painting Council Surface Preparation Specification No. 6, Commercial Sand Blasting.’ The contractor need not remove all paint but shall remove all rust, mill scale, dead or loose paint, no matter how small the areas, and any other matter that might be detrimental to the new paint coat. The cleaned areas need not be brought to a uniform color provided detrimental material is removed. The maximum size of the sand shall be not larger than that passing a 16-mesh screen, U. S. sieve series.”

*250 The document referred to in the provision quoted defines commercial blast cleaning as follows:

“Commercial Blast Cleaning is a method of preparing metal surfaces for painting by removing mill scale, rust, rust-scale, paint, or f oreign matter by the use of abrasives propelled through nozzles or by centrifugal wheels, to the degree hereafter specified.”

Plaintiff commenced work under the contract on June 9, 1959, and shortly thereafter discovered incrustations of rust so heavy that they could not be practicably removed by sandblasting. As a result the defendant, through engineers of the State Highway Department, issued two orders (referred to as change orders) “for extra work to be performed on force account basis,” i.e., cost plus a percentage. Order number one estimated the cost of the extra work for span 1 as $3,006, and order number two estimated the cost of that work for spans 2 and 3 at $6,000. The orders contained the following description of the work to be done:

“Compensate the contractor for extra costs involved in chipping and removing heavy rust scale inside steel members, vertical posts, box arch rings and other members.”

Each order contained the following explanation of the reason for classing the work as “extra work”:

“Heavy rust scale built up inside of steel members must be removed by chipping with air hammers and is not considered as part of normal sandblasting required by the contract. Areas to be sandblasted after chipping as part of contract requirement.”

Plaintiff proceeded with the job and completed it on October 22, 1960. Payments for the chipping pur *251 suant to change order number two instead of the estimated $6,000, amounted to $43,060.50.

On November 2, 1962, the plaintiff asserted the claim which is the basis of this action. As alleged in the amended complaint, on which the case was tried, the defendant grossly underestimated the amount of handchipping required to be performed and directed and required the plaintiff to perform handchipping at a cost in excess of $39,000 instead of the estimated $6,000 in change order number two. These directions constituted an alteration in the details of construction. The six-fold increase in amount of handchipping necessarily resulted in plaintiff being required to perform sandblasting and spot painting where base metal was exposed, to an extent far beyond that contemplated by the contract and materially changed the character of the other work to be performed and the cost to complete the same. (It was further alleged that the time for performing the work was extended to an additional work season increasing plaintiff’s cost. The court found against the plaintiff on this issue and, as no appeal has been taken by the plaintiff, that question is not in the case.) The amended complaint then alleges that under a provision of the contract (hereinafter set out) an allowance should be made in favor of the contractor in such amounts as would be fair and equitable and that a fair and equitable amount is $54,472.11 together with interest at the rate of six per cent per annum from November 2, 1962.

The answer of the defendant, in addition to denials, alleged that all the extra work described in the amended complaint was performed by the plaintiff pursuant to the two change orders and was fully paid for. The answer further alleged that plaintiff had failed to comply with a provision of the contract (here *252 inafter set forth) requiring the contractor to give notice in writing to the defendant’s engineer of the intention to make claim for compensation for extra work.

In its reply to these affirmative matters the plaintiff realleged the parties’ miscalculation as to the amount of work involved in change order number two and alleged that this work was performed under a mutual mistake of fact; that it was not until the work directed by defendant under the change orders amounted to a material increase in the handchipping required over that contemplated by the parties at the time the change orders were issued that the character of the work to be performed and its cost were materially changed so as to make applicable the provision of the contract referred to in the amended complaint.

A pretrial stipulation (omitting two provisions as to questions not at issue on this appeal) stated the questions for decision as follows:

“C. With respect to plaintiff’s claim for additional sandblasting and spot painting in the amount of $46,437.76:
1) Did the handchipping which the State required because of the excessive rust require the contractor to perform more sandblasting and spot painting than that contemplated by the original contract?
2) If so, what was the reasonable value contractor should recover for the performance of this work?
3) (a) Was the contractor required to give written notice before beginning this work?
(b) If so, was such requirement waived under the facts of this case?”

The court found that the plaintiff made a reasonable examination of the bridge prior to bidding the *253

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WEGROUP PC v. State of Oregon
885 P.2d 709 (Court of Appeals of Oregon, 1994)
Gilbert Pacific Corp. v. State ex rel. Department of Transportation
822 P.2d 729 (Court of Appeals of Oregon, 1991)
GILBERT PACIFIC v. Dept. of Transp.
822 P.2d 729 (Court of Appeals of Oregon, 1991)
Washer v. Clatsop Care & Rehabilitation District
741 P.2d 493 (Oregon Supreme Court, 1987)
Sunset Coatings Co. v. Department of Transportation
660 P.2d 164 (Court of Appeals of Oregon, 1983)
General Construction Co. v. Oregon State Fish Commission
554 P.2d 185 (Court of Appeals of Oregon, 1977)
McHorse v. Portland General Electric Company
521 P.2d 315 (Oregon Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
433 P.2d 817, 248 Or. 247, 1967 Ore. LEXIS 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-h-barbour-son-inc-v-state-highway-commission-or-1967.