Hash v. R. J. Sundling & Son, Inc.

436 P.2d 83, 150 Mont. 388, 1967 Mont. LEXIS 304
CourtMontana Supreme Court
DecidedDecember 28, 1967
Docket11294
StatusPublished
Cited by11 cases

This text of 436 P.2d 83 (Hash v. R. J. Sundling & Son, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hash v. R. J. Sundling & Son, Inc., 436 P.2d 83, 150 Mont. 388, 1967 Mont. LEXIS 304 (Mo. 1967).

Opinion

MR. JUSTICE HASWELL

delivered the Opinion of the Court.

This is an appeal from a judgment awarding a highway construction subcontractor the sum of $14,272 and interest against the prime contractor covering the reasonable cost of performing certain alleged unanticipated excavation under the subcontract between them. The case was tried in the district court of Park County before the Honorable Nat Allen, presiding judge, sitting without a jury, who rendered judgment based on his findings of fact and conclusions of law.

The plaintiff in the case is A. G. Hash, d/b/a Hash Construction Co., who is the subcontractor on the excavation work involved in the highway construction project herein, and who will be referred to hereafter as Hash. Defendant in the case is R. J. Sundling and Son, Inc., who is the prime contractor with the State of Montana on the entire highway construction contract and who subcontracted the excavation work to Hash; defendant will hereafter be referred to as Sundling. The contract provisions relating to the excavation work were contained in the prime contract between the State of Montana and Sundling; these identical provisions were incorporated in the subcontract between Sundling and Hash.

On June 25, 1963, Sundling entered into the prime contract with the State of Montana to reconstruct and widen approximately 5y2 miles of highway in Gallatin County between Gallatin Gateway and Pour Corners. The construction project generally involved removing the oiled surface of the existing high *390 way, excavating down to a snbgrade indicated by the plans and specifications for the project and staked by the Montana Highway Department, widening the highway and establishing a corresponding subgrade on the widened portion, and constructing the widened highway accordingly.

The specifications for the project as set forth both in the prime contract and the subcontract consisted of standard specifications common to all highway construction projects which were set forth in a pamphlet of 460 pages divided into 97 different sections. Insofar as these standard specification are pertinent to the excavation work in the instant case, they provided: (1) That the excavation work generally would consist of excavating and grading the roadway and borrow pit including excavation, removal, and disposal of unsuitable material from the roadbed and embankment areas within the limits of the work according to the specifications shown in the plans or as staked by the engineer; (2) Where the ground foundation for embankments is composed of muck or other unstable materials the same would be removed to the depth shown on the plans or as directed by the engineer, and the excavated area backfilled; (3) That the bidder would make a thorough examination of the site, the proposal, the plans and specifications, and the contract before bidding and satisfy himself as to the conditions to be encountered; (4) That some changes in the plans and specifications are inherent in highway construction contracts which must be recognized at the time of bidding within normal and expected margins, and the engineer has the right to make such changes; (5) That if such changes exceed an increase or decrease of more than twenty-five percent in (a) the length of the project, (b) the total cost of the work calculated from the original proposal of quantities and contract unit prices or (e) the quantity of any major contract item (including earth or common roadway excavation but excluding any other class or item of foundation piling), a supplemental agreement would be made covering adjustments in payment; *391 (6) Such adjustments would be made on the basis of the contract unit prices in the original contract for the additional work and materials; and (7) In case of discrepancies between the standard specifications and the plans, the plans would govern.

The plans for the project in general called for stripping off the oil mat on the existing highway, excavating to an average depth of one to two feet below the level of the existing road as staked by the Highway Department, and widening the road. The excavation generally did not exceed the base of the existing roadbed, did not reach the borrow pit level, and was already staked out by the Highway Department.

Hash became interested in securing a subcontract with Sundling for the excavation work involved. Hash inspected the site, examined the plans and specifications for the project, crosschecked the plans and specifications against the grade stakes installed by the Montana Highway Department, noted some wetness in the ditch bottom in the borrow pit alongside the existing highway and at one point probed the ditch bottom with a stick and found mud to a depth of one foot, and found that the general excavation depth averaged one to two feet beneath the surface of the existing road and generally did not exceed the base of the existing roadbed. Hash also talked to Sundling and to the project engineer for the State Highway Department, but the evidence is in conflict as to the statements allegedly made by them to Hash concerning the wetness of the subgrade and the conditions he was likely to encounter.

Subsequently Hash and Sundling negotiated the price of 25 cents per cubic yard for the excavation work under the subcontract at which time Hash indicated that soft conditions might be encountered in the excavation. On September 3, 1963, Hash entered into a subcontract with Sundling for the excavation work on the project consisting generally of unclassified excavation of 155,584 cubic yards at 25 cents per cubic yard or a total price of $38,896 according to the plans, specifications, *392 bid and proposal on file with the Secretary of the Montana Highway Commission pertaining to the project.

Shortly thereafter Hash commenced the excavation work on the project and all went well for two or three weeks. At that time Hash began to encounter excessive wetness below the sub-grade which required extensive “dig-outs” below the subgrade to provide a solid foundation for the bed of the highway to be constructed. The State Highway project engineer required of Sundling that all muck, water and unstable material be removed and that the excavation so created be backfilled; Sundling in turn required Hash to do this. All evidence indicates that Hash discussed with Sundling the matter of additional compensations for this work, but a substantial conflict exists over what assurances, if any, Sundling made to Hash covering additional compensation. Hash claims that shortly after he encountered the excessive wetness below subgrade as indicated in the plans and was required to make an extensive “dig-out,” he told Sundling he would have to quit and forfeit the work already done because he simply could not dig out the type of material actually encountered for the contract price, but that Sundling told him to go ahead with the excavation work, keep track of his time and expense on the excavation work below sub grade, that although he (Sundling) did not want to get into trouble with the State until after completion of another job for them, at that time he (Sundling) would see that Hash got additional compensation even to the extent of suing the State, if necessary. Hash claims that he continued the excavation work on the project based upon these representations by Sundling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Virginia Beach Federal Savings & Loan Ass'n v. Wood
901 F.2d 849 (Tenth Circuit, 1990)
Beco Corp. v. Roberts & Sons Construction Co.
760 P.2d 1120 (Idaho Supreme Court, 1988)
Haener v. Ada County Highway District
697 P.2d 1184 (Idaho Supreme Court, 1985)
Stenerson v. City of Kalispell
629 P.2d 773 (Montana Supreme Court, 1981)
Ray D. Lowder, Inc. v. North Carolina State Highway Commission
217 S.E.2d 682 (Court of Appeals of North Carolina, 1975)
Kiely Constr. Co. v. STATE, STATE HIGHWAY COM'N
463 P.2d 888 (Montana Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
436 P.2d 83, 150 Mont. 388, 1967 Mont. LEXIS 304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hash-v-r-j-sundling-son-inc-mont-1967.