Ace Electric Co. v. Portland General Electric Co.

637 P.2d 1366, 55 Or. App. 382, 1981 Ore. App. LEXIS 3918
CourtCourt of Appeals of Oregon
DecidedDecember 30, 1981
Docket6090, CA 18782
StatusPublished
Cited by2 cases

This text of 637 P.2d 1366 (Ace Electric Co. v. Portland General Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ace Electric Co. v. Portland General Electric Co., 637 P.2d 1366, 55 Or. App. 382, 1981 Ore. App. LEXIS 3918 (Or. Ct. App. 1981).

Opinion

*384 WARREN, J.

Ace Electric Company (Ace) brought this action against Portland General Electric Company, The Boardman Power Company, and Marine Midland Bank 1 (PGE), to recover the value of work which it performed on PGE’s Boardman Coal Project. Ace alleged that the work in question was outside the scope of its construction contract and it is, therefore, entitled to extra compensation. Alternatively, it contended that, if the work was within the scope of the contract, it is entitled to the reasonable value of the work because of its unilateral mistake of fact. PGE appeals from a judgment for Ace.

PGE is an Oregon public utility, and Ace is an electrical construction contractor. Swan Wooster is a major engineering firm, which PGE employed to act as architect/ engineer in supervising the construction of the Boardman Coal Project, a $350,000,000 construction project located in Morrow County.

On January 4,1977, PGE invited bids on preliminary electrical work from nine electrical contractors recommended by Swan Wooster as qualified and experienced. Each contractor received identical bid documents, which included the general terms and conditions of bidding and specifications and drawings which were intended to identify the nature and extent of the work to be bid. The bid required, among other things, a number of underground duct banks, which were to be constructed of either ordinary concrete with plastic conduit or reinforced concrete with galvanized rigid steel conduit (reinforced duct banks). The specifications stated that the reinforced duct banks were to be used wherever duct banks extended under railroads or roadways or in fill areas. Unfortunately, the electrical drawings, which described the work in detail and which showed the location of some of the duct banks, did not show either the railroads, roadways, or fill areas, or duct banks which were to extend under them. As a result, a contractor bidding on the documents submitted could not accurately bid the project as contemplated by PGE. Moreover, nothing in the original bid package indicated that the drawings were incomplete. *385 On February 8, PGE sent to all bidders an “addendum 4.” This addendum, “issued * * * for information and reference only,” consisted of construction drawings of the type used by road and railroad contractors, rather than by electrical contractors, and did not show any duct banks. The drawings did show the location of the roads and railroads; thus, an alert bidder, if he integrated these drawings with the other materials, could estimate with reasonable accuracy the amount of reinforced duct banks needed for the project. Neither the addendum itself nor PGE informed the bidders that they should so use the drawings, however. Only three of the nine bidders took account of these duct banks in formulating their bids.

Ace was one which did not, and it submitted the low bid of $183,300. This bid was substantially less than the high bid of $259,583 and the $450,000 that Swan Wooster had independently estimated would be the cost of this job. Swan Wooster suspected immediately upon opening the bids that most of the bidders, and particularly Ace, had failed to provide for reinforced duct banks under roads, railroads, and in fill areas. 2 Swan Wooster’s engineer, in a report to PGE dated March 14, recommended awarding the contract to Ace, but recommended that PGE first discuss with Ace the amount and type of conduit it expected to use in order to determine whether Ace’s bid included all the necessary work. PGE decided not to follow this recommendation, however, and instead phoned Ace’s estimating manager to inquire only whether Ace was satisfied with its bid. PGE mentioned none of the matters which had concerned Swan Wooster and, when asked by Ace why it was inquiring, responded only that it was “checking” because Ace’s bid was “so low.”

Although Ace rechecked its bid because of this telephone conversation, it did not discover its mistake, and the contract was executed on March 31. On April 4 and April 11, Ace was provided with new drawings which showed the reinforced duct banks in detail and their precise location *386 under the roads and railroad. Ace immediately objected to Swan Wooster that the drawings required work which was outside the contract. Swan Wooster ordered Ace to proceed with the work and to submit a proposal for additional compensation in accordance with contract provisions, which required Ace to submit all questions of contract interpretation to Swan Wooster, whose decision was final unless a written protest was submitted to PGE and which further required that, pending a decision, Ace had to proceed with the work, if Swan Wooster so ordered. Ace followed the various protest procedures and kept separate records for the disputed work.

Ace’s claim, totalling $53,260.77, 3 was ultimately rejected by PGE, and Ace sought recovery in circuit court under three legal theories. The first two theories involved interpreting the contract in such a manner that the disputed work was not a part of it. Under the third theory, Ace sought recovery for the reasonable value of supplying reinforced duct banks as relief from its unilateral mistake. The trial court found for Ace on. all of its theories and also awarded Ace $30,000 attorney fees and prejudgment interest.

We will assume, as contended by PGE, that the disputed work was part of the contract, but we agree with the trial court that Ace is entitled to recover on its unilateral mistake theory.

The controlling principle is stated as follows:

“[I]n this State an offer and an acceptance are deemed to effect a meeting of the minds, even though the offeror made a material mistake in compiling his offer, provided the acceptor was not aware of the mistake and had no reason to suspect it. But if the offeree knew of the mistake, and if it was basic, or if the circumstances were such that he, as a reasonable man, should have inferred that a basic mistake was made, a meeting of the minds does not occur. * * *” Rushlight Co. v. City of Portland, 189 Or 194, 244, 219 P2d 732 (1950).

See also, Highway Com. v. State Construction Co., 203 Or 414, 436-437, 280 P2d 370 (1955), where the Rushlight principle *387 was held to apply generally to bidders’ errors which are made without gross negligence. It is clear that this case falls squarely under the Rushlight principle. The trial court determined that Swan Wooster knew that Ace had made a mistake, and our review of the record confirms that conclusion. Moreover, Swan Wooster, in addition to being PGE’s agent, communicated its misgivings directly to PGE.

PGE makes a great deal of its request that Ace recheck its bid, styling this telephone call a “red flag,” which was designed to alert Ace to its error but which could not be more explicit, because “negotiation” is improper in lump sum bidding. In the first place, we find PGE’s explanation for the obscurity of the warning strikingly unpersuasive, as “negotiation” was hardly necessary — all that Rushlight

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burwell v. Oklahoma Farm Bureau Mutual Insurance Co.
1995 OK CIV APP 50 (Court of Civil Appeals of Oklahoma, 1995)
SDS Lumber Co. v. Allendale Mutual Insurance
563 F. Supp. 608 (D. Oregon, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
637 P.2d 1366, 55 Or. App. 382, 1981 Ore. App. LEXIS 3918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-electric-co-v-portland-general-electric-co-orctapp-1981.