North Pacific Construction Co. v. Wallowa County

249 P. 1100, 119 Or. 565
CourtOregon Supreme Court
DecidedNovember 16, 1926
StatusPublished
Cited by13 cases

This text of 249 P. 1100 (North Pacific Construction Co. v. Wallowa County) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Pacific Construction Co. v. Wallowa County, 249 P. 1100, 119 Or. 565 (Or. 1926).

Opinion

*566 PER CURIAM.

The plaintiff had two' contracts with the defendant connty to construct two pieces of road in that county under the usual form of highway contracts, each of which contained the following provision:

“The engineer shall determine the amount or quantity of the work which is to be paid for under this contract, and decide all questions which may arise relative to the fulfillment of these specifications, and his estimates and decisions shall be final and conclusive and binding upon both parties to this contract.”

When the work had been completed and accepted by the county, it became the duty of the engineer in charge of the work, as soon as practicable thereafter as agent for the county, in pursuance of the terms of the contracts, to make a final estimate of the work and the amount to be paid and it was required by the agreement that within thirty-five days from the filing of such estimate the defendant should pay the contractor the balance due after deducting all previous payments. The engineer made such an estimate on July 6, 1921, and this suit was commenced to set aside the same and to make a proper allowance for the work performed and not yet paid for. We assume from the making and filing of the final estimate that the parties treated the project as completed for all practical purposes, else why the final estimate of the engineer?

That such a suit may be maintained, notwithstanding the provision of the contract just quoted, making the decision of the engineer final, is well settled in this state, the latest decision being that of Baker v. Multnomah County, 118 Or. 143 (246 Pac. 352), in which the opinion was written by Mr. Justice Bean.

*567 Aside from the rock excavation known as “sub-grade,” there is no essential dispute about the quantities of excavation. The vital issue is about the classification. This provision appears in the contracts :

“Excavation shall be classified under three heads, viz.: Common excavation, intermediate excavation solid rock excavation.

“Common Excavation shall include all earth, clays, sand and gravel, or all earth, clays, sand and gravel containing loose stone, measuring less than one-half (%) of one cubic foot, and all material that can be plowed with a good four-horse team.

“Intermediate Excavation shall include hardpan, shale, sandstone, soft and decomposed rock, cemented gravel, boulders and stone measuring less than one-half (%) cubic yard in volume, shell rock and all other material of a rock nature or otherwise, that in the judgment of the engineer may be loosened with a pick, although blasting may be resorted to in order to expedite the work.

“Solid Bock Excavation shall include all hard rock found in place in ledges, and in masses, or boulders measuring more than one-half (%) cubic yard, and which can only be removed by blasting, which fact shall be determined by the engineer.”

The testimony is quite voluminous; in fact, unnecessarily so and cannot be repeated here in detail. A dispute having arisen between the parties respecting the classification, the matter to be determined is whether the classification of the engineer in charge of the work, as agent of the county, was reasonably fair or whether it was so • grossly erroneous as to amount to an injustice or fraud upon the contractor. A great many plats of cross-sections of cuts and embankments have been introduced in evidence, but as a *568 practical matter, analogous to the examination of long accounts, we are compelled to rely upon the testimony of expert engineers who as witnesses are skilled in the examination and computation of such data.

The road was constructed over an undulating pedregal. There was a great deal of loose rock on the surface and in places the bedrock cropped out and in other portions it was covered with only a thin layer of earth. There were many cuts excavated through solid rock. It is in the testimony that the engineer had given the county court an estimate that the whole highway could be constructed for about $28,000, but when the proposal was advertised, the cost indicated by the bid seemed to have surprised the engineer and there is a vein running throughout the testimony, and substantially admitted by him, that he considered the price of the work too high and that, in making up his estimate, he was strongly influenced by that conception, with the result that he classified the excavation as “common” to an unwarranted extent in order to pay for the same at the cheapest rates. On one contract the price for common excavation was $1.07% per cubic yard, while intermediate was priced at $2.25 and solid rock at $5 per cubic yard. On the other those prices were respectively 95 cents, $2.15 and $4.25 per cubic yard. The engineer was greatly interested in protecting his original estimate and paying for the work at the cheapest possible price, and while properly he should protect the interests of the county, so far as he lawfully could in compliance with the contract, he would have no right to use his position as engineer in charge to do a wrong to the contractor or to violate the agreement between the principals. Whether the price was too high or too low was a question to settle at the outset by the County Court as manager of the fiscal concerns of the county.

*569 Before any litigation was commenced, the parties called to their assistance as gwsi-arbitrators the engineer who had charge of the work as representing the county, another engineer, H. S. Huson, representing the contractor, the plaintiff herein, and a third, Lyman Griswold, who represented neither party hut was wholly indifferent between them. It was agreed in the first place that the decision of these engineers should not be binding on either party but, in pursuance of that stipulation, they went over the work together within two or three months after the completion of the road and agreed, as it appears from the weight of the testimony, upon the quantities to be allowed of each kind of excavation, aside from the question of “subgrade” excavation. However, when the report was typewritten and the prices for the various kinds of excavation were extended, the county engineer refused to sign the report. He did not make any minority report but simply refused to sign on the ground that he had not checked up the items. This report showed a large increase of solid rock excavation and materially reduced the less difficult “common excavation. Failing to come to an agreement or settlement, this litigation was commenced, after which other engineers on both sides were called in to estimate the work.

All measurements, after the failure to agree on the arbitration so called, were made many months after the work had been completed and accepted by the county and after the road had been used considerably. It is conceded that the most accurate remeasurements of excavations and fills are to be made either as the work progresses or immediately after its completion and that the longer the lapse of time after the work is finished before remeasurement is undertaken, the less accurate the same will be. Most of the classifi *570

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. State
96 P.3d 1239 (Court of Appeals of Oregon, 2004)
Newport Church of the Nazarene v. Hensley
56 P.3d 386 (Oregon Supreme Court, 2002)
SDS Lumber Co. v. Allendale Mutual Insurance
563 F. Supp. 608 (D. Oregon, 1983)
Laro Lumber Co., Inc. v. Patrick
630 P.2d 400 (Court of Appeals of Oregon, 1981)
Krieg v. UNION PACIFIC LAND RESOURCES CORPORATION
525 P.2d 48 (Oregon Supreme Court, 1974)
State Highway Commission v. Carmel Estates, Inc.
525 P.2d 61 (Court of Appeals of Oregon, 1974)
Lundgren v. Freeman
307 F.2d 104 (Ninth Circuit, 1962)
Eldon v. Chandler
275 P.2d 748 (Oregon Supreme Court, 1954)
Public Market Co. v. City of Portland
138 P.2d 916 (Oregon Supreme Court, 1942)
Northern Pac. Ry. Co. v. Twohy Bros. Co.
95 F.2d 220 (Ninth Circuit, 1938)
Mayer v. East Side Logging Co.
280 P. 343 (Oregon Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
249 P. 1100, 119 Or. 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-pacific-construction-co-v-wallowa-county-or-1926.