Savage v. Peter Kiewit Sons' Co.

437 P.2d 487, 432 P.2d 519, 249 Or. 147, 1967 Ore. LEXIS 658
CourtOregon Supreme Court
DecidedOctober 13, 1967
StatusPublished
Cited by19 cases

This text of 437 P.2d 487 (Savage v. Peter Kiewit Sons' Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Savage v. Peter Kiewit Sons' Co., 437 P.2d 487, 432 P.2d 519, 249 Or. 147, 1967 Ore. LEXIS 658 (Or. 1967).

Opinion

GOODWIN, J.

The Oregon State Highway Commission appeals from a declaratory decree allowing compensation to a subcontractor for extraordinary expenses incurred in performing his contract. As this suit was tried below as a suit in equity, we have considered the record de novo pursuant to ORS 19.125 (3).

The defendant Kiewit was the prime contractor with the Highway Commission for the construction of the West Marquam Interchange on Interstate Five in Multnomah County. The plaintiff, Savage, subcontracted with Kiewit for the cleaning and painting of the structural steel used in the interchange.

The contract between the Highway Commission and Kiewit provided for all structural steel to be cleaned by sandblasting, either (1) in the steel supplier’s shop, (2) on the ground at the bridge site, or (3) in the air after erection. Savage elected to sandblast in the air, which witnesses agreed was the most economical method, and computed his bid accordingly. Savage had concluded after inspecting the site that, with certain precautions, the open-air method could be used without undue damage to nearby businesses.

After the steel was in place and the other optional methods were thus precluded, Savage began the sandblasting. He proceeded without difficulty until a complaint of damage from falling sand was made by Alaska Steel Co., a concern which operated machinery under the work area. Savage then commenced to take the precautions which, he testified, he had anticipated probably would be necessary. These consisted of pro *151 viding covers for Alaska Steel’s equipment, working on weekends, and working only when the winds were favorable. Despite Savage’s precautions, Alaska Steel continued to complain that sand particles were damaging its machinery, and on June 3, 1965, obtained a permanent injunction against further sandblasting above its land.

After the injunction was decreed, the Highway Commission asked Savage to conduct tests of cleaning methods other than sandblasting. During the tests, Savage received from the bridge engineer and from the assistant state highway engineer conflicting advice as to his duties under his contract. Confused by these communications, Savage commenced a suit for declaratory relief on July 1, 1965. Between the filing of this suit and the hearing thereof, the Commission again advocated some variation of the open-air sandblasting method. Savage and Kiewit then devised an enclosed structure, a sort of movable cocoon, which could be rolled along the spans and which was designed to contain the sand particles.

After the hearing of the declaratory proceeding, the trial court concluded that Savage’s original obligation to perform his contract with Kiewit had been discharged by impossibility (Alaska Steel’s injunction). The court then treated the Commission’s urging that Savage proceed by the newly devised method as an alteration of the original contract, and ordered Savage to finish the sandblasting on a quantum meruit basis. The Commission had been urging Savage to proceed, and had helped to have the existing injunction modified to permit him to do so, but the Commission vigorously opposed the portion of the declaratory decree which ordered Savage’s compensation on a quantum meruit basis.

*152 The Commission’s appeal contends that Kiewit was hound to deliver for the contract price a finished product according to contract specifications, and that the injunction which prevented the completion of Savage’s subcontract as planned did not constitute a legal excuse for nonperformance nor create a right to extra compensation.

Savage contends that the injunction constituted a supervening event which made his performance impossible and thereby excused him from performance, citing 6 Corbin, Contracts § 1320, at 323 (1962). Supervening impossibility occurs “where, after the formation of a contract facts that a promisor had no reason to anticipate, and for the occurrence of which he is not in contributing fault, render performance of the contract impossible, the duty of the promisor is discharged, unless a contrary intention has been manifested * * Restatement of Contracts § 457 (1932). Included as one of the supervening events which in a proper case may excuse performance is prohibition by a court order. Restatement of Contracts § 458 (1932); Annotation, 84 ALR2d 12, 46 (1962).

Cases dealing with impossibility caused by court order frequently speak of situations where an injunction prevents all performance, but this is not really what happened to Savage. He was eventually able to complete his promised sandblasting, but to do so he had to spend more money than he had planned on spending to protect third persons. The alleged impossibility in this case arises out of increased expense in complying with court orders.

In applying the doctrine of impossibility, courts recognize that unexpected difficulty or expense may approach such an extreme that a practical impossibility exists. See, e.g., Natus Corporation v. *153 United States, 371 F2d 450 (Ct Cl 1967). To operate as a discharge, however, the hardship mast be so extreme as to be oatside any reasonable contemplation of the parties. Natus Corporation v. United States, sapra. And see Restatement of Contracts § 454 (1932); Transatlantic Financing Corporation v. United States, 363 F2d 312, 315 (DC Cir 1966).

Unexpected difficalties and expense, therefore, whether caased by injunction or by other causes, do not necessarily excuse performance of a contract. The qaestion is whether the unforeseen hazard was one that reasonably shoald have been guarded against. One purpose of a contract is to shift reasonably foreseeable business risks to the party promising the performance so that the promisee can devote his energies and capital to other matters. A mere showing of commercial nnprofitability, without more, will not excuse the performance of a contract. Learned v. Holbrook, 87 Or 576, 170 P 530,171 P 222 (1918).

Returning to the Restatement limitations upon the excuse of impossibility (Contracts § 457), we need not search for contributing faalt on the part of Savage. Whatever liabilities Savage may have incurred toward Alaska Steel, it is not necessary in this case to assign faalt as a basis thereof. We assume for the purpose of this case that Savage did his pre-injunction sandblasting with reasonable care bat that notwithstanding sach care his operations caased harm to a nearby landowner and had to be drastically modified in order to avoid sach harm.

The trial court found that “the situation which developed was beyond the contemplation and experience of all the parties to this case.” The important qaestion, however, is whether Savage shoald have anticipated the danger of serious harm to nearby *154 landowners. Perhaps Savage should not have been expected to anticipate that his work might be enjoined, since he had no previous experience with injunctions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Link v. State by & Through Dept. of Fish & Game
591 P.2d 214 (Montana Supreme Court, 1979)
Holmgren v. Utah-Idaho Sugar Co.
582 P.2d 856 (Utah Supreme Court, 1978)
General Construction Co. v. Oregon State Fish Commission
554 P.2d 185 (Court of Appeals of Oregon, 1977)
Diesel Service Unit Co. v. Bonbright
555 P.2d 452 (Oregon Supreme Court, 1976)
Borton v. Medicine Rock Land Company
549 P.2d 1122 (Oregon Supreme Court, 1976)
Rose City Transit Co. v. City of Portland
525 P.2d 1325 (Court of Appeals of Oregon, 1974)
Sachs v. Precision Products Co.
476 P.2d 199 (Oregon Supreme Court, 1970)
Schafer v. Sunset Packing Company
474 P.2d 529 (Oregon Supreme Court, 1970)
Savage v. Peter Kiewit Sons' Co.
461 P.2d 59 (Oregon Supreme Court, 1969)
Savage v. PETER KIEWIT SONS'CO.
437 P.2d 487 (Oregon Supreme Court, 1968)
A. H. Barbour & Son, Inc. v. State Highway Commission
433 P.2d 817 (Oregon Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
437 P.2d 487, 432 P.2d 519, 249 Or. 147, 1967 Ore. LEXIS 658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savage-v-peter-kiewit-sons-co-or-1967.