General Construction Co. v. Oregon State Fish Commission

554 P.2d 185, 26 Or. App. 577
CourtCourt of Appeals of Oregon
DecidedAugust 30, 1977
DocketNo. 394-578, CA 4833
StatusPublished
Cited by3 cases

This text of 554 P.2d 185 (General Construction Co. v. Oregon State Fish Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Construction Co. v. Oregon State Fish Commission, 554 P.2d 185, 26 Or. App. 577 (Or. Ct. App. 1977).

Opinion

FORT, J.

This case arises out of the construction of a contract for a fish ladder at Willamette Falls on the Willamette River between West Linn and Oregon City. After trial the court awarded plaintiff a judgment of $543,204 for breach of the contract. The issues are first whether plaintiff signed an accord and satisfaction thus defeating the cause of action for a breach of contract, and second whether testimony of plaintiff’s expert witness and certain exhibits were properly admissible.

Shortly after plaintiff started construction of the fish ladder in July 1969, it discovered significant errors in the specifications and drawings provided by defendant State Fish Commission. The inaccuracies resulted from erroneous data furnished by defendant about the existing dam against which the fish ladder was to be built. These errors required new surveying and engineering as well as changes in work already done, all of which delayed construction significantly at greatly increased cost. Timing on the progress of the project was critical since water regularly overtopped the dam during fall and winter and the contractor’s plans required that the work be sufficiently completed before the high water period to withstand the overflowing water. As a result, by the time overflow of the river occurred in the fall of 1969 the structure had not been sufficiently completed to withstand its impact and was badly damaged by the water.

In March and April 1970 while flow of the water still overtopped the dam, the parties signed Change Order No. 1 which increased the contract price by $19,646 and specified certain changes in the plans. This document did not state that it was plaintiff’s exclusive remedy for all damages arising from the inaccurate specifications nor did it state that plaintiff reserved its right to collect further damages. Defendant contends that this change order was an accord and satisfaction by which plaintiff signed away all its rights for recovery of extra costs resulting from defendant’s mistakes in design and [580]*580errors in specifications. Plaintiff contends that the $19,646 was intended to cover costs only of the specific changes described in that document since at that time the parties had no idea what other damages would result from the delay or from the overflow damage to work already done.

Near the end of the project in'1971 plaintiff filed a claim for an equitable adjustment as required under the contract for all damages resulting from the delay by reason of the inaccurate specifications. Defendant commission rejected the claim. Plaintiff thereupon sued for breach of contract, specifying breach of the state’s warranty that the specifications would be accurate.

On appeal defendant does not challenge any of the trial court’s findings of fact.1 We are thus bound by them.

[581]*581Based on these findings, the court also entered conclusions of law. On appeal defendant challenges both the conclusion of law that Change Order No. 1 was not an accord and satisfaction for all damages resulting from the inaccurate specifications and also the conclusion that the inaccurate plans and specifications constituted a material breach of the contract.

We conclude from the findings of fact that the latter challenge cannot be sustained, as the breaches there described were indeed material. The contract contained a provision relating to defective specifications which provided in part:

"* * * That in the case of defective specifications for which the State is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with such defective specifications.”

In Barbour & Son v. Highway Com., 248 Or 247, 433 P2d 817 (1967), the court in a case involving faulty specifications in a contract to paint a bridge said:

"The specification is in the nature of a warranty that, if it is 'complied with, satisfactory performance will result’: J. D. Hedin Construction Company v. United States, 347 F2d 235, 241 (Ct Cl); United States v. Spearin, [582]*582248 US 132, 136, 39 S Ct 59, 63 L ed 166; Montrose Contracting Co. v. County of Westchester, 80 F2d 841 (2d Cir). See Savage v. Peter Kiewit Sons’ Co., 249 Or 147, 432 P2d 519, 523.
"In these circumstances the provision of the contract respecting loss arising from 'unforeseen difficulties’ has no application.” 248 Or at 257-58.

Whether Change Order No. 1 was an accord and satisfaction of all damages resulting from the inaccurate specifications depends on the intent of the parties. In Lenchitsky v. H. J. Sandberg Co., 217 Or 483, 343 P2d 523 (1959), the Supreme Court said:

"This court has twice approved the following statement from 1 CJ 529, Accord and Satisfaction § 16, as evidencing its concept of what is necessary to constitute a valid accord and satisfaction:
" 'To constitute a valid accord and satisfaction it is also essential that what is given or agreed to be performed shall be offered as a satisfaction and extinction of the original demand; that the debtor shall intend it as a satisfaction of such obligation, and that such intention shall be made known to the creditor in some unmistakable manner. It is equally essential that the creditor shall have accepted it with the intention that it should operate as a satisfaction. Both the giving and the acceptance in satisfaction are essential elements, and if they be lacking there can be no accord and satisfaction. The intention of the parties, which is of course controlling, must be determined from all the circumstances attending the transaction.’ (Emphasis ours.)” (Italics in second sentence ours.) 217 Or at 490.

The party alleging an accord and satisfaction thus has the burden of proof on that issue. Lenchitsky v. H. J. Sandberg Co., supra, 217 Or at 490.

Witnesses for both sides testified that nothing but the specific items covered were discussed in negotiations for Change Order No. 1. Plaintiff points out that the delay damages could not have been fully determined at the time of the change order since water was still overflowing the previous season’s work. Thus the parties could not have considered those clamages at that time.

[583]*583Plaintiff’s letter enumerating the cost increases resulting from the specific changes in the layout to be incorporated in Change Order No. 1 refers only to those specific changes embraced in Change Order No. 1. Defendant relies on its letter accompanying Change Order No. 1 in which it stated:

"* * * Items included in this change order are those which we have discussed in detail and mutually agreed upon.
"Your letter of February 26, 1970, requests that contract time be extended to cover flood conditions and structural damage. Your request did not include specific reasons nor the exact number of days requested. Without such details, we would have to deny your request. We also believe that Change Order No. 1 makes your request academic. We therefore will take no action on this matter at this time.”

We do not believe that this letter as a matter of law makes it known to the creditor in some unmistakable manner that Change Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davison v. Parker
622 P.2d 1113 (Court of Appeals of Oregon, 1981)
Meislahn v. Demorest
617 P.2d 322 (Court of Appeals of Oregon, 1980)
State ex rel. Juvenile Department v. Kramer
580 P.2d 211 (Court of Appeals of Oregon, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
554 P.2d 185, 26 Or. App. 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-construction-co-v-oregon-state-fish-commission-orctapp-1977.