Ryan v. City of New York

179 A.D. 181, 166 N.Y.S. 575, 1917 N.Y. App. Div. LEXIS 7415
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 13, 1917
StatusPublished
Cited by4 cases

This text of 179 A.D. 181 (Ryan v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryan v. City of New York, 179 A.D. 181, 166 N.Y.S. 575, 1917 N.Y. App. Div. LEXIS 7415 (N.Y. Ct. App. 1917).

Opinions

Shearn, J.:

The contract was between plaintiff’s assignor and the defendant for the construction of a public improvement, an extension of the Riverside Drive from the old viaduct over Manhattan valley (One Hundred and Thirty-fifth street) to One Hundred and Forty-fifth street. The contract was executed on or about December 7, 1903, and was fully performed. Concerning the items involved in the dismissal, the plaintiff complained that the work was needlessly delayed by the defendant, to the damage of plaintiff’s assignor; that increased cost was imposed upon the contractor due to the substitution of Portland cement in place of Rosendale cement by order of defendant’s engineer; and that the defendant wrongfully withheld moneys due on progress payments, entitling plaintiff to recover interest on such deferred payments. The damages for delay are grouped in three classes: (a) 1904; (b) 1906; and (c) 1907-8.

Taking up the 1904 delay, we find that the complaint alleges that during the performance of the work and for a period of two months and upwards including the month of July and parts of the months of June and August, 1904, the plaintiff’s firm was wrongfully delayed in the progress of the work by the directions and unauthorized interference of the defendant, arising in part from uncertainty as to plans for the east wall with reference to pipe galleries. About March 1, 1904, the city’s engineer had sent the contractor drawings [184]*184for the foundations of the east wall from One Hundred and Thirty-fifth to One Hundred and Thirty-eighth streets; but the engineer, after sending the letter, countermanded the instructions given because of uncertainty with respect to the installation of pipe galleries near the top of the east wall. Whether pipe galleries were to be constructed or not made no difference with the construction of the wall up to that point, but of course the contractor required plans for the foundation work up to that point. The plaintiff introduced a letter written by Engineer Williamson on May 20, 1904, in which reference was made to the plans for the east wall and conferences had respecting the possible use of pipe galleries near the top of the wall, in which the engineer wrote:

However, I propose to build the sewer on the wall in any case, so that you are safe in going ahead with the wall up to the bottom of the sewer. Above this level there will be some difference when we know whether to construct a pipe gallery or not. You are, therefore, authorized to go ahead with the east retaining wall as shown on the above mentioned plans, up to the bottom of the sewer.”

Small, the engineer of plaintiff’s assignor, testified that when the east wall had been finished up to the bottom pipe gallery the work was stopped for two months, awaiting the city’s decision as to the pipe galleries, and that this delay was damaging because it prevented the contractor from dumping and filling along the east wall excavated material required to be taken from other parts of the job, thus affecting several portions of the entire work as well as the work of building the east wall. Small testified that the wall was built up to the bottom of the sewer in the latter part of June or early in July, 1904, when the contractor had to stop for about two months. Later he corrected this testimony: “I say some time in August it probably reached this height, but I am not willing to say that it reached it on the 20th of August or the 3rd of September, or any particular definite time during that period. Q. But it did not reach that stage any time in July? A. I would say no.” The documentary evidence shows clearly that no concrete work had been done in this foundation up to August 5, 1904, yet the work called for a three-foot slab of concrete under the east wall. Assuming that the con[185]*185tractor was actually prevented from beginning the foundation work for the east wall until the letter of May 20, 1904, at which time concededly the contractor had the plans showing the work up to the bottom of the pipe gallery level, no delay could fairly be charged to stoppage of work after the pipe gallery level was reached in view of the fact that the contractor dic^ not even lay the bottom concrete layer until August, 1904. If the contractor had brought the work up to the pipe gallery level by the first of July and had then been stopped for two months, it would be easy to see a fair basis for the claim of prejudicial delay, but, clearly, uncertainty in August over the pipe gallery level near the top of the wall could not be a basis for a claim of two months’ delay in June, July and the early part of August of the same year, when the contractor had not up to the first week in August laid the concrete at the very base of the foundation wall. It is argued that the contractor could not proceed expeditiously with the foundation wall because the plans were withdrawn. The contractor, however, knew that the only change contemplated was with reference to that part of the wall near the top and had tracings of the plans that, according to the testimony of Andrew M. Parker, a member of the contracting firm, made it possible to proceed with the work up to the pipe gallery level. With reference to the alleged delay of two months in June, July and the early part of August, 1904, the learned trial justice was clearly right in dismissing the complaint upon the ground assigned, namely, that “ plaintiff has not only failed to show that there was delay, but he has failed to show that the whole of the delay was caused through no act of his own and through the act of the defendant. The evidence, to my mind, shows that the work proceeded and could have proceeded with the plans which were received, and I am taking the testimony of the witness Parker as my guide in this matter.”

1906 delay. The complaint alleges that by the directions and unauthorized interference of the defendant, its officers and engineers, the performance and completion of work on the east wall from One Hundred and Fortieth to One Hundred and Forty-second streets, by reason of a proposed change of plan, was delayed for a period of six months in the summer [186]*186of 1906, to the damage of plaintiff in the sum of $174,590.43. The total east wall ran for about ten blocks, or half a mile, and the stretch of the east wall involved in this claim between One Hundred and Fortieth and One Hundred and Forty-second streets, a distance of 460 feet, was about one-fifth of the length of the wall. On May 3, 1906, Mr. Williamson, the consulting engineer of the borough president, sent a letter to the contractor reading as follows:

“Dear Sirs.— Going over your work this morning, I noticed that you have begun excavating for the east retaining wall between 140th and 142nd Streets.
“ Inasmuch as plans are now before the Board of Estimate purposing to widen this part of the extension of Riverside Drive, I think it unwise to do any work at this point of your contract which may prove to be unnecessary if the changes are made.
“ This is, therefore, to request you to .do nothing further in regard to the east wall between above mentioned streets until you hear further from me in regard to the matter.”

On May 7, 1906, the secretary and treasurer of the Ryan-Parker Construction Company, which was then doing the work under the contract, wrote to Mr. Williamson an acknowledgment of this letter. No protest was made against the direction to suspend but it was suggested that, because of the delay entailed, additional moneys out of the retained percentages should be paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County Asphalt, Inc. v. State
63 Misc. 2d 329 (New York State Court of Claims, 1969)
A. H. Barbour & Son, Inc. v. State Highway Commission
433 P.2d 817 (Oregon Supreme Court, 1967)
Quinn-Meissner, Inc. v. State
268 A.D. 936 (Appellate Division of the Supreme Court of New York, 1944)
Rapid Transit Subway Construction Co. v. City of New York
129 Misc. 714 (New York Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
179 A.D. 181, 166 N.Y.S. 575, 1917 N.Y. App. Div. LEXIS 7415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryan-v-city-of-new-york-nyappdiv-1917.