Gillingham Construction Inc. v. Newby-Wiggins Construction Inc.

42 P.3d 680, 136 Idaho 887, 2002 Ida. LEXIS 21
CourtIdaho Supreme Court
DecidedFebruary 22, 2002
Docket26577
StatusPublished
Cited by10 cases

This text of 42 P.3d 680 (Gillingham Construction Inc. v. Newby-Wiggins Construction Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gillingham Construction Inc. v. Newby-Wiggins Construction Inc., 42 P.3d 680, 136 Idaho 887, 2002 Ida. LEXIS 21 (Idaho 2002).

Opinion

EISMANN, Justice.

This is an appeal from a directed verdict dismissing the plaintiffs claim for breach of a construction contract. We affirm in part, reverse in part, and remand for further proceedings.

I. FACTS AND PROCEDURAL HISTORY

Viewing the evidence favorably to the appellant Gillingham Construction, Inc., (Gillingham), as we must on an appeal from a directed verdict, the facts are as follows. The State of Idaho awarded the respondent Newby-Wiggins Construction, Inc., (NewbyWiggins) the prime contract to construct the regional headquarters building for the Idaho Department of Parks and Recreation on Warm Springs Avenue in Boise, Idaho. On July 19,1993, Newby-Wiggins entered into a subcontract with the appellant Gillingham under which Gillingham agreed to perform certain demolition and excavation work in connection with that construction project. That work included demolishing and removing the remains of an old brickyard; excavating the building pads and parking areas for the new construction; and rough grading the site. Newby-Wiggins agreed to pay Gillingham a lump sum for its work under the subcontract.

Gillingham first completed the demolition and removal of the buildings, concrete and asphalt driveways, and other remnants of the old brickyard, and it then began preparing the ground for construction as required in its subcontract. It completed the ground preparation in stages, first installing the pad for the construction of the headquarters building, then excavating and grading for the west parking lot, and then excavating and grading for the east parking lot. Before Gillingham began work on each stage, another subcontractor would drive survey stakes into the ground in that portion of the construction site. The survey stakes would show the existing elevation of the ground and the depth of dirt, in hundredths of an inch, that Gillingham would have to either cut (remove) or fill (add) in order to bring the existing ground elevation to the finish grade elevation specified in the plans. After Gillingham had completed approximately 85% of the work required under its subcontract, its project superintendent discovered that there was an error in the elevations recorded on the survey stakes. While grading a portion of the site where the elevation of the finish grade was to match the elevation of the adjoining land, he realized that the two grades would not match.

Gillingham’s project superintendent brought the problem to the attention of Newby-Wiggins, and the matter was then discussed at the next weekly construction meeting, which was held on October 6, 1993. After the meeting, representatives of Gillingham, Newby-Wiggins, and the State checked the problem area. They discovered that in parts of the construction site that were still undisturbed, the elevations shown on the plans did not correspond to the elevations shown on the survey stakes. Newby-Wiggins and the architect hired by the State then told Gillingham to stop work on the project until the problem could be resolved.

After Gillingham had stopped work for sixteen days, it removed its equipment from the site (demobilized) until it received word from Newby-Wiggins to resume work. On November 1, 1993, Gillingham moved its *890 equipment back to the site (remobilized), but seven days later it was again told to stop work. At some point in November, Gillingham returned to work, but had to stop working again because of the weather. It completed its obligations under the subcontract in the spring of 1994, based upon new site drawings that were prepared for the project.

Gillingham requested additional compensation for its work done on the site. It contended that the survey upon which the site drawings were based was incorrect and that the elevations shown on those drawings were lower than the actual elevations. As a result, Gillingham was required to remove more dirt than the site drawings showed it would be required to move. It also claimed compensation for the time that its equipment sat idle at the construction site after it was told to stop work (standby charges) and for the costs incurred in demobilizing and remobilizmg.

On June 27, 1997, Gillingham filed this, action against Newby-Wiggins seeking to recover the additional compensation it claimed. Newby-Wiggins filed a third-party claim against the State, alleging that Gillingham’s damages were caused by the State. The State then filed a third-paity claim against the architects it had hired to draw the plans and specifications for the project, alleging that the architects were liable for any deficiency in those plans and specifications.

After being set and rescheduled several times, this case was set for a jury trial to commence on April 3, 2000. Just prior to trial, Gillingham entered into a settlement with the State. Although the settlement documents are not part of the record, in its brief Gillingham describes the terms of the settlement as follows, “Gillingham settled NewbyWiggins’ indemnity claim agáinst the State and agreed to indemnify the State for any liability it might have as a result of NewbyWiggins’ indemnification claim.”

After three days of trial, Gillingham rested its case against Newby-Wiggins, who then moved for a directed verdict dismissing Gillingham’s complaint. The district court granted that motion, and later awarded New-by-Wiggins court costs, including attorney fees, totaling $60,642.19. Gillingham then appealed.

II. ANALYSIS

Gillingham alleged three causes of action in its complaint. In Count One it alleged that Newby-Wiggins had impliedly warranted the sufficiency of the plans and specifications provided by the State and had breached that warranty. In Count Two it alleged that it was entitled to additional compensation for the extra work it was required to perform because of the defective plans and specifications provided by the State. In Count Three it alleged that Newby-Wiggins was unjustly enriched by the extra work that Gillingham had performed on the project. Prior to trial, the district court granted Newby-Wiggins’ motion to dismiss Count Three for failure to state a claim upon which relief could be granted, and Gillingham has not appealed that dismissal. This ease went to trial on Gillingham’s claims of breach of an implied warranty regarding the sufficiency of the plans and specifications and for additional compensation for the extra work.

A. Did the district court err in dismissing Gillingham’s claim that Newby-Wiggins had impliedly warranted that the plans and specifications provided by the State were sufficient?

The district court dismissed the implied warranty claim at the conclusion of Gillingham’s case on the ground that under Idaho law a general contractor does not impliedly warrant to a subcontractor the sufficiency of the plans and specifications provided by the owner. Whether or not such a warranty is implied in construction contracts between contractors and their subcontractors is an issue of law over which we exercise free review.

Although not yet addressed by appellate courts in Idaho, courts in several other jurisdictions have held that an owner who provides plans and specifications to a contractor impliedly warrants that they are sufficient for their particular purpose. State, Dept. of Natural Res. v. Transamerica Premier Ins. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SRM Arms, Inc. v. GSA Direct, LLC
494 P.3d 744 (Idaho Supreme Court, 2021)
Investor Recovery Fund v. Hopkins
Idaho Supreme Court, 2020
Dennis J. Sallaz and Marcy Fox v. Eugene (Roy) Rice
384 P.3d 987 (Idaho Supreme Court, 2016)
In Re University Place/Idaho Water Center Project
199 P.3d 102 (Idaho Supreme Court, 2008)
University of Idaho Foundation, Inc. v. Civic Partners, Inc.
199 P.3d 102 (Idaho Supreme Court, 2008)
Todd v. Sullivan Construction LLC
191 P.3d 196 (Idaho Supreme Court, 2008)
Hansen v. City of Pocatello
184 P.3d 206 (Idaho Supreme Court, 2008)
Gunter v. Murphy's Lounge, LLC
105 P.3d 676 (Idaho Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
42 P.3d 680, 136 Idaho 887, 2002 Ida. LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gillingham-construction-inc-v-newby-wiggins-construction-inc-idaho-2002.