Laro Lumber Co., Inc. v. Patrick

630 P.2d 400, 52 Or. App. 1035, 1981 Ore. App. LEXIS 2879
CourtCourt of Appeals of Oregon
DecidedJune 29, 1981
Docket36224, CA 17828
StatusPublished
Cited by10 cases

This text of 630 P.2d 400 (Laro Lumber Co., Inc. v. Patrick) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laro Lumber Co., Inc. v. Patrick, 630 P.2d 400, 52 Or. App. 1035, 1981 Ore. App. LEXIS 2879 (Or. Ct. App. 1981).

Opinion

*1037 WARREN, J.

Plaintiff brought this action to foreclose a construction lien for work done on a road. Defendant counterclaimed, contending that plaintiff failed to complete the work in a workmanlike manner, and prayed for damages representing the cost of completing the work in accordance with the contract terms.

The trial court found that the parties had entered into a written contract under which plaintiff agreed to construct a road to defendant’s subdivision development for cost plus 10 percent to "* * * be completed in a substantial and workmanlike manner according to standard practices.” It found that under the agreement plaintiff was entitled to recover $20,831.16. On defendant’s counterclaim, the court found that the maximum grade of the road allowable to obtain local fire department service to the subdivision and to obtain local planning board approval was 12 percent. Because the grade exceeded 12 percent and because of substandard drainage and fill, the trial court concluded the road was of little value to defendant as a subdivider. It found plaintiff was aware of defendant’s needs and should have been aware of local requirements for grade, drainage and fill and that defendant was entitled to a setoff of $8,484, the cost of bringing the road up to local standards.

Plaintiff first contends that the trial court erred in allowing defendant any setoff, because the amount of defendant’s damage was not proved with reasonable certainty. In a case involving a claim of lost profits, the party with the burden of proof must establish with reasonable certainty that some profits would have been made even though the amount of such profit may be determined from evidence from which a satisfactory estimate based upon supporting data may be made. Douglas Const. v. Mazama Timber, 256 Or 107, 110- 111, 471 P2d 768 (1970). But this is not a case in which defendant claimed loss of profits. Defendant’s claimed setoff was for the cost of bringing the defendant’s road up to the standards required by the contract. In such case, the cost of repair is the correct measure of damage. Beik v. American Plaza Co., 280 Or 547, 555, 572 P2d 305 (1977). Defendant produced evidence that the cost of repairing the road would range from a low estimate *1038 of $7,000 to a high estimate of $15,000. The estimates were based on supporting data as to the nature of the work, including removal of rock and the amount of labor and material that would be required to resurface the road. The evidence supports the trial court’s conclusions both as to the fact that defendant sustained damage and as to the cost of repairing the road. Thus we affirm that portion of the decree. 1

Plaintiff next contends that the trial court erred in failing to award him costs and attorney fees pursuant to ORS 87.060(4), which provides:

"When notice of intention to commence suit to foreclose the lien has been given, pleaded and proven as provided for in ORS 87.057, the Court, upon entering judgment for the lien claimant, shall allow as part of the costs all moneys paid for the filing or recording of the lien. In suits to enforce a lien created by ORS 87.010 the Court shall allow as part of the costs, a reasonable amount as attorney fees to the prevailing party, except as provided in subsection (2) of ORS 87.039 and subsection (3) of ORS 87.057.”

ORS 87.039 provides:

"(1) A person filing a claim for a lien as provided by ORS 87.035 shall deliver to the owner a notice in writing that the claim has been filed. The notice shall be delivered not later than 20 days after the date of filing. Notice delivered to the owner who received the delivery notice as provided by ORS 87.021 shall be deemed in compliance with the requirement of this subsection, unless the person giving notice has actual knowledge of changed ownership.
"(2) No costs, disbursements or attorney fees otherwise allowable as provided by ORS 87.060 shall be allowed to any party failing to comply with subsection (1) of this section.”

The maimer of giving the notice is specified in ORS 87.018, which provides that all notices required to be given *1039 under the lien statutes shall be in writing and delivered in person or by registered or certified mail. It is undisputed that, while the notice of intent to foreclose the lien was given by certified mail, the notice of the filing of the lien was given by regular mail. Though defendant admitted receipt of the notice, the trial court in reliance on ORS 87.039(2) denied attorney fees and lien costs, as well as general costs under ORS 20.040. It was apparently the trial court’s belief that all costs and attorney fees should be denied, because the lien filing notice was not sent by registered or certified mail.

In Ore. Broadcast, v. Grecian Health Spa, 271 Or 31, 34, 530 P2d 80 (1975), the Supreme Court noted:

"The obvious purpose of the requirement that notice of an intent to foreclose a lien must be given to the property owner is to give the owner an opportunity, prior to the commencement of the suit, to pay the lien and to prevent liability for costs and disbursements including attorney’s fees. Defendants suggests no other reason for requiring such notice * * (Emphasis added.)

See also Nugent v. Carson, 42 Or App 701, 704, 601 P2d 840 (1979). Although these cases hold that a total failure to give notice of intent to foreclose prevents a lienor from recovering lien costs and attorney fees, they do not hold that failure to give notice in the manner prescribed precludes the award of costs and attorney fees under ORS 87.060.

Here the notice of intent to foreclose the lien was properly given under Ore. Broadcast, and Nugent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hazelwood Water District v. First Union Management, Inc.
715 P.2d 498 (Court of Appeals of Oregon, 1986)
Banister Continental Corp. v. Northwest Pipeline Corp.
709 P.2d 1103 (Court of Appeals of Oregon, 1985)
Simkins-Hallin Lumber Co. v. Simonson
692 P.2d 424 (Montana Supreme Court, 1984)
Leffler v. Spindler
686 P.2d 1045 (Court of Appeals of Oregon, 1984)
Parsons v. Henry
672 P.2d 717 (Court of Appeals of Oregon, 1983)
SDS Lumber Co. v. Allendale Mutual Insurance
563 F. Supp. 608 (D. Oregon, 1983)
Ace Electric Co. v. Portland General Electric Co.
637 P.2d 1366 (Court of Appeals of Oregon, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
630 P.2d 400, 52 Or. App. 1035, 1981 Ore. App. LEXIS 2879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laro-lumber-co-inc-v-patrick-orctapp-1981.