Stenerson v. City of Kalispell

629 P.2d 773, 193 Mont. 8, 1981 Mont. LEXIS 794
CourtMontana Supreme Court
DecidedJune 15, 1981
Docket80-320
StatusPublished
Cited by2 cases

This text of 629 P.2d 773 (Stenerson v. City of Kalispell) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stenerson v. City of Kalispell, 629 P.2d 773, 193 Mont. 8, 1981 Mont. LEXIS 794 (Mo. 1981).

Opinion

*9 MR. CHIEF JUSTICE HASWELL

delivered the opinion of the Court.

Plaintiffs Stenerson and Schmidt, contractors, brought this' action in District Court, Flathead County, seeking to recover $28,301.31 from the City of Kalispell. The district judge entered judgment for the contractors for the total cost overrun on a rough grading job on the Buffalo Hills Golf Course. The City appeals.

In March 1975, the City of Kalispell asked for bids for rough grading and related work on an addition to the Buffalo Hills Golf Course. Respondent contractors obtained copies of the plans and specifications for the proposed work, including a booklet entitled “Rough Grading Specifications” and a map entitled “Rough Grading Plans”. Based on these documents, respondents submitted a bid of $94,991.50.

On April 18, 1975, respondents entered into a contract with the City for the lump sum of $94,991.50, with a unit cost of $1.10 per cubic yard for any additional work. Plaintiffs began working shortly thereafter and completed the work in the allotted 60 days. During this period, respondents performed additional work which was negotiated separately and was paid for by the City. They also entered into a contract for additional construction, called Phase Two, which was terminated after partial completion because of lack of funds.

While engaged in Phase One, the contractors apparently advised the City on several occasions that they were moving more material than was contemplated in the contract. They did not request a change order, nor demand extra compensation before contracting for Phase Two, nor did they ever refuse to continue working.

Final payment for Phases One and Two was completed prior to January 1976. On January 7, 1976, contractors demanded by letter that the City compensate them for the extra 27,477 cubic yards of earth which they had moved which had not been computed into the bid price. The City refused to pay and the contractors filed suit.

The City moved to dismiss, and following plaintiffs’ filing of an amended complaint, moved for summary judgment. The City *10 argued that by reason of certain exculpatory clauses in the grading contract, the contractors had assumed the risk of making an erroneous bid and could not hold the City responsible. Because of the provisions in the contract documents indicating that the calculations on the “Rough Grading Plan” were “approximate,” and that the contractors “shall make [their] own determination as to the amount of topsoil and grading work to be done before submitting a bid,” the City asserts that the contractors can have no claim for the additional work done.

The district judge found that plaintiff contractors justifiably relied on the information provided in the specifications and plans in making their bid, and that the specifications and plans were in error in setting forth the amount of material which would have to be moved. He awarded $28,301.31 to plaintiffs to compensate for the overrun of 27,477 cubic yards moved. The City appeals, raising several issues which we frame as follows:

1) Did the district judge err in not granting defendant’s motion for summary judgment?

2) Does the evidence support the findings of the District Court?

3) Is the City entitled to judgment under the language of the contract?

After the contractors filed their amended complaint, the City moved for summary judgment. The City argued that the contract documents plainly advised all bidders to make their own determination as to the amount of material to be moved and not to rely on the figures on the plans and specifications. By entering into the contract, the bidders bound themselves to do the rough grading at the price bid and can get no additional compensation. Thus, the City argues, the plaintiffs’ complaint fails to state a claim, there can be no issues of material fact before the court, and summary judgment should have been granted.

Rule 56, M.R.Civ.P. provides that a defending party may move for summary judgment. Summary judgment shall be rendered by the judge “if the pleadings, depositions ... interrogatories ... admissions ... [and] affidavits, if any, show that there is no gen *11 uine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Here the district judge denied summary judgment, without memorandum. His reason appears to be obvious; a genuine issue of material fact existed in this case. Based on a recent line of cases from this Court, the district judge determined that the fact finder had to hear the evidence in order to find whether or not the contractors justifiably relied on the plans and specifications in entering into the contract. See Sandkay Const. Co. v. State Highway Comm’n (1965), 145 Mont. 180, 399 P.2d 1002; Haggart Const. Co. v. State Highway Comm’n (1965), 149 Mont. 422, 427 P.2d 686; Hash v. Sundling & Son, Inc. (1967), 150 Mont. 388, 436 P.2d 83; Sornsin Const. Co. v. State (1978), 180 Mont. 248, 590 P.2d 125, 35 St.Rep. 2001. With this factual determination necessary to a decision in the case, the district judge was correct in denying defendant’s motion.

Appellant next attacks the findings of fact and conclusions of law, arguing that the evidence does not support the findings, and that the findings and conclusions do not support the judgment. In making this argument, appellant again urges this Court to ignore the long line of cases from this Court which give a contractor the right to rely on plans and specifications furnished to him in bidding on and contracting a job. The district judge here considered the evidence in light of these decisions and based his findings and conclusions on the evidence presented. We find no error.

In 1965, in the case of Sandkay Const. Co. v. State Highway Comm’n (1965), 145 Mont. 180, 399 P.2d 1002, this Court addressed the following issue:

“[W]here plans and estimates or specifications are used as a basis for bids, is a contractor who has been led to believe that the conditions indicated in such plans exist, able to rely on them and recover for expenses necessary by conditions being other than as represented by such plans?” Sandkay, supra, 145 Mont. at 184, 399 P.2d at 1005.

In Sandkay, we answered that question in the affirmative, finding there that the conditions actually encountered by the contrac *12 tors in performing the contract could not have been reasonably anticipated, which, in effect, put the contractors into the position of having to “ ‘perform an entirely different contract than [sic] the one upon which they bid.’ ” Sandkay, supra, 145 Mont. at 185, 399 P.2d at 1005. See also Hash v. Sundling and Son, Inc. (1967), 150 Mont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark Bros. Contractors v. State
710 P.2d 41 (Montana Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
629 P.2d 773, 193 Mont. 8, 1981 Mont. LEXIS 794, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stenerson-v-city-of-kalispell-mont-1981.