Douglas Construction Corp. v. Mazama Timber Products, Inc.

471 P.2d 768, 256 Or. 107, 1970 Ore. LEXIS 295
CourtOregon Supreme Court
DecidedJuly 1, 1970
StatusPublished
Cited by24 cases

This text of 471 P.2d 768 (Douglas Construction Corp. v. Mazama Timber Products, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Douglas Construction Corp. v. Mazama Timber Products, Inc., 471 P.2d 768, 256 Or. 107, 1970 Ore. LEXIS 295 (Or. 1970).

Opinion

TONG-UE, J.

This is an action by a road construction contractor against a logging operator for damages for breach of an oral contract under which plaintiff was engaged by defendant to remove rock from two quarries and to load, haul, spread and compress the rock on a timber access road, at a specified rate per cubic yard of rock “in place.” As damages resulting from the improper termination of that contract, plaintiff seeks to recover profits which it claims that it would have made if permitted to complete performance of the contract.

Defendant appeals from a verdict and judgment of $6,000, contending that the court erred in overruling defendant’s motions for involuntary nonsuit and for a directed verdict. The single issue on appeal is whether plaintiff offered sufficient evidence to support any award for alleged loss of profits.

The only evidence offered by plaintiff on this issue was the testimony of its president, who had been engaged in such work for 31 years and who testified that at the time of the termination of the contract, after hauling 8,000 cubic yards of rock, at least 14,000 cubic yards would have been required to complete *109 the contract and that “we would have made a profit if we had done the job of approximately 60 cents per yard.”

No evidence was offered to show either the actual or estimated cost of completing the contract, either as a whole or for each of the various operations involved, such as for the preparation of the road bed by “pulling” the ditches, the drilling and “shooting” of rock at the quarries, the loading of rock into trucks, the hauling of rock to the road, and the spreading and “compaction” of the rock, as well as for such items as labor, maintenance and overhead, among other items of cost properly chargeable to the performance of such a contract.

In addition, no evidence was offered to show the amount of previous profits, if any, made by plaintiff on other operations, much less on other similar operations. On the contrary, it was admitted that plaintiff suffered a loss in placing the initial 8,000 cubic yards of gravel on the roads in question, for which plaintiff was paid in full, although some items of cost might otherwise have been “spread” over all or a portion of the remaining work to be done, but for the improper termination of the contract.

There was also uncontradicted evidence that the weather was extremely bad during the period in question, with both rain and snow, and that weather is related to “the expense involved * * * in the rocking of a roadway” in that “the more it rains the muddier it gets and it is that much harder to get through” and requires “a lot more time.”

Plaintiff contends that testimony of a man with 31 years of experience that the net profit would have been 60 cents per cubic yard was “the type of proof that the law requires — the difference between the con *110 tract price and the cost of doing the work”; that “the witness was never required to segregate the various items of expense” and that “it would have been a simple matter for the appellant, on cross-examination, to have arrived at any itemization which it may have required.”

As the party with the burden of proof, however, plaintiff could not properly complain that defendant, on cross-examination, did not develop facts relating to actual costs and other facts from which it might have been possible to determine whether plaintiff would have made a profit on this contract and, if so, the amount of such profit. Thus, the question presented by this case is whether the opinion of an experienced contractor that a profit of 60 cents per cubic yard of gravel would have been made on 14,000 cubic yards of gravel if plaintiff had been permitted to complete the contract, unsupported by evidence of actual costs or other supporting facts, is alone sufficient to support a verdict and judgment for alleged loss of profits, particularly in a case in which plaintiff concedes that “it would have been a simple matter” to provide such an “itemization” as “may have been required.”

Plaintiff also concedes that “proof in a case involving a claim for loss of profits must establish that profits were reasonably certain to accrue,” but contends that “certainty as to the amount is not fatal, but an uncertainty as to whether any benefit or gain would be derived bars a claim for damages founded on alleged profits,” citing Randles v. Nickum & Kelly Sand & Gravel Co., 169 Or 284, 287, 127 P2d 347 (1942). Similarly, plaintiff contends that “it is not a sufficient reason for disallowing damages claimed that they cannot be exactly calculated. It is sufficient if, from prox *111 imate estimate of witnesses, a satisfactory conclusion can be reached,” citing Buck v. Mueller, 221 Or 271, 283, 351 P2d 61 (1960). Other less recent eases are also cited by plaintiff in support of these contentions, but none is directly in point.

It is true that in Randles this court, at p 287, approved the proposition that the rule that damages which are uncertain or contingent cannot be recovered applies only in determining whether there would have been any gain or benefit from the performance of a contract and “does not embrace an uncertainty as to the value of the benefit or gain to be derived from the performance of the contract.” In that case a building contractor testified that he would have made a profit of $800 on each of several houses being built by him under separate contracts, as the “normal profit” for each house.

It was held by this court in that case, however, that such testimony was insufficient to support an award for loss of profits, stating, at pp 287-88, that an award of damages for an alleged loss of profits by a contractor cannot be sustained where it is based upon “mere estimate” as to the amount of the alleged profit, without “supporting data,” and with “no testimony that the plaintiff had ever made a profit under similar contracts,” and in a busines recognized to be “highly speculative in its nature.”

Thus, this court concluded (at p 288), quoting with approval from 15 Am Jur 574, Damages § 157 that:

“The proof must pass the realm of conjecture, speculation, or opinion not founded on facts, and must consist of actual facts from which a reasonably accurate conclusion regarding the cause and the amount of the loss can be logically and rationally drawn.”

*112 This is in accord with the rule as stated in the Restatement of Contracts § 331 (previously approved by this court in Stubblefield v. Montgomery Ward & Co., 163 Or 432, at 447-48, 96 P2d 774 (1940)), as follows:

“(1) Damages are recoverable for losses caused or for profits and other gains prevented by the breach only to the extent that the evidence affords a sufficient basis for estimating their amount in money with reasonable certainty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rennick v. Jackson & Coker
767 P.2d 478 (Court of Appeals of Oregon, 1989)
Custom Harvesting Oregon, Inc. v. Smith Truck & Tractor, Inc.
706 P.2d 186 (Court of Appeals of Oregon, 1985)
Laro Lumber Co., Inc. v. Patrick
630 P.2d 400 (Court of Appeals of Oregon, 1981)
Hardwick v. Dravo Equipment Co.
569 P.2d 588 (Oregon Supreme Court, 1977)
Wall v. SEC Co., Inc.
528 P.2d 1054 (Oregon Supreme Court, 1974)
Jenks v. Larimer
518 P.2d 1301 (Oregon Supreme Court, 1974)
Kwipco, Inc. v. General Trailer Co., Inc.
515 P.2d 1317 (Oregon Supreme Court, 1973)
Best Logging Co. v. Bevens
514 P.2d 555 (Oregon Supreme Court, 1973)
Melms v. Mitchell
512 P.2d 1336 (Oregon Supreme Court, 1973)
Meyer v. Harvey Aluminum
501 P.2d 795 (Oregon Supreme Court, 1972)
Verret v. Leagjeld
501 P.2d 780 (Oregon Supreme Court, 1972)
Davis v. Wilson
493 P.2d 31 (Oregon Supreme Court, 1972)
Brenneman v. Auto-Teria, Inc.
491 P.2d 992 (Oregon Supreme Court, 1971)
Fulton v. BF Goodrich Company
490 P.2d 178 (Oregon Supreme Court, 1971)
Pearson v. Schmitt
487 P.2d 84 (Oregon Supreme Court, 1971)
Sachs v. Precision Products Co.
476 P.2d 199 (Oregon Supreme Court, 1970)
Schafer v. Sunset Packing Company
474 P.2d 529 (Oregon Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
471 P.2d 768, 256 Or. 107, 1970 Ore. LEXIS 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/douglas-construction-corp-v-mazama-timber-products-inc-or-1970.