Sachs v. Precision Products Co.

476 P.2d 199, 257 Or. 273, 1970 Ore. LEXIS 276
CourtOregon Supreme Court
DecidedNovember 5, 1970
StatusPublished
Cited by13 cases

This text of 476 P.2d 199 (Sachs v. Precision Products Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sachs v. Precision Products Co., 476 P.2d 199, 257 Or. 273, 1970 Ore. LEXIS 276 (Or. 1970).

Opinion

TONGUE, J.

This is an action by a distributor against a manu *276 facturer for damages for breach of a franchise agreement, based upon allegations that the defendant “refused and neglected to deliver and perform said contract.” The defendant denies that it breached the contract and by cross-complaint has asked the court to hold that plaintiff terminated the contract, based upon allegations that he refused to accept further deliveries and abandoned all efforts to sell the products.

Defendant appeals from a judgment for plaintiff for $16,192.26, including $11,614.74 for lost profits on undelivered orders, $3,400.45 representing down payments made by plaintiff on such orders, and $1,177.17 for moneys expended by plaintiff in the promotion and sale of the product. The trial court also denied defendant’s cross-complaint.

In February 1966 the parties met and discussed the design, manufacture and sale of a small portable hoist. Eight months later no production model had yet been completed, but discussions and plans had progressed to the point that a contract was prepared and signed on October 18, 1966. By the terms of that contract plaintiff was given a five year exclusive franchise as a distributor for the sale of the “Atlas Hoist” in Oregon, Washington and California. Defendant was required to “supply any requirements of the distributor and make shipments promptly in accordance with the distributor’s orders.”

Plaintiff then opened an office and undertook a sales promotion program and arranged for distributors in Seattle and San Francisco. It was not until October however, that defendant developed and completed a production model that “worked reasonably satisfactorily.”

On October 4, 1967, plaintiff placed his first order *277 with defendant for 100 hoists. Twelve days later, on October 16, 1967, Mr. Frizzell, the Seattle distributor, placed a written order with plaintiff for 50 hoists. Al: though plaintiff testified that this was “in addition” to his previous order, there was no evidence that it was ever transmitted by plaintiff to defendant and it was marked “Cancelled. Due to unforeseen delay in production. 11/15/67.” By the end of December 1967 only 46 of the 100 units ordered by plaintiff had been delivered.

In January 1968 plaintiff was informed that “trouble” had been encountered in lowering the hoist with a heavy load, involving the “piling up” of cable on the “capstan,” with the possiblity of the cable “snapping,” so as to cause an accident. Plaintiff then reported this to defendant’s president, Mr. Wilcox, who verified the problem in tests of the hoist. Although plaintiff felt that the hoist was already a “good product,” he testified that he “figured it was good business to have it corrected.” Accordingly, the parties agreed that the units previously sold be picked up and returned for correction.

Mr. Wilcox then worked “about a month” designing a new “capstan.” In that process he proceeded, by trial and error, to re-design 10 or 12 different models with slightly different angles and radii, each of which then had to be sent out to be “case-hardened,” requiring three to four days. This experimental work was done personally by Mr. Wilcox and was not completed *278 until March 1968. During that period work on orders for the hoist was stopped, although defendant’s plant proceeded with other work for other customers.

Meanwhile, also in January 1968, plaintiff met with Mr. Wilcox to discuss the problem of delays in deliveries. He was then told by Mr. Wilcox that defendant did not have “enough money to operate.” Plaintiff then suggested that he pay 50% “in advance with the orders,” so as to “assist” defendant and “increase the speed” of production.

A new contract was then prepared, dated January 11, 1968. By its terms the new agreement “supercedes” [sic] the previous agreement of October 1966 and “constitutes the entire understanding of the parties.” It also provided that plaintiff was to have an exclusive franchise, without limitation of territory and for a period of ten years. He was, however, still required to purchase a minimum of 100 units each year, as under the previous contract. Also, the shipping requirements were changed so as to provide that upon receiving written orders defendant was to “immediately notify distributor of the date upon which the items ordered shall be shipped” and was to be “liable for general damages caused by delay in delivery or failure to manufacture due to its fault or negligence,” but not for causes “beyond its reasonable control.”

During the following six weeks plaintiff delivered two additional purchase orders to defendant. Thus, on January 30, 1968, he ordered 100 hoists with the notation under “Date Required — March 1/68.” On February 17, 1968, he ordered an additional 100 units with *279 “Date Required- — -April 1/68.” These orders were accompanied by payment of 50% down, in the total sum of $3,400.45.

During that period Mr. Frizzell, the Seattle distributor, on February 19,1968, submitted to plaintiff another order for 100 units, at a price “as agreed” in the sum of $49.75. Again, however, there is no evidence that this order was transmitted to defendant, much less that a 50% deposit was made upon it, and the order bears a notation by plaintiff, dated March 18, 1968, to the effect that it was returned unfilled for the reason that “we are still in the process of correcting the faulty capstan and we will not be able to make shipment on the date specified.”

Plaintiff testified that in May 1968, after receiving no notification of shipping dates for his last two orders and apparently after receiving further excuses and promises from defendant (although the correction of the design of the faulty capstan had been completed sometime in March), plaintiff asked defendant for the return of his down payment. Defendant testified that this demand was made in April 1968.

On May 9, 1968, defendant mailed an “acknowledgment of order” to plaintiff, stating that it expected to ship the order dated January 30, 1968, “on or about October 31, 1968” and the order dated February 17, 1968, “on or about December 20,1968.” At “some time after May 9, 1968,” plaintiff called defendant’s office and stated that he would not accept delivery of any more hoists and was turning the matter over to an attorney. He was told at that time by defendant’s employees that he had been “very patient” in waiting for the deliveries. Defendant also admitted that the reason for the delays in shipment was that the hoist *280 had originally not been properly designed, but contends that plaintiff was aware of the problems in correcting the design.

Plaintiff also testified that while defendant offered to return the down payment, it would do so only on condition that he agree to a termination of the contract. Plaintiff contends, however, that he still has the exclusive contract right to sell all hoists produced by defendant and that he is willing to buy the hoists from defendant “at any time.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sawyers v. FMA Leasing Co.
722 P.2d 773 (Utah Supreme Court, 1986)
UNITED STATES NAT. BANK OF OR. v. Caldwell
655 P.2d 180 (Court of Appeals of Oregon, 1982)
Penelko, Inc. v. John Price Associates, Inc.
642 P.2d 1229 (Utah Supreme Court, 1982)
Bixler v. First Nat. Bank of Oregon
619 P.2d 895 (Court of Appeals of Oregon, 1980)
Reeder v. Kay
577 P.2d 925 (Oregon Supreme Court, 1978)
Hankins v. City of Newport
549 P.2d 1297 (Court of Appeals of Oregon, 1976)
Verret v. Leagjeld
501 P.2d 780 (Oregon Supreme Court, 1972)
Pearson v. Schmitt
487 P.2d 84 (Oregon Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
476 P.2d 199, 257 Or. 273, 1970 Ore. LEXIS 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sachs-v-precision-products-co-or-1970.