WEGROUP PC v. State of Oregon

885 P.2d 709, 131 Or. App. 346, 1994 Ore. App. LEXIS 1640
CourtCourt of Appeals of Oregon
DecidedNovember 16, 1994
Docket16-92-08580; CA A81256
StatusPublished
Cited by4 cases

This text of 885 P.2d 709 (WEGROUP PC v. State of Oregon) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WEGROUP PC v. State of Oregon, 885 P.2d 709, 131 Or. App. 346, 1994 Ore. App. LEXIS 1640 (Or. Ct. App. 1994).

Opinion

*348 HASELTON, J.

In this action, brought by an architectural firm seeking payment for work performed for the State of Oregon in connection with remodeling what is now the Eastern Oregon Correctional Institute (EOCI), the trial court granted the state’s motion for partial summary judgment. Plaintiff appeals from the resulting judgment pursuant to ORCP 67B, and we affirm.

In 1982, faced with a shortage of prison cells in Oregon, the legislature appropriated $9 million to convert the Eastern Oregon Hospital and Training Center into a prison. The project was to be completed in stages; initially, only the east side of the facility would be converted. The Corrections Division, as the responsible agency, hired plaintiff Wegroup PC Architects and Planners to provide architectural and related services needed for that portion of the project.

In 1987, the governor directed that the completion of the western half of the EOCI project, which would provide an additional 761 spaces, should be expedited. On March 10, 1987, the Corrections Division contracted with plaintiff to provide architectural services for the western renovation.

The western renovation contract provided that plaintiff would complete its work in four phases — a site analysis phase, a schematic design phase, a design development phase, and a construction documents phase —and would complete each phase according to an expedited and extremely rigorous schedule. 1 Plaintiff was to receive a lump sum fee of $843,100 for completing all four phases.

Plaintiff began work immediately. Between May 1987 and November 1988, plaintiff and the state entered into eight written amendments to the contract. Each amendment required plaintiff to perform services not covered by the original contract and increased plaintiffs fee accordingly.

In early 1988, the events giving rise to this litigation occurred: The state changed its mind about a portion of the west wing, Unit C, which had originally been designed solely as an activity space, and directed plaintiff to redesign the unit *349 for flexible use either as cells or as activity space. Although the parties agree that the services involved in redesigning Unit C went beyond those contemplated under the original contract, it appears that neither party attempted to negotiate or modify the contract price before those additional services were performed. Nor is there any documentation in the summary judgment record, memorializing any agreement of the parties to defer negotiation or contractual modification with respect to the Unit C redesign. The record discloses only that plaintiff complied with the request and later submitted bills for the redesign work to the state.

When the state refused to pay those bills or negotiate a price for the additional services, plaintiff brought this action. Plaintiffs claims included multiple counts of breach of contract, based on allegations that the state: (1) requested services beyond those contemplated by the written contract;

(2) refused to negotiate for those additional services;

(3) violated its duty of good faith and fair dealing by failing to draft a contract amendment regarding the additional services; and (4) violated an implied promise to pay for the additional services. 2

The state moved for summary judgment on those claims. It argued that, as a matter of law, it was not obligated to pay for the additional work because the necessary approvals to enter into a contract amendment for those additional services had never been obtained. The trial court granted the state’s motion, and plaintiff appeals the resulting ORCP 67B judgment.

Summary judgment is properly granted when the moving party establishes that there is no issue as to any material fact and that it is entitled to judgment as a matter of law. Seeborg v. General Motors Corporation, 284 Or 695, 699, 588 P2d 1100 (1978). Here, plaintiff and the state agree about the content of their contract, and further agree that the redesign of Unit C exceeded the work contemplated in that contract. We consider the legal sufficiency of plaintiffs contractual claims in light of those undisputed material facts.

*350 Plaintiff first asserts that the state breached the contract by ordering plaintiff to redesign Unit C. That conduct, plaintiff maintains, violated the state’s contractual duty to refrain from imposing extra work by revisiting and changing phases of work that had already been approved. Such a duty, plaintiff argues, derives from the phased structure of the contract, which required the state to “sign off” on plaintiffs work at the end of each phase. In plaintiffs view, adoption of that phased structure implied that the state would not request changes in work that had already been approved. 3 In addition, plaintiff reads one contractual term, which states that “[t]he Architect shall be entitled to rely upon the accuracy and completeness of the services, information, surveys and reports furnished by the Division,” as a promise by the state to adhere to its phased approvals.

Assuming, but not deciding, that the state breached some contractual duty by merely requesting the Unit C redesign, any recovery for such a breach is barred, as a matter of law, by plaintiffs own failure to comply with contractual, statutory and regulatory requirements before performing the additional work. In particular, if the state’s demand for the redesign of Unit C did, in fact, materially alter the scope and expense of plaintiffs services, plaintiff was obligated to refuse to proceed until an appropriate contract amendment had been negotiated and approved in writing by all parties. SectionB.1.02 ofthe parties’ contract provides:

“The Division reserves the right to accept or reject the Architect’s plans at the end of each phase and to require the Architect to change or modify such plans at any time prior to their acceptance. Design of bid alternatives is not considered to be a major factor in the scope of this Project. In the event alternative designs substantially change the scope of the Architect’s Contract, the Architect’s fee for such change shall be negotiated with the Division and work shall commence only after the Contract has been amended in writing and approved by all parties.” (Emphasis supplied.)

*351 That requirement accords with ORS 279.712, which provides that the Department of Administrative Services

“shall approve all professional and personal services contracts of agencies for architectural, engineering, and related services before any such contract becomes binding and before any service may be performed under the contract.” (Emphasis supplied.)

Finally, Corrections Division rules reiterate and expand on the statutory approval requirement of ORS

Related

Reedsport School District No. 105 v. Gulf Insurance
152 P.3d 988 (Court of Appeals of Oregon, 2007)
Richardson v. Guardian Life Insurance Co. of America
984 P.2d 917 (Court of Appeals of Oregon, 1999)
Fanning v. Oregon Division of State Lands
950 P.2d 353 (Court of Appeals of Oregon, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
885 P.2d 709, 131 Or. App. 346, 1994 Ore. App. LEXIS 1640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wegroup-pc-v-state-of-oregon-orctapp-1994.