Kiely Construction Co. v. State ex rel. State Highway Commission

463 P.2d 888, 154 Mont. 363, 1970 Mont. LEXIS 403
CourtMontana Supreme Court
DecidedJanuary 20, 1970
DocketNo. 11637
StatusPublished
Cited by2 cases

This text of 463 P.2d 888 (Kiely Construction Co. v. State ex rel. State Highway Commission) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kiely Construction Co. v. State ex rel. State Highway Commission, 463 P.2d 888, 154 Mont. 363, 1970 Mont. LEXIS 403 (Mo. 1970).

Opinion

MR. JUSTICE JOHN C. HARRISON,

delivered the Opinion of the Court.

Plaintiff brought this suit for two different claims arising out of the performance of a highway construction project. The trial court directed the verdict for the plaintiff as to liability on one of the claims and the jury awarded the verdict for the plaintiff on the other claim. Damages were awarded in the amount of $25,000 for each claim. Defendant appeals from judgment and a denial of a motion for a new trial.

Kiely Construction Company (hereinafter referred to as Kiely) was the successful bidder on the “Butte East Project” on Interstate 90. Kiely was to subsurface and pave with concrete approximately 2.8 miles of the road east out of Butte over Pipestone Pass toward Bozeman. When the project was completed Kiely had expenses greatly in excess of estimates on two particular parts of the job, first the crushing operations in a rock quarry, and the second, the added expense of obtaining concrete aggregate sand for paving the road. Believing that the additional expense was attributable to actions and errors on the part of the highway department rather than just a failure to properly bid the project, Kiely filed a claim, for additional compensation. • The highway department refused to pay and Kiely sued.

The Montana State Highway Department as a matter of regular practice provides prospective bidders on road construction projects with an “Available Surfacing Materials Re[365]*365port,” a report that describes the condition and site of rock quarries and gravel pits obtained for use on the project. The purpose of providing this report is to assist the contractor in preparing his bid and to obtain a lower bid.

Approximately twelve days before bids on the “Butte Bast Project” were to be let Kiely received an Available Surfacing Materials Report from the State Highway Department. The first page consists of a graph showing the percentages by weight of various sizes of crushed rock that passed through screens ranging in size between four inches and number 200. It also has two columns showing that 80% of the rock is over 6 inches in size and 5% of tlxc rock is between 4 and 6 inches in size.

The second page of the report contains a sketch of the quarry site beside the road and has 8 locations on it numbered in sequence. Below the map there is a “Test Hole Log.”

“TEST HOLE LOG
LAB NO. TEST HOLE
252536........................ 1 ...................... 30.0' — Granite
252537........................ 2 ...................... 30.0' — Granite
252538........................ 3 ...................... 30.0' — Granite
252539........................ 4 ...................... 30.0' — Decomposed Granite
252540........................ 5 ..................... 30.0' — Decomposed Granite
252541........................ 6 ..................... 30.0' — Granite
252542........................ 7 ..................... 30.0' — Granite
252543........................ 8 ...................... 30.0' — Granite

This form is a standard lab report form used by the highway department and it is the same form that was used in the contract litigated in Haggarty Const. Co. v. State Highway Comm’n, 149 Mont. 422, 427 P. 686.

Highway Department geologists testified they followed standard procedure in making their analysis of the quarry Site. They climbed up the steeply sloping hill and took surface samples of about 50 pounds from each of the locations marked with numbers on the second page of the report. The samples were broken off rock ledges with a sledge hammer [366]*366and a pick and placed in sacks. All samples iaken were sur-, face samples even though the appellant included in its bid information the “Test Hole Log.” The appellant’s geologists testified that it was their practice, where there was a steeply-sloping area, to only make surface reports, but no explanation was given why this practice was not communicated to bidders. During the pleading stage of the case the highway department amended their answer to remove their previous denial of the failure to drill holes, and admitted that no holes were in fact drilled to 30.0 feet, or to any other depth.

Mr. Kiely testified that his company relied on the materials report in preparing their estimates on the job. One of his employees testified that they worked directly from the report in preparing the estimates and they made only a cursory examination of the quarry site during the twelve day period they had to prepare their estimate.

The quarry site was filled with great boulders interpersed with sand and gravel. The rock was not a type of granite which would fracture when blasted or crushed. When the rock was blasted the boulders did not break up enough to be put into the crusher, and when the rock ivas crushed it would pulverize to form a coarse sand called fines, instead of the rough crushed gravel that was needed for the road subsurface.

Mr. Kiely testified that during crushing operations approximately one load of sandlike fines v as hauled away from the crusher and dumped for each load of usable crushed rock produced. When highway engineers measured the principal pile of dumped fines they estimated it contained 23 to 25% of the total production of the crusher. Additional fines were deposited around the quarry site, and some of the fines were hauled away for use by the highway department in winter sanding operations. This sand was not intended to be used and could not be used in the concrete surfacing that was placed on the road.

[367]*367As a result of the above described problems Kiely filed a claim for additional costs. The amount of the claim was based upon the highway department’s determination of 25% reject fines even though Kiely’s claim was higher. The claim included increased costs for additional crushing and blasting operations, for increased labor and machinery costs necessary to remove the lines allegedly caused by the highway department’s misleading Test Hole Log information.

The plaintiff claimed that the highway department either through neglect or faulty practice misrepresented the actual condition of the quarry site, causing him to rely on a clear statement that test holes which had been drilled to 30 feet showed the presence of solid granite. His reliance on the report resulted in great additional expense to him when the quarry did not contain 30 feet of solid granite, but did contain large amounts of conglomerated boulders interspersed with sand, and great amounts of decomposed granite which did not crush properly.

Concerning this claim the highway department contends there is no proof that Kiely relied on the report, and that the report accurately represents the condition of the quarry because two of the 8 holes or 25% of the quarry contained decomposed granite which will produce excessive fines when crushed.

The other phase of the project for which Kiely filed an additional cost claim with the highway department arose out of the rejection by highway engineers of 5,796 yards of concrete aggregate sand Kiely had purchased from Tri-City Products in Anaconda and had hauled to Butte and stockpiled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Commission v. Vaughan
470 P.2d 967 (Montana Supreme Court, 1970)
Kiely Constr. Co. v. STATE, STATE HIGHWAY COM'N
463 P.2d 888 (Montana Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
463 P.2d 888, 154 Mont. 363, 1970 Mont. LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiely-construction-co-v-state-ex-rel-state-highway-commission-mont-1970.